Report for August 2014

Report Date
August 2014

Report compiled by Dawn Nicholls (Programme Manager) for Liz Welch (Programme Owner)

Section 1: Programme Commentary, RAG and Resources Update

Section 2: Projects Not Started

Section 3: Projects In Progress

Section 4: Closed or Withdrawn Projects

Section 1: Programme Commentary, RAG and Resources Update   

Commentary

FIN081 - Project has been delayed by Serengeti upgrade project preventing access to Dev & Test environments

FIN086 - Issues obtaining test files from WPM. Change of Project Manager. Replanning required following resource conflict with RMAS.

FIN094 - Concerns raised by Income Section about impact on Financial procedures

FIN097 - Budget sourcing not agreed

FIN099 - Project started this month

FIN100 - Project brought forward to start this month to install security patches prior to desktop rollout in October

FIN101 - Project started this month as planned

  

 

 

 

 

Section 2: Projects Not Started

 

Project InfoProgramme Managers Commentary

AP34-016

Student Fees - Interest charging on invoices

Core funded

Planning - January 2015

Delivery - June 2015

RAG Status : GREEN

Plan

 

Dependencies

AP45-018

Supporting scan & destroy policy using Serengeti

Core funded

Planning - January 2015

Delivery - June 2015

RAG Status : GREEN

Plan

 

Dependencies

AP45-019

Financial reporting changes for FRS102

Core funded

Planning - Feb 2015

Delivery - July 2015

RAG Status : GREEN

Plan

 

Dependencies

AP45-020

Estates & Buildings - Finance interface requirements

Core funded

Planning - November 2014

Delivery - May 2015

RAG Status : GREEN

Plan

 

Dependencies

 

Section 3: Projects in Progress

 

Project InfoProject Managers Commentary

FIN081 (12-024)

Document Management for Finance Applications

Category: Discretionary

Milestones

 

Target dateTitle
25-Jul-2014Business Analysis
25-Jul-2014Deploy to Development
12-Sep-2014Document Scanning Activity Completed
26-Sep-2014Deploy to Test
17-Oct-2014Deploy to Live
31-Oct-2014Closure

RAG Status : AMBER

Report by Karen Stirling for August 2014

Achievements this period

  •  

Issues

  • Delays caused by the Serengeti upgrade project
  • Project Manager on special leave

Next steps

  • Agree revised timeline 

 

Project is on AMBER due to the delays from the Serengeti project, which have prevent the project from re-planning

FIN086 (AP23-004)

ePay Reconciliation

Category:  Compliance

Milestones

 

17-Sep-2014Build Complete
06-Oct-2014Integration Test Signed Off
27-Oct-2014Acceptance Sign Off
05-Nov-2014Deliver
12-Nov-2014DSOR
19-Nov-2014Project Close

 RAG Status:  AMBER

 

 

Report by Sally Hayward for August 2014

Achievements in this Reporting Period

  • Due to workload and illness, a new PM has been asked to cover this project. 

Issues

  • Still awaiting WPM file  - PM to follow up. 

Next Steps

  • PM to meet with the business.
  • PM to chase up the WPM file.
  • Complete build.

 

Project is AMBER as  the PM has just been asked to cover the project. The plan and budget seem to be on track but this has yet to be confirmed with the business and the WPM file that was reported as outstanding during the previous reporting period is still outstanding. Project will remain amber until the PM has met with the customer and project team to confirm the status. 

FIN094

SAAS/SLC Reconciliation

Category: Compliance

Milestones

Target dateTitle
10-Sep-2014Integration sign-off
08-Oct-2014Acceptance sign-off
15-Jan-2015Go-live
04-Feb-2015Deployment sign-off
18-Feb-2015Closure

 RAG Status: AMBER

Report by Dawn Nicholls for August 2014

Achievements this period

  • Software build and peer review has been successfully completed
  • Application has been deployed to the Test environment ready for integration testing

Issues

  • Concerns have been raised by Income Section about the impact on current reconciliation processes. This has been escalated to the FIS Business Lead. The project has been placed on AMBER status until this is resolved internally by Finance.
  • Integration testing has been delayed due to resource conflicts in Applications Management with higher priority support tasks. This has now been replanned.

Next steps

  • Integration testing
  • UAT by FIS, Income Section, SFS and Financial Accounts 

 

Full details on project activities can be seen in the Project Journal

FIN097

Archiving for eFinancials

Category:  Funded

Milestones 

 

Not agreed. 

 RAG Status :  RED

Report by Morna Findlay for August 2014

Achievements this period

  • Peer review completed.
  • Implementation plan completed.
  • TAD completed.
  • Build review achieved.
  • TEST deployment carried out and TEST made available to business.
  • Arrangements made for ABS resource to work with IS Applications on BI deliverables in September

 

Issues

  • Revised plan and funding still to be agreed with Project Sponsor  - project reported on RED until this is agreed 
  • FIS business lead unavailable in mid-September may make October delivery unachievable
  • No sign off criteria from business  for reporting delierables

Next Steps

  • Carry out and sign off User acceptance testing ( purging and archiving)
  • Facilitate BI work by ABS resource
  • Agree budget and set new dates for remaining milestones

 

 

The project  is RED as a new budget and milestones have not yet been approved.

FIN098

eExpenses Replacement

Category:  Discretionary

Milestones

 

Target dateTitle
21-Nov-2014End of Development
19-Dec-2014End of Maintenance
16-Jan-2015Closure

 RAG Status:  GREEN

Report by Dawn Nicholls for August 2014

Achievements this period

  • Two more development iterations have been completed.  Details of functionality delivered can be seen on the project website at iteration 1.5 and iteration 1.6
  • eAuthorisations build has completed.

Issues

  • Insufficient business input on requirement details.  This is being addressed by scheduling meetings with FIS and ABS to review requirements in more detail
  • Issues on the Serengeti upgrade project have delayed access to the Dev/Test Serengeti environments.  This has resulted in the Serengeti-related User Stories being delayed to later in the project.

Next steps

  • Clarifications of requirements with FIS/ABS
  • Deployment of eAuthorisations changes to Test environment
  • Further development iterations
  • User Group meeting to demonstrate development to-date for feedback 

  

Further details on project activities can be seen in the Project Journal

FIN099

Essential Enhancements for Finance Applications 2014/15

Category: Disctretionary

Milestones

Target dateTitle
05-Sept-2014Prioritisation of Work Packages Complete
17-Jul-2015Last Work Package Delivered
31-Jul-2015Project Closure
 RAG Status: GREEN

Report by Stephanie Ruthven for August 2014

Achievements in Last Period

  • List gathered of ehancements in scope
  • List prioritised by Liz Welch
  • Enhancements added to Jira
  • Continuation of carried over tasks from FIN093

Issues

  • None

Next Steps

  • Prioritse enhancements
  • Sign off Project Brief

FIN100

ABS Systems Security Patching for Java 7

Category: Funded

Milestones

Target dateTitle
29-Aug-2014Planning
08-Sep-2014Build
19-Sep-2014Acceptance
25-Sep-2014Deployment
30-Sep-2014Completion
 

 RAG Status: GREEN

Report by Ben Armstrong for August 2014
 
Achievements in Last Period
  • WIS approved project start on 22nd August;
  • Engaged supplier (ABS) to carry out work in Dev environment, working with Dev Tech
  • Project Brief drafted and circulated to project stakeholders

Issues

  • None noted

Next Steps

  • Project stakeholders to sign off Project Brief
  • Updates to be completed in Dev and replicated in Test and Live environments
  • User testing to confirm acceptance
  • Plan final deployment and completion

FIN101

SSO/Launchpad Phase 2

Category: Discretionary

Milestones

19-Sep-201419-Sep-2014End of Planning

 

RAG Status : GREEN

 

 

Report by Morna Findlay for August 2014

Achievements this period

  • Project team identified
  • Initial kickoff meeting held.
  • Draft project brief circulated
  • Initial investigations into bulk-load of Finance users into OpenAm carried out

 

Issues

  • None

 

Next Steps

  • Agreement and approval of project bried, plan and estimate.

 

Section 4: Closed or Withdrawn Projects

 

Project InfoProject Managers Commentary