Report for September 2014
- Report Date
- September 2014
Report compiled by Dawn Nicholls (Programme Manager) for Liz Welch (Programme Owner)
Section 1: Programme Commentary, RAG and Resources Update
Section 2: Projects Not Started
Section 3: Projects In Progress
Section 4: Closed or Withdrawn Projects
Section 1: Programme Commentary, RAG and Resources Update
Commentary
FIN086 - WPM files are still not being received via the payment gateway. This has been ongoing for 3 months now so we may have to consider suspending project until this is resolved.
FIN098 - insufficient budget to cover the extensive requirements. Need to agree additional funding and/or reduce scope.
FIN081 - Finance resource conflicts from sickness/leave are hampering progress. Should consider suspending until key resource returns from sick leave.
FIN097 - Late change of scope which has delayed UAT sign-off. Additional UAT and re-planning required.
FIN101 - Scope not agreed re eAuthorisations. Phase 2 project to be considered.
Section 2: Projects Not Started
Project Info | Programme Managers Commentary |
AP34-016 Student Fees - Interest charging on invoices Core funded Planning - January 2015 Delivery - June 2015 RAG Status : GREEN | Plan
Dependencies |
AP45-018 Supporting scan & destroy policy using Serengeti Core funded Planning - January 2015 Delivery - June 2015 RAG Status : GREEN | Plan
Dependencies |
AP45-019 Financial reporting changes for FRS102 Core funded Planning - Feb 2015 Delivery - July 2015 RAG Status : GREEN | Plan
Dependencies |
AP45-020 Estates & Buildings - Finance interface requirements Core funded Planning - November 2014 Delivery - May 2015 RAG Status : GREEN | Plan
Dependencies |
Section 3: Projects in Progress
Project Info | Project Managers Commentary | ||||||||||||||||||||||
FIN081 (12-024) Document Management for Finance Applications Category: Discretionary Milestones
RAG Status : AMBER | Report by Karen Stirling forSeptember 2014 Achievements in last period
Issues
Next Steps
The project status is currently AMBER/ RED due to no progress having been completed by Finance to identify folder types and no current / agreed milestones | ||||||||||||||||||||||
FIN086 (AP23-004) ePay Reconciliation Category: Compliance Milestones
RAG Status: AMBER | Report by Sally Hayward for September 2014 Achievements in this Reporting Period
Issues
Next Steps
Project is currently AMBER as we remain unable to continue the work without the WPM file. | ||||||||||||||||||||||
FIN094 SAAS/SLC Reconciliation Category: Compliance Milestones
RAG Status: GREEN | Report by Dawn Nicholls for September 2014 Achievements this period
Issues
Next steps
Full details on project activities can be seen in the Project Journal | ||||||||||||||||||||||
FIN097 Archiving for eFinancials Category: Funded Milestones | Report by Morna Findlay for September 2014 Achievements this period
Issues
Next Steps
The project is AMBER as new milestones have to be agreed with the project sponsor. | ||||||||||||||||||||||
FIN098 eExpenses Replacement Category: Discretionary Milestones
RAG Status: RED | Report by Dawn Nicholls for September 2014 Achievements this period
Issues
Next steps
Further details on project activities can be seen in the Project Journal | ||||||||||||||||||||||
FIN099 Essential Enhancements for Finance Applications 2014/15 Category: Disctretionary Milestones
| Report by Stephanie Ruthven for September 2014 Achievements in Last Period
Issues
Next Steps
| ||||||||||||||||||||||
FIN100 ABS Systems Security Patching for Java 7 Category: Funded Milestones
RAG Status: GREEN | Report by Ben Armstrong for September 2014
Achievements in Last Period
Issues
Next Steps
| ||||||||||||||||||||||
FIN101SSO/Launchpad Phase 2 Category: Discretionary Milestones
RAG Status : RED
| Report by Morna Findlay for September 2014 Achievements this period
Issues
Next Steps
The project status is RED as end of planning has not been achieved. |
Section 4: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
|