Report for October
- Report Date
- October 2016
Report compiled by Nikki Stuart (Programme Manager) for Liz Welch & Lee Hamill (Programme Owners)
Section 1: Programme Commentary, RAG and Resources Update
Programme Manager's Commentary
The monthly programme burn rate remains low but this is inline with the number of in progress projects and the current phase of each. This is expected to ramp up significantly in the next few months as the in progress projects progress and the eFinancials Upgrade project starts.
AP56-016 eFinancials Upgrade - early pre-planning discussions are underway with the project due to be officially started in November.
FIN108 Financial Systems Essential Enhancements - Key stakeholders have agreed that this project should be suspended awaiting a successful patch being applied to DEV.
FIN115 Financial Systems deprovisioning - issues with the eAuthorisation migration to the new infrastructure are being investigated.
FIN116 eTime - Planning now complete and resources secured for design and build phases.
Resource Position
Forward Look
Section 2: Projects Not Started
Project Info | Programme Managers Commentary |
AP56-016 eFinancials upgrade Core funded Planning - Oct 2016 Delivery - Jul 2017 RAG Status : GREEN |
|
AP67-023 eCash Core funded Planning - tbc Delivery - tbc RAG Status : GREEN |
|
AP67-024 eInvoicing for medium suppliers Planning - tbc Delivery - tbc RAG Status : GREEN |
|
AP67-025 Fraud protection for Accounts Payable Planning - tbc Delivery - tbc RAG Status : GREEN |
Section 3: Projects in Progress
Project Info | Project Managers Commentary | ||||||||||||||||||||||||||||||
FIN108 (AP56-042) Essential enhancements (FIS) Category: Discretionary Milestones tbc - dependent on the Supplier's delivery of a successful fix. Milestones to be re-planned RAG Status : SUSPENDED |
Report by Jill Nicoll for October 2016 Achievements in last period
Issues
Next Steps
|
||||||||||||||||||||||||||||||
FIN111 (AP56-036) eExpenses enhancements Category: Discretionary Milestones RAG Status : BLUE (suspended) |
Report by Dawn Holmes for July 2016 This project is now suspended until the end of September 2016 |
||||||||||||||||||||||||||||||
FIN115 (AP67-026) FInancial systems user de-provisioning Category: Compliance Milestones - WP1
RAG Status : AMBER |
Report by Nikki Hackett-Reed for October 2016 Achievements this period Cold Fusion 11 build complete
Code migration & Bamboo deployed
Integration test documentation created and undertaken
KPMG Review released WP2/3 Decision Point undertaken - progress with proposed approach as per Project Brief WP2/3 'AS IS' Business Analysis progressing Issues NONE Next Steps The application appears to be consuming so much memory on startup it is overloading the instance and bringing down all the Finance applications with it. From what we can see it tries to dynamically create a hierarchy of Objects + Job Codes and store those Objects in the Applications memory e.g storing over 2000 dynamically created Objects in the Applications memory. The error debug output is over 78,000 lines as a result.
WP2/3 'AS IS' Business Analysis completed Production Deployment Checklist completed Undertake WP2/WP3 scoping workshop |
||||||||||||||||||||||||||||||
FIN116 (AP67-022) eTime - guaranteed hours Category: Compliance Milestones
RAG Status : GREEN |
Report by Jill Nicoll for October 2016 Achievements in last period
Issues
Next Steps
|
||||||||||||||||||||||||||||||
FIN117 (AP56-054) Finance BI Improvement Category: Complianec Milestones
RAG Status: Amber |
Reported by Duncan Stewart for October 2016 Achievements this period Review of progress to date on JIRAs transferred from FIN109 & FIN112
Review of other proposed scope items and priority/order. Preliminary analysis undertaken on the following proposed items to determine if these can be delivered as part of the project:
Project brief drafted
Risks
Next steps
Achieving the above steps should return the project to Green (currently reporting Amber due to unconfirmed scope items). |
Section 4: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
FIN112 (AP56-921) Finance strategic review Category : discretionary / funded |
Project Manager - Dawn Holmes Project closed 2nd August 2016 |
AP45-020 Estates & Buildings - Finance interface requirements Category: Discretionary |
Project withdrawn |
FIN114 (AP56-039) Financial documents revitalisation (Version One) Category: Discretionary |
Project Manager - Nikki Hackett Reed Project closed 2nd September 2016 |