Report for May 2014
- Report Date
- May 2014
Report compiled by Rhian Davies (IS Apps Programme Manager) for Liz Welch (Programme Owner)
Section One: Programme Commentary, and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, and Resources Update
Section Two: Projects Not Started
Project Info | Programme Managers Commentary |
AP34 Student Fees - Interest Charging on Invoices Compliance Planning - September 2014 Delivery - tbc RAG Status - GREEN | Plan
Dependencies Need to get decision from Fee Strategy Group which meets quarterly - FIS following up on status, but agreed that the project will not start until next year now as FIS resources are allocated to other projects. |
Section Three: Projects in Progress
Project Info | Project Managers Commentary | ||||||||||||||||
FIN081 (12-024) Document Management for Finance Applications Category: Discretionary Milestones (to be reviewed and agreed)
RAG Status : AMBER | Report by Karen Stirling for May 2014 Achievements in Last period
Issues
Next Steps
The project status AMBER due to business documentation details not finalised, impact of change in resource and milestones to be revised. | ||||||||||||||||
FIN085 (AP01-008) eTime Phase 3
Category: Compliance
Milestones
RAG Status: GREEN | Report by Jill Nicoll for May 2014 Achievements in last period: Release 6:
HSS-funded enhancement:
Closure:
Issues: Two weeks of post-deployment support was provided by the project team. However, two post-deployment issues were raised at the end of this two-week period. Additional resources have been requested, to address these issues. The Deployment Sign-off Review and Closure milestones have been extended, by a few days, to accommodate this work. The UAT testing Risks have been closed, but the project team remains concerned that the Research regression testing, which did not start until the final week of the UAT stage, may have been inadequate. Next Steps: Closure:
| ||||||||||||||||
FIN086 (AP23-004) ePay Reconciliation
Category: Compliance
RAG Status: AMBER
| Report by Louise Heathcote for May 2014 Achievements in this Reporting Period
Issues
Next Steps
| ||||||||||||||||
FIN087 (23-058) Credit Note/Sales Invoice Interface Changes Category: Discretionary Milestones
RAG Status: GREEN | Report by Dawn Nicholls for May 2014 Achievements this period
Issues
Next steps
Full details on project activities can be seen in the Project Journal | ||||||||||||||||
FIN088 (AP12-017) ERA Decommissioning
Category: Compliance
Milestones
RAG Status: AMBER | Report by Louise Heathcote for May 2014
Report Date: May 2014
| ||||||||||||||||
FIN089 (34-004) eAuthorisations Migration
Category: Compliance & Funded
Milestones
RAG Status: GREEN | Report by Jill Nicoll for May 2014 Achievements in last period: Phase 4: Batch 1:
Batch 2:
Batch 3:
Batch 4:
Issues: Progress on the Build stage for Phase 4, batch 4 has been delayed, by unplanned effort required to address:
The revised release date for UAT is 3rd June. This will reduce the batch 4 UAT stage to 10 days duration 8 working days). Progress on the Phase 4, batch 4 change to the BI Universe has been delayed by the Developer's inability to gain access and authentication permission to the Dev BI environment. Thesa issues are ongoing, and point to a weakness in the ISA procedures for gaining BI access. Next Steps: Phase 4: Batch 4:
| ||||||||||||||||
FIN093 Essential Enhancements for Finance Applications Compliance Milestones
RAG Status: AMBER | Report by Steph Ruthven for May 2014Achievements in Last Period
Issues
Next Steps
| ||||||||||||||||
FIN094 SAAS/SLC Reconciliation Compliance Milestones
RAG Status - GREEN | Report by Dawn Nicholls for May 2014Achievements this period
Issues
Next steps
Full details on project activities can be seen in the Project Journal | ||||||||||||||||
Local Implementation of SSO and Launchpad Discretionary
Milestones
These will be reviewed ( see issues - over)
The project status is AMBER pending review of project milestones.
| Report by Morna Findlay for May 2014Achievements this period
Investigations by IS Apps and FIS of Launchpad functionality in DEV. Report on shibboleth integration indicated this approach should not be continued. Successful integration of launchpad and cosign Build review approved
Issues
Unavailability of key devtech and FIS resources in July require project to be re-planned.
Next Steps
Project re-estimate, re-plan and confirmation of deliverables. FIS to provide benchmarking information in order to assess impact of Launchpad on eFinancials performance. Launchpad to be implemented in TEST. UAT to complete
| ||||||||||||||||
FIN096 eInvoicing
Category: Funded
Milestones
RAG Status: GREEN | Report by Jill Nicoll for May 2014 Achievements in last period: Finance: Planning:
ISA Planning:
System Design:
Build:
Issues: The project plan required that both the ABS CIBR and the Office Depot server directory & sample files would be available at the start of the ISA Build on 26-May. None of these was in place. The delay to these prerequisites risk the project's ability to deliver the Build stage by its target date of 16-June. The Brief estimates assumed that Finance and ABS would provide and configure the CIBR. Consequently, no ISA estimate was included for this work. However, the Business Area manager has asked ISA to participate in the application of the Dev CIBR, and to apply and configure the Test and Live CIBRs. The project budget does not cover this additional scope. Once the Dev CIBR is in place, estimates for ISA either to continue the support, or to take over the work, in Test and Live will be sought. The resulting increase will be then be notified to the Project Sponsor and Programme Manager, for a decision on how to proceed.
Next Steps: Office Depot:
Finance & ABS: Build:
Integration:
ISA: Build:
Integration:
| ||||||||||||||||
FIN097 Archiving for eFinancials
Category: Funded
Milestones
These are not yet approved.
RAG Status: AMBER | Achievements this period
Project brief, estimate, plan and milestones agreed with project sponsor Research and development work carried out by project team with ABS consultants Rollback plan drafted Analysis review drafted
Issues
Project brief not yet approved by WIS
Next Steps
Achieve project brief approval Complete analysis review Confirm scope with project sponsor Re-estimate and re-plan project Confirm project milestones
The project is AMBER pending approval of the project brief | ||||||||||||||||
FIN098 eExpenses Replacement
Category: Discretionary
Milestones
RAG Status: GREEN | Report by Dawn Nicholls for May 2014Achievements this period
Issues
Next steps
Further details on project activities can be seen in the Project Journal
|
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
FIN078 eFin Journal Auto Upload (JAMS) Category : Discretionary | Report by Dawn Nicholls This project was closed on 4th October 2013 Please see the completion report for further information |
FIN079 LEAN Review of Financial Systems Category : Discretionary | Report by Dawn Nicholls This project was closed on 24th September 2013 Please see the completion report for further information |
FIN092 Corporate Planner Category: Compliance | Report by Anne Mathison This project was closed on 20th December 2013 Please see the completion report for further information |
AP34 Migration of BOXI reports Compliance | Withdrawn - January 2014 |
AP89-008 FPM for eInvoicing | Withdrawn - January 2014 |
FIN092 Corporate Planner Category: Compliance | Closed - January 2014 |
FIN091 eFinancials upgrade Phase 2 Category; Compliance | Closed 31/3/14 |
FIN080 Customer Interface Improvements Category : Discretionary | This project was closed on 8th April 2014 Please see the completion report for further information |
FIN056 eInvoicing Category: Funded | This project was closed 30th May, remaining work will be completed under FIN096. |
FIN090 eExpenses Replacement Business Case Category: Compliance | This project was closed 30th May, a project to develop new expenses software is underway under FIN098. |
Section Five: New Approved Projects from 13/14 Annual Plan
Any projects that were approved in previous annual planning rounds and have been postponed to start in 13/14 will be listed under section 2: Projects Not Started. Projects started in 12/13 but which will carry over to 13/14 are listed under section 3: In Progress.
Project Info | Project Managers Commentary |
AP34 Student Fees - Interest Charging on Invoices Compliance Planning - Delivery - RAG Status | Plan
Dependencies
|
AP34 Student Fees - SAAS and SLC Fees Reconciliation Compliance Planning - Delivery - RAG Status | Plan
Dependencies |
AP34 Migration of BOXI reports Compliance Planning - Delivery - RAG Status | Plan
Dependencies |
AP34 Essential Enhancements for Finance Applications Compliance Planning - Delivery - RAG Status | Plan
Dependencies |
AP34 eExpenses replacement Compliance Planning - Delivery - RAG Status | Plan
Dependencies |