Report for January 2017
- Report Date
- January 2017
Report compiled by Nikki Stuart (Programme Manager) for Liz Welch & Lee Hamill (Programme Owners)
Programme Manager's Commentary
The burn rate has increased for January but still remains low. This reflects the need to reduce the overall programme allocation to match revised demand and what IS and Finance can realistically deliver in the remaining months.
There is a risk that the preferred upgrade slot on November 2017 for the eFinancials upgrade will not be achievable based on supplier availability, this is being escalated within Finance senior management. The other in progress projects (FIN115, FIN116 and FIN117) are all marked as AMBER due to minor changes agreed to the milestones or budgets.
This month provided an opportunity to restart the eExpenses Enhancement work, with the remaining stories being reviewed. The iterations will now be planned and the work scheduled to start during March.
Resource Position
Forward Look
Section 2: Projects Not Started
Project Info | Programme Managers Commentary |
AP67-024 eInvoicing for medium suppliers Planning - tbc Delivery - tbc RAG Status : GREEN |
|
AP67-025 Fraud protection for Accounts Payable Planning - tbc Delivery - tbc RAG Status : GREEN |
Section 3: Projects in Progress
Project Info | Project Managers Commentary | ||||||||||||||
FIN108 (AP56-042) Essential enhancements (FIS) Category: Discretionary Milestones tbc - dependent on the Supplier's delivery of a successful fix. Milestones to be re-planned RAG Status : SUSPENDED |
Report by Nikki Stuart Project has been suspended awaiting an FPM patch being applied and signed off in DEV. Testing is currently underway in Finance for the latest patch which was released and applied to DEV. Initial testing was positive and if the patch is signed off in DEV then the project will be reopened.
Next Steps
|
||||||||||||||
FIN111 (AP56-036) eExpenses enhancements Category: Discretionary Milestones RAG Status : BLUE (suspended) |
Report by Nikki Stuart This project is now suspended until the April |
||||||||||||||
FIN115 (AP67-026) FInancial systems user de-provisioning Category: Compliance Milestones - WP1
RAG Status : AMBER |
Report by Nikki Hackett-Reed for January 2017 Achievements this periodWP1 Acceptance
Deployment
WP2 System Design
Build
Risks/IssuesWP1/WP2 NONE Next StepsWP1 Deployment
WP2 Build
Integration
|
||||||||||||||
FIN116 (AP67-022) eTime - guaranteed hours Category: Compliance Milestones Indicative revised milestones - to be approved by Project Team and Sponsor
RAG Status : AMBER |
Report by Nikki Stuart for January 2017 Achievements in last period
Issues
Next Steps
RAG Status AMBER to reflects need to replan the project with a new PM and to accommodate impact from develop conflict. |
||||||||||||||
FIN117 (AP56-054) Finance BI Improvement Category: Discretionary Milestones
RAG Status: Amber |
Reported by Duncan Stewart for January 2017 Achievements this period
Risks
Issues
Next steps
Amber RAG status reflects slippage against planned start date of Finance team's review of existing BI reports, which is due to the issues encountered with the BI reports required for the analysis. Status should revert to Green once report issues have been resolved by Service Management.
|
||||||||||||||
FIN118 (AP56-016) eFinancials upgrade Core funded Milestones: November go-live now considered unlikely. Revised milestones to be discussed 13 February with Project Sponsor.
RAG Status: AMBER |
Report by Chris Orrell for January 2016 Achievements in Last Period
Issues
Next Steps
|
Section 4: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
AP67-023 eCash Core funded
|
Project withdrawn |
FIN112 (AP56-921) Finance strategic review Category : discretionary / funded |
Project Manager - Dawn Holmes Project closed 2nd August 2016 |
AP45-020 Estates & Buildings - Finance interface requirements Category: Discretionary |
Project withdrawn |
FIN114 (AP56-039) Financial documents revitalisation (Version One) Category: Discretionary |
Project Manager - Nikki Hackett Reed Project closed 2nd September 2016 |