Report for September 2014

Report Date
September 2014

Report compiled by Dawn Nicholls (Programme Manager) for Liz Welch (Programme Owner)

Section 1: Programme Commentary, RAG and Resources Update

Section 2: Projects Not Started

Section 3: Projects In Progress

Section 4: Closed or Withdrawn Projects

Section 1: Programme Commentary, RAG and Resources Update   

Commentary

FIN086 - WPM files are still not being received via the payment gateway. This has been ongoing for 3 months now so we may have to consider suspending project until this is resolved.

FIN098 - insufficient budget to cover the extensive requirements. Need to agree additional funding and/or reduce scope.

FIN081 - Finance resource conflicts from sickness/leave are hampering progress. Should consider suspending until key resource returns from sick leave.

FIN097 - Late change of scope which has delayed UAT sign-off.  Additional UAT and re-planning required.

FIN101 - Scope not agreed re eAuthorisations. Phase 2 project to be considered.

  

 

 

Section 2: Projects Not Started

 

Project InfoProgramme Managers Commentary

AP34-016

Student Fees - Interest charging on invoices

Core funded

Planning - January 2015

Delivery - June 2015

RAG Status : GREEN

Plan

 

Dependencies

AP45-018

Supporting scan & destroy policy using Serengeti

Core funded

Planning - January 2015

Delivery - June 2015

RAG Status : GREEN

Plan

 

Dependencies

AP45-019

Financial reporting changes for FRS102

Core funded

Planning - Feb 2015

Delivery - July 2015

RAG Status : GREEN

Plan

 

Dependencies

AP45-020

Estates & Buildings - Finance interface requirements

Core funded

Planning - November 2014

Delivery - May 2015

RAG Status : GREEN

Plan

 

Dependencies

 

Section 3: Projects in Progress

 

Project InfoProject Managers Commentary

FIN081 (12-024)

Document Management for Finance Applications

Category: Discretionary

Milestones

 

Target dateTitle
TBCBusiness Analysis
TBCDeploy to Development
TBCDocument Scanning Activity Completed
TBCDeploy to Test
TBCDeploy to Live
TBCClosure

RAG Status : AMBER

Report by Karen Stirling forSeptember 2014

Achievements in last period

  • Meeting held with DDSR and FINANCE at end of August to review demonstrators for the Finance Directorate document folders on Serengeti, this being based on the previously scanned documentation by DDSR and attributes provided by FInance
  • It was confirmed by Finance that they would prefer the folder structure to be created in same format for both backlog and future scanned documentation - action to be completed by Finance to identify folder type and breakdown each folder into tabs
  • Finance attendees advised that they will require additional resource from FTP to assist with this exercise, however they committed to complete this exercise in 2 weeks but expected additional resource would be required due to other committments on this basis it was agreed for them to confirm progress by end of the 2 week period - 15th September
  • DDSR to be provided with sample files once tab exercise completed
  • Further attribute details provided by Finance for a further 3 folders which have now been added to sample files

 

Issues

  • PM on special leave until 15th September
  • Due to other workload committments / annual leave in Finance project team no progress has been made on completing the folder exercise this has been raised to the Business PM to establish when work can commence / complete. Update provided from Business PM, one of resource is now on long term leave.
  • Project milestones cannot be reviewed and agreed until confirmation of Finance activity has been advised, this is to be discussed with Programme Manager and Project Sponsor should project be 'suspended' for a short period to allow resource to return and undertake tab exercise before recommencing project

 

Next Steps

  • Commence / complete folder type exercise
  • Review and agree new milestones
  • Replan activity for document scanning with DDSR

 

The project status is currently AMBER/ RED due to no progress having been completed by Finance to identify folder types and no current / agreed milestones

FIN086 (AP23-004)

ePay Reconciliation

Category:  Compliance

Milestones

 

22-Oct-2014Build Complete
29-Oct-2014Integration Test Signed Off
27-Nov-2014Acceptance Sign Off
02-Dec-2014Deliver
16-Dec-2014DSOR
12-Jan-2015Project Close

 RAG Status:  AMBER

Report by Sally Hayward for September 2014

Achievements in this Reporting Period

  • The original business contact, Joyce Smart has retired and the contact from within the business is now Gordon Forbes.
  • New timescales have been produced to reflect the ongoing issues with getting the WPM file. 

Issues

  • The project cannot continue any further until IS have the WPM file. 

Next Steps

  • Project Manager to continue to work with the business to try to get the WPM file so that the development can continue.
  • Complete development of the build once this is recieved.

 

Project is currently AMBER as we remain unable to continue the work without the WPM file.

FIN094

SAAS/SLC Reconciliation

Category: Compliance

Milestones

Target dateTitle
08-Oct-2014Acceptance sign-off
15-Jan-2015Go-live
04-Feb-2015Deployment sign-off
18-Feb-2015Closure

 RAG Status: GREEN

Report by Dawn Nicholls for September 2014  

Achievements this period

  • None (due to resource conflicts from higher priority work and annual leave in both Finance and Project Services) 

Issues

  • Resource conflicts from higher priority work and annual leave in both Finance and Project Services have hindered progress.  Overall project delivery dates are not affected so the project is still being reported on green despite this delay
  • Integration testing has not taken place due to lack of test data. It has been agreed to replace this step with additional testing alongside UAT once further test data is available

Next steps

  • Organise UAT by FIS, Income Section, SFS and Financial Accounts 

  

Full details on project activities can be seen in the Project Journal

FIN097

Archiving for eFinancials

Category:  Funded

Milestones 

 

13-Oct-2014Deployment Sign off Review
20-Oct-2014Close
 

  RAG Status :  AMBER

Report by Morna Findlay for September 2014

 Achievements this period 

  • ABS worked with IS Apps resources to create BOXi universe

  • User acceptance testing completed

  • Acceptance sign off and delivery achieved.

  • New budget and milestones agreed by project manager, project sponsor, programme manager and portfolio manager

Issues

  • New budget to be approved by WIS 
  • Acceptance and delivery milestones were missed - remaining milestones must be agreed with project sponsor.

Next Steps

  • FIS to test purging and archiving of one subledger in LIVE

  • FIS to complete documentation for FIS users

  • Deployment sigoff

  • Close
  •  

The project  is AMBER  as new milestones have to be agreed with the project sponsor.

FIN098

eExpenses Replacement

Category:  Discretionary

Milestones

 

Target dateTitle
21-Nov-2014End of Development
19-Dec-2014End of Maintenance
16-Jan-2015Closure

 RAG Status:  RED

Report by Dawn Nicholls for September 2014

Achievements this period

  • Two more development iterations have been completed.  Details of functionality delivered can be seen on the project website at iteration 1.7 and iteration 1.8
  • eAuthorisation changes deployed to Test environment

Issues

  • Although the project has made good progress through the mandatory User Stories, requirements have been much more complex than originally anticipated and additional requirements are continuously being added to the backlog.  The result is that there are far more requirements that the project can cover within the allocated budget.  This has been highlighted to the Product Owner who is reviewing and re-prioritising the backlog.
  • The remaining 3 development iterations will be required to develop basic Serengti functionality (which has been been prioritised as mandatory by the Project Sponsor) so further core eExpenses functionality development will not be possible within the current budget.

Next steps

  • Agree additional funding (or reduction of scope)
  • UAT of eAuthorisations changes
  • 3 further development/testing iterations
  • User Group meeting to demonstrate development to-date for feedback 

 

Further details on project activities can be seen in the Project Journal

FIN099

Essential Enhancements for Finance Applications 2014/15

Category: Disctretionary

Milestones

 

Target dateTitle
17-Oct-2014Work Package 1 Delivered
31-Oct-2014Workpackage 2 Specified
12-Dec-2014Work Package 2 Delivered
16-Jan-2015Work Package 3 Specified
27-Feb-2015Work Package 3 Delivered
13-Mar-2015Work Package 4 Specified
24-Apr-2015Work Package 4 Delivered
08-May-2015Work Package 5 Specified
17-Jul-2015Work Package 5 Delivered
31-Jul-2015Project Closure
 RAG Status: GREEN

Report by Stephanie Ruthven for September 2014

Achievements in Last Period

  • Batch 1 of must-have enhancements started, along with others
  • Continuation of carried over tasks from FIN093

Issues

  • To take advantage of the available resource in the Development teams, more tasks are currently on the go than originally scheduled.

Next Steps

  • Complete Batch 1 and FIN093 carry-over tasks

FIN100

ABS Systems Security Patching for Java 7

Category: Funded

Milestones

 

Target dateTitle
17-Oct-2014Deployment
24-Oct-2014Completion

 RAG Status: GREEN

Report by Ben Armstrong for September 2014

 

Achievements in Last Period
  • Project Brief signed off
  • Patches successfully implemented and tested in eFinancials Development and Test environments
  • Build stage of project signed off
  • Implementation plan agreed for deploying patches to eFinancials Live environment

Issues

  • A couple of issues arose during user testing which have been fully resolved, following consultation with IS Applications and the external supplier ABS

Next Steps

  • Project stakeholders to sign off Acceptance stage of project
  • Patches to be deployed to eFinancials Live environment
  • Project team to sign off Deployment
  • Project to be submitted for closure

 

FIN101

SSO/Launchpad Phase 2

Category: Discretionary

Milestones

 

30-Sep-2014End of Planning
 

RAG Status : RED

 

 

Report by Morna Findlay for September 2014 

Achievements this period 

  • Draft project brief, plan, estimate and milestones circulated.
  • R&D into bulk load of existing FIS users into OpenAM and OpenAm groups carried out.
  • Change of scope to split project into two projects  proposed.

 Issues

  •  Project change of scope, brief, plan, estimate and milestones not approved.

 

Next Steps

  • Agreement and approval of project brief, plan, milestones and estimate.
  • Deploy ABS applications into DEV
  • Test bulk load of existing users in DEV
  • Sign off Build and proceed to UAT.

 

The project status is RED as end of planning has not been achieved.

 

Section 4: Closed or Withdrawn Projects

 

Project InfoProject Managers Commentary