Report for April 2017
- Report Date
- April 2017
Programme Manager's Commentary
A Programme Meeting was held on Wednesday 26th April. It was agreed to initiate eInvoicing for Medium Suppliers (FIN119) and Fraud Protection for Accounts Payable (FIN120) early in May 2017.
Resource changes this month have been focussed on the reduced budget requirement for eFinancials Upgrade and Migration (FIN118). This is due to the delayed start of the project which has pushed the bulk of the project into 2017/18, requirements for 2016/17 has therefore reduced from 350 days to 215 days. The project has therefor been given a red RAG status
In the Financial systems user deprovisioning project (FIN115) additional works / bug fixes were undertaken which have pushed out the timeline and increased the budget estimate to 160 days. The RAG is red due to the additional 40 days budget required to reach closure.
The revised Programme Budget is therefore now 940 days, a decrease of 125 days from the previous budget of 1065 days.
Resource Position
Forward Look
Section 2: Projects Not Started
Project Info | Programme Managers Commentary |
AP67-024 eInvoicing for medium suppliers Planning - tbc Delivery - tbc RAG Status : GREEN |
It was agreed at Programme meeting that this project would commence in May 2017. |
AP67-025 Fraud protection for Accounts Payable Planning - tbc Delivery - tbc RAG Status : GREEN |
It was agreed at Programme meeting that this project would commence in May 2017. |
Section 3: Projects in Progress
Project Info | Project Managers Commentary | ||||||||||||||
FIN108 (AP56-042) Essential enhancements (FIS) Category: Discretionary Milestones tbc - dependent on the Supplier's delivery of a successful fix. Milestones to be re-planned RAG Status : SUSPENDED |
Report by Nikki Stuart for April 2017 Project has been suspended awaiting an FPM patch being applied and signed off in DEV. Testing is currently underway in Finance for the latest patch which was released and applied to DEV. Initial testing was positive and if the patch is signed off in DEV then the project will be reopened. Next Steps
|
||||||||||||||
FIN111 (AP56-036) eExpenses enhancements Category: Discretionary Milestones RAG Status : AMBER Milestones (aligned to Revised Milestones PICCL report 7th and 21st April)
|
Report by Emma McNab for April 2017 Achievements this Period
Issues
Next Steps
AMBER - ISSUE: There is dependencies with Financial System User De-Provisioning (FIN115). Any over run of the project impacts the planned milestones aligned to the final iteration of the eExpenses project. Reprioritisation of work is being undertaken to manage this.
|
||||||||||||||
FIN115 (AP67-026) Financial systems user de-provisioning Category: Compliance Milestones - WP1
RAG Status : AMBER |
Report by Richard Bailey for April 2017 Achievements this periodWP2
Risks/Issues WP2 Next StepsWP2
AMBER: ISSUE - 40 days budget was approved by WIS and milestones revised to allow the project to be completed. Closure now on track.
|
||||||||||||||
FIN116 (AP67-022) eTime - guaranteed hours Category: Compliance Milestones
RAG Status : AMBER |
Report by Richard Bailey for April 2017 Achievements in last period
Issues / RisksNext Steps
MilestonesApproved by Project Team and Sponsor and ratified at WIS 30/03/2017 AMBER - RISK - Key Finance project team members may not be available, this is still a risk as we are in the annual leave window, especially as we approach testing, however this far any impact has been managed. |
||||||||||||||
FIN117 (AP56-054) Finance BI Improvement Category: Discretionary Milestones
RAG Status: Green |
Report by Richard Bailey for April 2017 Achievements this period
Risks
Next steps
|
||||||||||||||
FIN118 (AP56-016) eFinancials upgrade Core funded
RAG Status: Red |
Report by Chris Orrell for April 2017 Achievements in Last Period
Issues
Next Steps
RED - CHANGE - Item 3: All remaining major milestones have been changed to reflect the availability now confirmed by the vendor. Revised milestones were reviewed and approved at Key Stakeholder Meeting 18 April and was approved by WIS on 21 April. |
Section 4: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
AP67-023 eCash Core funded
|
Project withdrawn |
FIN112 (AP56-921) Finance strategic review Category : discretionary / funded |
Project Manager - Dawn Holmes Project closed 2nd August 2016 |
AP45-020 Estates & Buildings - Finance interface requirements Category: Discretionary |
Project withdrawn |
FIN114 (AP56-039) Financial documents revitalisation (Version One) Category: Discretionary |
Project Manager - Nikki Hackett Reed Project closed 2nd September 2016 |