Report for August 2014
- Report Date
- August 2014
Report compiled by Dawn Nicholls (Programme Manager) for Liz Welch (Programme Owner)
Section 1: Programme Commentary, RAG and Resources Update
Section 2: Projects Not Started
Section 3: Projects In Progress
Section 4: Closed or Withdrawn Projects
Section 1: Programme Commentary, RAG and Resources Update
Commentary
FIN081 - Project has been delayed by Serengeti upgrade project preventing access to Dev & Test environments
FIN086 - Issues obtaining test files from WPM. Change of Project Manager. Replanning required following resource conflict with RMAS.
FIN094 - Concerns raised by Income Section about impact on Financial procedures
FIN097 - Budget sourcing not agreed
FIN099 - Project started this month
FIN100 - Project brought forward to start this month to install security patches prior to desktop rollout in October
FIN101 - Project started this month as planned
Section 2: Projects Not Started
Project Info | Programme Managers Commentary |
AP34-016 Student Fees - Interest charging on invoices Core funded Planning - January 2015 Delivery - June 2015 RAG Status : GREEN | Plan
Dependencies |
AP45-018 Supporting scan & destroy policy using Serengeti Core funded Planning - January 2015 Delivery - June 2015 RAG Status : GREEN | Plan
Dependencies |
AP45-019 Financial reporting changes for FRS102 Core funded Planning - Feb 2015 Delivery - July 2015 RAG Status : GREEN | Plan
Dependencies |
AP45-020 Estates & Buildings - Finance interface requirements Core funded Planning - November 2014 Delivery - May 2015 RAG Status : GREEN | Plan
Dependencies |
Section 3: Projects in Progress
Project Info | Project Managers Commentary | ||||||||||||||
FIN081 (12-024) Document Management for Finance Applications Category: Discretionary Milestones
RAG Status : AMBER | Report by Karen Stirling for August 2014 Achievements this periodIssues
Next steps
Project is on AMBER due to the delays from the Serengeti project, which have prevent the project from re-planning | ||||||||||||||
FIN086 (AP23-004) ePay Reconciliation Category: Compliance Milestones
RAG Status: AMBER |
Report by Sally Hayward for August 2014 Achievements in this Reporting Period
Issues
Next Steps
Project is AMBER as the PM has just been asked to cover the project. The plan and budget seem to be on track but this has yet to be confirmed with the business and the WPM file that was reported as outstanding during the previous reporting period is still outstanding. Project will remain amber until the PM has met with the customer and project team to confirm the status. | ||||||||||||||
FIN094 SAAS/SLC Reconciliation Category: Compliance Milestones
RAG Status: AMBER | Report by Dawn Nicholls for August 2014Achievements this period
Issues
Next steps
Full details on project activities can be seen in the Project Journal | ||||||||||||||
FIN097 Archiving for eFinancials Category: Funded MilestonesNot agreed. RAG Status : RED | Report by Morna Findlay for August 2014Achievements this period
Issues
Next Steps
The project is RED as a new budget and milestones have not yet been approved. | ||||||||||||||
FIN098 eExpenses Replacement Category: Discretionary Milestones
RAG Status: GREEN | Report by Dawn Nicholls for August 2014Achievements this period
Issues
Next steps
Further details on project activities can be seen in the Project Journal | ||||||||||||||
FIN099 Essential Enhancements for Finance Applications 2014/15 Category: Disctretionary Milestones
| Report by Stephanie Ruthven for August 2014 Achievements in Last Period
Issues
Next Steps
| ||||||||||||||
FIN100 ABS Systems Security Patching for Java 7 Category: Funded Milestones
RAG Status: GREEN | Report by Ben Armstrong for August 2014 Achievements in Last Period
Issues
Next Steps
| ||||||||||||||
FIN101SSO/Launchpad Phase 2 Category: Discretionary Milestones
RAG Status : GREEN
| Report by Morna Findlay for August 2014 Achievements this period
Issues
Next Steps
|
Section 4: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
|