Report for September 2016
- Report Date
- September 2016
Report compiled by Nikki Stuart (Programme Manager) for Liz Welch & Lee Hamill (Programme Owners)
Section 1: Programme Commentary, RAG and Resources Update
Section 2: Projects Not Started
Section 3: Projects In Progress
Section 4: Closed or Withdrawn Projects
Section 1: Programme Commentary, RAG and Resources Update
Programme Manager's Commentary
Project AP56-054 FInance BI Improvement hasn't yet formally started, but advantage has been taken of specialist BI resource availability in the Software Development team to make a head start on some of the required improvements identified during FIN112 FInance Strategic Review. This work is being temporarily coded against the programme code until the project formally opens, resulting in s short-term defecit on the FINP01 code.
FIN116 eTime Guaranteed Hours is showing a large defecit as currently the project has brought forward 150 days from 16/17. Agreement on how best to progress this work is still to be formally agreed.
Resource Position
Forward Look
Section 2: Projects Not Started
Project Info | Programme Managers Commentary |
AP56-016 eFinancials upgrade Core funded Planning - Oct 2016 Delivery - Jul 2017 RAG Status : GREEN | |
AP56-054 Finance BI improvement Core funded Planning - tbc Delivery - tbc RAG Status : GREEN | |
AP67-023 eCash Core funded Planning - tbc Delivery - tbc RAG Status : GREEN | |
AP67-024 eInvoicing for medium suppliers Planning - tbc Delivery - tbc RAG Status : GREEN | |
AP67-025 Fraud protection for Accounts Payable Planning - tbc Delivery - tbc RAG Status : GREEN |
Section 3: Projects in Progress
Project Info | Project Managers Commentary | ||||||||||||
FIN108 (AP56-042) Essential enhancements (FIS) Category: Discretionary Milestones tbc - dependent on the Supplier's delivery of a successful fix. Milestones to be re-planned RAG Status : RED | Report by Jill Nicoll for September 2016 Achievements in last period
Issues
Next Steps
| ||||||||||||
FIN111 (AP56-036) eExpenses enhancements Category: Discretionary Milestones RAG Status : BLUE (suspended) | Report by Dawn Holmes for July 2016 This project is now suspended until the end of September 2016 | ||||||||||||
FIN115 (AP67-026) FInancial systems user de-provisioning Category: Compliance Milestones - WP1
RAG Status : GREEN | Report by Nikki Hackett-Reed for September 2016 Achievements this period - WP1WP1 3Point Estimate Planning completed Business Requirements Document signed off Technical Architecture Document completed CF11 build commenced Business Analyst assigned Issues - WP1NONE Next Steps - WP1WP2 'AS IS' Business Analysis to commence CF11 build completed Code migration & Bamboo deployed Production Depolyment Checklist completed Peer Testing completed AS IS Analysis completed KPMG Review WP2 decission point | ||||||||||||
FIN116 (AP67-022) eTime - guaranteed hours Category: Compliance Milestones tbc - pending confirmation of estimates RAG Status : AMBER | Report by Jill Nicoll for September 2016 Achievements in last period
Issues
Next Steps
|
Section 4: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
FIN112 (AP56-921) Finance strategic review Category : discretionary / funded | Project Manager - Dawn Holmes Project closed 2nd August 2016 |
AP45-020 Estates & Buildings - Finance interface requirements Category: | Project withdrawn |
FIN114 (AP56-039) Financial documents revitalisation (Version One) Category: Discretionary | Project Manager - Nikki Hackett Reed Project closed 2nd September 2016 |