Report for December 2016
- Report Date
- December 2016
Report compiled by Nikki Stuart (Programme Manager) for Liz Welch & Lee Hamill (Programme Owners)
Programme Manager's Commentary
The monthly programme burn rate remains low but this is inline with the number of in progress projects and the current phase of each. This expected to ramp up significantly now that the eFinancials upgrade project is underway.
All projects are progressing well with the exception of FIN116 eTime which has experienced conflicts for the developer and the PM's unplanned extended absence, a new PM is being assigned and the development resources replanned to start mid January.
Resource Position
Forward Look
Section 2: Projects Not Started
Project Info | Programme Managers Commentary |
AP67-024 eInvoicing for medium suppliers Planning - tbc Delivery - tbc RAG Status : GREEN |
|
AP67-025 Fraud protection for Accounts Payable Planning - tbc Delivery - tbc RAG Status : GREEN |
Section 3: Projects in Progress
Project Info | Project Managers Commentary | ||||||||||||||
FIN108 (AP56-042) Essential enhancements (FIS) Category: Discretionary Milestones tbc - dependent on the Supplier's delivery of a successful fix. Milestones to be re-planned RAG Status : SUSPENDED |
Report by Nikki Stuart Project has been suspended awaiting an FPM patch being applied and signed off in DEV. Testing is currently underway in Finance for the latest patch which was released and applied to DEV. Initial testing was positive and if the patch is signed off in DEV then the project will be reopened.
Next Steps
|
||||||||||||||
FIN111 (AP56-036) eExpenses enhancements Category: Discretionary Milestones RAG Status : BLUE (suspended) |
Report by Nikki Stuart This project is now suspended until the April |
||||||||||||||
FIN115 (AP67-026) FInancial systems user de-provisioning Category: Compliance Milestones - WP1
RAG Status : GREEN |
Report by Nikki Hackett-Reed for December 2016 Achievements this periodWP1 Build/Integrate
Acceptance
WP2 System Design
WP3 De-scoped from the delivery of this project due to development/implementation complexities identified during the TO BE analysis Risks/IssuesWP1/WP2 NONE WP3 https://www.projects.ed.ac.uk/unpublished/project/fin115/risks/3 Next StepsWP1 Deployment
WP2 System Design
Build
|
||||||||||||||
FIN116 (AP67-022) eTime - guaranteed hours Category: Compliance Milestones Indicative revised milestones - to be approved by Project Team and Sponsor
RAG Status : AMBER |
Report by Nikki Stuart for December 2017 Achievements in last period
Issues
Next Steps
RAG Status AMBER to reflects need to replan the project with a new PM and to accommodate impact from develop conflict. |
||||||||||||||
FIN117 (AP56-054) Finance BI Improvement Category: Discretionary Milestones
RAG Status: Green |
Reported by Duncan Stewart for December 2016 Achievements this period
Risks
Next steps
|
||||||||||||||
FIN118 (AP56-016) eFinancials upgrade Core funded Milestones
RAG Status: Green |
Report by Chris Orrell for December 2016 Achievements in Last Period
Issues
Next Steps
|
Section 4: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
AP67-023 eCash Core funded
|
Project withdrawn |
FIN112 (AP56-921) Finance strategic review Category : discretionary / funded |
Project Manager - Dawn Holmes Project closed 2nd August 2016 |
AP45-020 Estates & Buildings - Finance interface requirements Category: Discretionary |
Project withdrawn |
FIN114 (AP56-039) Financial documents revitalisation (Version One) Category: Discretionary |
Project Manager - Nikki Hackett Reed Project closed 2nd September 2016 |