Report for May 2014

Report Date
May 2014

Report compiled by Rhian Davies (IS Apps Programme Manager) for Liz Welch  (Programme Owner)

Section One: Programme Commentary, and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

 

 

Section One: Programme Commentary, and Resources Update  

 

 

 

 

 

 

Section Two: Projects Not Started

 

Project InfoProgramme Managers Commentary

 AP34

Student Fees - Interest Charging on Invoices

Compliance

Planning - September 2014

Delivery - tbc

 RAG Status - GREEN

 Plan

 

Dependencies

Need to get decision from Fee Strategy Group which meets quarterly - FIS following up on status, but agreed that the project will not start until next year now as FIS resources are allocated to other projects.

 

Section Three: Projects in Progress

 

Project InfoProject Managers Commentary

FIN081 (12-024)

Document Management for Finance Applications

Category: Discretionary

Milestones (to be reviewed and agreed)

TBC

Agree Scanning Activity Ownership

TBC

Finance Document Requirements available

TBC

Business Analysis

TBC

Document Scanning Activity Completed

TBC

Deploy to Development

TBC

Deploy to Test

TBC

Deploy to Live

TBC

Closure

RAG Status : AMBER

Report by Karen Stirling for May 2014

Achievements in Last period

  • Finance team provided DDSR with 3 examples folder to scan
  • DDSR provided file which were uploaded to Test environment due to issues with Dev environment being investigated via CMW010 project. Application Management advised that Document retrieval from Serengeti using client-based Adobe reader  was very fast.
  • Directorate documentation - high level review of folder completed by Finance with some documents listed for scanning, disposal or archive, further work required to provide a comprehensive detailed list to complete analysis. Finance have advised that they have removed a number of files from the list however number of files not provided.

Issues

  • Project progress limited this month as Finance resource have still to provide an updated list of documents to allow discussion / analysis to take place regarding atrributes, files and folder structure. This area of work requires focus / ownership to allow estimation of costs for scanning by DDSR (this includes xml attribute allocation ) to be agreed and business requirements / business analyis to be reviewed and agreed. This will be impacted due to changes in Finance key project resource.
  • Resource changes on the FIN081 project were communicated to Project Manager on 29th May:
  1. Shirley Lee, Finance advised  that she is going on a 1 year secondment from 12th June so she will be handing over FIN081 project to another Finance colleague however this person has still to be confirmed. Project manager  has arranged a meeting for week commencing 8th June to review with new project contacts.
  2. Andrew McFarlane, Service Management will be replacing Chris McKay. Due to Chris's workload on projects e.g. IDM, VRS, Serengeti upgrade and this finance project  he is handing over both CMW010 and FIN081 to Andrew.  An initial handover meeting was held on 3rd June.
  • Limited availability of PM this month as on Jury Duty (unplanned 1 week) , annual leave (1 week) and sick leave (2 days)
  • Due to the current upgrade CMW010 project,  the test system being taken out of service on 21 May, Apps Management performed a quick upload exercise of 3 files to Test Serengeti document management system provided by DDSR. Although initial concerns around file sizes, as these ranged  up to 33MB, (maximum upload setting was set to 10MB).  However, after increasing it to 50MB,  Application Management were able to upload all three files in a few minutes. The tab-based bookmarks work well although we will need to confirm that this suits Finance users. The OCR overlay is also excellent, although we will also need to consider if this option should be included.  Indeed we may also consider whether it is feasible to make the OCR content searchable via Serengeti system this will be part of CMW010 project. Assuming that the bookmark tabs are deemed suitable, we still need to discuss and agree some form of attribute/XML allocation in order to allow automated import before we can progress further.
  • Revised project milestones remain outstanding due to : business requirements/analysis not completed, change in project resource and transfer of 35 days budget moved to 14/15.

 

Next Steps

  • Revised Milestones for project
  • Agree attributes, folder, file structure
  • Agree costs and dates for scanning activities

 

The project status AMBER due to business documentation details not finalised, impact of change in resource and milestones to be revised.

FIN085  (AP01-008)

eTime Phase 3

 

Category:  Compliance

 

 

Milestones

06-Jun-2014Deployment signed off
20-Jun-2014Closure

RAG Status:  GREEN

Report by Jill Nicoll for May 2014

Achievements in last period:

Release 6:

  • UAT re-testing and sign off completed
  • Deployed to Live

HSS-funded enhancement:

  • UAT re-testing and sign off completed
  • Deployed to Live

Closure:

  • Full system documentation, and a 3.5 hour handover presentation, have been provided to Applications Management.

Issues:

Two weeks of post-deployment support was provided by the project team.  However, two post-deployment issues were raised at the end of this two-week period.  Additional resources have been requested, to address these issues.  The Deployment Sign-off Review and Closure milestones have been extended, by a few days, to accommodate this work.

The UAT testing Risks have been closed, but the project team remains concerned that the Research regression testing, which did not start until the final week of the UAT stage, may have been inadequate.

Next Steps:

Closure:

  • Address post-deployment issues and deploy to Live
  • Complete Closure Report
  • Close project

FIN086 (AP23-004)

ePay Reconciliation

 

Category:  Compliance

 

30-May-2014System Design Complete
20-Jun-2014Build Complete
04-Jul-2014Integration Test Signed Off
18-Jul-2014Acceptance Sign Off
25-Jul-2014Deliver
31-Jul-2014Project Close

 

 

 

RAG Status:  AMBER

 

Report by Louise Heathcote for May 2014

Achievements in this Reporting Period

  • Project now estimated
  • Brief signed off
  • Requirements and System Design complete

 

Issues

  • WPM can't make new file for four weeks, creating a dummy file to not hold up build

 

Next Steps

 

 

FIN087 (23-058)

Credit Note/Sales Invoice Interface Changes

Category:  Discretionary

Milestones

 

Target dateTitle
28-May-2014Acceptance Review
12-Jun-2014Go-Live
26-Jun-2014Deployment Review
03-Jul-2014Project Closure

RAG Status:  GREEN

Report by Dawn Nicholls for May 2014

Achievements this period

  • Integration testing completed this month and the new interface was passed to Finance for acceptance testing
  • Acceptance testing is almost complete 

Issues

  • Some minor changes have been requested as a result of UAT (e.g. changes of email recipients) which has delayed the sign-off of this phase
  • The go-live date is now likely to be delayed to the end of June - a revised date has yet to be agreed with Finance 

Next steps

  • Completion and sign-off of UAT
  • Go-live

 

Full details on project activities can be seen in the Project Journal

FIN088 (AP12-017)

ERA Decommissioning

 

Category:  Compliance

 

Milestones

 

10-Jun-2014Acceptance Finance Channel Complete
18-Jun-2014Deliver Finance Channel
26-Jun-2014Project Closed & Finance Deployment Sign Off

 

 RAG Status:  AMBER

Report by Louise Heathcote for May 2014

 

Report Date: May 2014

 

  • Achievements in this Reporting Period

    • Finance Channel Integration testing complete
    • Finance Channel UAT commenced
    • WPM call back move tested and scheuled to go live on 3rd June
    • WPM Call Back performance review meeting scheduled
    • New milestones submitted for approval

     

    Issues

    • Project Manager leaving at the end of June plan to put Finance Channel live before she leaves

     

    Next Steps

    • FIS to test Finance Channel
    • Schedule live deployment
    • Project Close

 

FIN089 (34-004)

eAuthorisations Migration

 

Category:  Compliance & Funded

 

 

Milestones

13-Jun-2014Phase 4 UAT approved
19-Jun-2014Phase 4 Delivery
04-Jul-2014Phase 4 Deployment approved
11-Jul-2014Closure

 

RAG Status:  GREEN

Report by Jill Nicoll for May 2014
 

Achievements in last period:

Phase 4:

Batch 1:

  • UAT testing signed off
  • Deployed to Live

Batch 2:

  • UAT testing signed off
  • Deployed to Live

Batch 3:

  • Build completed
  • UAT testing signed off
  • Deployed to Live

Batch 4:

  • Build completed, but peer testing ongoing

Issues:

Progress on the Build stage for Phase 4, batch 4 has been delayed, by unplanned effort required to address:

  • two post-deployment Live issues, and
  • an item of added scope requested by the Project Sponsor. 

The revised release date for UAT is 3rd June.  This will reduce the batch 4 UAT stage to 10 days duration 8 working days).

Progress on the Phase 4, batch 4 change to the BI Universe has been delayed by the Developer's inability to gain access and authentication permission to the Dev BI environment.  Thesa issues are ongoing, and point to a weakness in the ISA procedures for gaining BI access. 

Next Steps:

Phase 4:

Batch 4:

  • Complete peer testing and release for UAT
  • UAT test and sign off
  • Deploy to Live

FIN093

Essential Enhancements for Finance Applications

Compliance

Milestones

 

Target dateTitle
04-Jul-2014Final Delivery
18-Jul-2014DSOR
31-Jul-2014Closure

 

 

RAG Status:  AMBER

Report by Steph Ruthven for May 2014

 

 

Achievements in Last Period

  • Continued work on PDF Module

  • Investigation into changes to BI Suite universes scheduled
  • eProcurement patch scheduled
  • eStores unidesk calls scheduled

Issues

  • No movement on the Bank Wizard changes. Waiting on ABS and Experian to advise what's required.
  • Development resource unavailable to complete a number of changes.

Next Steps

  • Concentrate on picking up Unidesk calls
  • Schedule changes to BI Suite universes
  • Complete eProcurement patch
  • Complete eStores unidesk calls

 

 

FIN094

SAAS/SLC Reconciliation

Compliance

Milestones

Target dateTitle
02-Jun-2014Analysis & Design sign-off
30-Jul-2014Build sign-off
22-Aug-2014Integration sign-off
12-Sep-2014Acceptance sign-off
19-Sep-2014Go-live
03-Oct-2014Deployment sign-off
17-Oct-2014Closure

 RAG Status - GREEN

Report by Dawn Nicholls for May 2014

Achievements this period

  • Planning stage sign-off, including the formal approval of the Project Brief
  • Solution design agreed on. This design is quite a simple approach and the budget will be re-estimated
  • System design document (SDD) has been completed  and walked through with key stakeholders from FIS and Registry

Issues

  • None at present

Next steps

  • Formal design sign-off
  • Re-estimate budget
  • Software build

   

Full details on project activities can be seen in the Project Journal

 

Local Implementation of SSO and Launchpad

Discretionary

 

 

Milestones

 

These will be reviewed ( see issues - over)

 

09-Jun-2014Integration Review
30-Jun-2014Acceptance Review
10-Jul-2014Delivery
21-Jul-2014Deployment Review
31-Jul-2014

Close

 

 

 

 

 

 

The project status is AMBER pending review of project milestones.

 

 

 

Report by Morna Findlay for May 2014

Achievements this period

 

Investigations by IS Apps and FIS of Launchpad functionality in DEV.

Report on shibboleth integration indicated this approach should not be continued.

Successful integration of launchpad and cosign

Build review approved

 

Issues

 

Unavailability of key devtech and FIS resources in July require project to be re-planned.

 

Next Steps

 

Project re-estimate, re-plan  and confirmation of deliverables.

FIS to provide benchmarking information in order to assess impact of Launchpad on eFinancials performance.

Launchpad to be implemented in TEST.

UAT to complete

 

 

 

FIN096

eInvoicing

 

Category:  Funded

 

 

Milestones

Target dateTitle
09-May-2014Project Brief approved
14-Jul-2014UAT Sign-off
16-Jul-2014Delivery
28-Jul-2014Deployment Sign-off
30-Jul-2014Closure

 

RAG Status:  GREEN

Report by Jill Nicoll for May 2014
 
Achievements in last period:

Finance:

Planning:

  • Project Brief reviewed by Project Sponsor and signed off.
  • Project approach confirmed by Project Sponsor.

ISA

Planning:

  • Project re-planned to reflect approach decision.
  • Resources secured in ISA.

System Design:

  • Progress to date on project FIN056 assessed, and its status confirmed.

Build:

  • Dev FIN056 transfer process upgraded to new Dev eFinancials paths.
  • Dev file transfer process successfully re-tested, using an in-house ("dummy") source directory.

 

Issues: 

The project plan required that both the ABS CIBR and the Office Depot server directory & sample files would be available at the start of the ISA Build on 26-May.  None of these was in place.  The delay to these prerequisites risk the project's ability to deliver the Build stage by its target date of 16-June.

The Brief estimates assumed that Finance and ABS would provide and configure the CIBR.  Consequently, no ISA estimate was included for this work.  However, the Business Area manager has asked ISA to participate in the application of the Dev CIBR, and to apply and configure the Test and Live CIBRs.  The project budget does not cover this additional scope.  Once the Dev CIBR is in place, estimates for ISA either to continue the support, or to take over the work, in Test and Live will be sought.  The resulting increase will be then be notified to the Project Sponsor and Programme Manager, for a decision on how to proceed. 

 

Next Steps:

Office Depot:

  • Create UoE-specific Test and Live server directory.
  • Set up Test and Live public-private key exchange.
  • Provide Test XML invoice files, in the format specified by Finance.

Finance & ABS:

Build:

  • Update Dev eInvoicing CIBR.
  • Reconfigure Dev CIBR to use new Dev eFinancials paths.
  • Re-test file Dev upload process.
  • Confirm that Dev upload runs successfully.

Integration:

  • Update Test eInvoicing CIBR.
  • Reconfigure Test CIBR to use new Dev eFinancials paths.

ISA:

Build:

  • Upgrade Dev FIN056 transfer process to new Office Depot source directory and authentication method.
  • Re-test Dev file transfer process from new Office Depot source directory.
  • Confirm that Dev files transfer successfully.

Integration:

  • Deploy transfer process to Test.
  • Complete Integration testing and release for UAT.

FIN097

Archiving for eFinancials

 

Category:  Funded

 

 

Milestones

 

These are not yet approved.

 

29-May -2014  End of planning
30-May-2014Analysis Review Signoff
09-Jun-2014Build Review
23-Jun-2014Acceptance Review
01-Jul-2014Delivery
14-Jul-2014Deployment Sign off Review
01-Aug-2014Close

 

 

 

 

 

 

 

 

 

 

 

 

 

 

RAG Status:  AMBER

Achievements this period

 

 

Project brief, estimate, plan and milestones agreed with project sponsor

Research and development work carried out by project team with ABS consultants

Rollback plan drafted

Analysis review drafted

 

Issues

 

Project brief not yet approved by WIS

 

Next Steps

 

Achieve project brief approval

Complete analysis review

Confirm scope with project sponsor 

Re-estimate   and re-plan project 

Confirm project milestones

 

The project is AMBER pending approval of the project brief

FIN098

eExpenses Replacement

 

Category:  Discretionary

 

Milestones

Target dateTitle
06-Jun-2014End of Foundations
24-Oct-2014End of Development
07-Nov-2014End of Maintenance
21-Nov-2014Closure

 

RAG Status:  GREEN

 

Report by Dawn Nicholls for May 2014

Achievements this period

  • The planning stage for formally signed off and the Project Brief approved
  • User Groups held with both FInance and non-Finance users of the current eExpenses system
  • Outputs of the workshop consolidated and resulting User Stories estimated
  • Technical environments set-up
  • Planning meeting held for development iteration 1 which start on 9th June

Issues

  • Annual leave of the key stakeholders has made the foundations stage sifficult to progress

Next steps

  • Formal sign-off of the foundations stage
  • Multiple software development iterations

  

Further details on project activities can be seen in the Project Journal

 

 

Section Four: Closed or Withdrawn Projects

 

Project InfoProject Managers Commentary

FIN078

eFin Journal Auto Upload (JAMS)

Category : Discretionary 

Report by Dawn Nicholls

This project was closed on 4th October 2013

Please see the completion report for further information

FIN079

LEAN Review of Financial Systems

Category : Discretionary

Report by Dawn Nicholls

This project was closed on 24th September 2013

Please see the completion report for further information

FIN092

Corporate Planner

Category:  Compliance

Report by Anne Mathison

This project was closed on 20th December 2013

Please see the completion report for further information

AP34

Migration of BOXI reports

Compliance

Withdrawn - January 2014

AP89-008

FPM for eInvoicing

Withdrawn - January 2014

FIN092

Corporate Planner

Category:  Compliance

Closed - January 2014

FIN091

eFinancials upgrade Phase 2

Category; Compliance

Closed 31/3/14

FIN080

Customer Interface Improvements

Category : Discretionary

This project was closed on 8th April 2014

Please see the completion report for further information

FIN056

eInvoicing

Category: Funded

This project was closed 30th May, remaining work will be completed under FIN096.

FIN090

eExpenses Replacement Business Case

Category: Compliance

This project was closed 30th May, a project to develop new expenses software is underway under FIN098.

 

Section Five: New Approved Projects from 13/14 Annual Plan

Any projects that were approved in previous annual planning rounds and have been postponed to start in 13/14 will be listed under section 2: Projects Not Started. Projects started in 12/13 but which will carry over to 13/14 are listed under section 3: In Progress.

 

 

 

 

 

 

 

 

 

 

 

 

Project InfoProject Managers Commentary

 AP34

Student Fees - Interest Charging on Invoices

Compliance

Planning -

Delivery -

 RAG Status

 Plan

 

Dependencies

 

AP34

Student Fees - SAAS and SLC Fees Reconciliation

Compliance

Planning -

Delivery -

 RAG Status

Plan

 

Dependencies

AP34

Migration of BOXI reports

Compliance

Planning -

Delivery -

 RAG Status

Plan

 

Dependencies

AP34

Essential Enhancements for Finance Applications

Compliance

Planning -

Delivery -

 RAG Status

Plan

 

Dependencies

AP34

eExpenses replacement

Compliance

Planning -

Delivery -

 RAG Status

Plan

 

Dependencies