Report for April 2014
- Report Date
- April 2014
Report compiled by Rhian Davies (IS Apps Programme Manager) for Liz Welch (Programme Owner)
Section One: Programme Commentary, and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, and Resources Update
Commentary
FIN080 closed
Section Two: Projects Not Started
Project Info | Programme Managers Commentary |
AP34 Student Fees - Interest Charging on Invoices Compliance Planning - September 2014 Delivery - tbc RAG Status - GREEN | Plan
Dependencies Need to get decision from Fee Strategy Group which meets quarterly - FIS following up on status, but agreed that the project will not start until next year now as FIS resources are allocated to other projects. |
Section Three: Projects in Progress
Project Info | Project Managers Commentary | ||||||||||||||||||||||||||||
FIN056 (AP Number) eProcurement Scotland - eInvoicing Category: Funded Milestones --- --- --- RAG Status : SUSPENDED | Report by Rhian Davies for Mar 2014. Project suspended until 13/14 - meeting held with Finance and Procurement to discuss future of project. Will know by early May if this project is still required.
| ||||||||||||||||||||||||||||
FIN081 (12-024) Document Management for Finance Applications Category: Discretionary Milestones (proposed to be agreed)
RAG Status : GREEN | Report by Karen Stirling for April 2014 Achievements in last period
Issues
Next Steps
| ||||||||||||||||||||||||||||
FIN085 (AP01-008) eTime Phase 3
Category: Compliance
Milestones
RAG Status: GREEN | Report by Jill Nicoll for April 2014 Achievements in last period: Release 6:
HSS-funded enhancement:
Issues: Only one area outwith the project stakeholder group was recruited to UAT test the Batch Processing functionality (Risk 8). The key Research stakeholders were unable to start regression testing until the final week of the 6-week UAT testing block (Risk 9). Next Steps: Release 6:
HSS-funded enhancement:
| ||||||||||||||||||||||||||||
FIN086 (AP23-004) ePay Reconciliation
Category: Compliance
Milestones 26-Apr-13 Planning
RAG Status: AMBER
| Report by Louise Heathcote for April 2014
Achievements in this Reporting Period
Issues
Next Steps
| ||||||||||||||||||||||||||||
FIN087 (23-058) Credit Note/Sales Invoice Interface Changes Category: Discretionary Milestones
RAG Status: GREEN | Report by Dawn Nicholls for April 2014 Achievements this period
Issues
Next steps
Full details on project activities can be seen in the Project Journal | ||||||||||||||||||||||||||||
FIN088 (AP12-017) ERA Decommissioning
Category: Compliance
Milestones
RAG Status: GREEN | Report by Louise Heathcote for April 2014
Report Date: April 2014 Achievements in this Reporting Period
Issues
Next Steps
| ||||||||||||||||||||||||||||
FIN089 (34-004) eAuthorisations Migration
Category: Compliance & Funded
Milestones
RAG Status: GREEN | Report by Jill Nicoll for April 2014 Achievements in last period: Phase 4: Batch 1:
Batch 2:
Issues: Progress on the Build tasks for Phase 4 has been delayed:
However, it is still planned that the project will deliver Phase 4 batches 1 & 2 on May 14th, along with eTime's new Batch Processing functionality. Next Steps: Phase 4: Batch 1:
Batch 2:
Batch 3:
Batch 4:
| ||||||||||||||||||||||||||||
FIN093 Essential Enhancements for Finance Applications Compliance Milestones
RAG Status - AMBER | Report by Steph Ruthven for April 2014Achievements in Last Period
Issues
Next Steps
| ||||||||||||||||||||||||||||
FIN094 SAAS/SLC Reconciliation Compliance Milestones
RAG Status - AMBER | Report by Dawn Nicholls for April 2014Achievements this period
Issues
Next steps
Full details on project activities can be seen in the Project Journal | ||||||||||||||||||||||||||||
Local Implementation of SSO and Launchpad Discretionary
RAG STATUS: GREEN
| Report by Morna Findlay for April 2014Achievements this period
Project brief, milestones, estimate and plan agreed and approved. Launchpad webinar held with ABS. Launchpad installed in DEV. Shibboleth investigations progressed.
Next Steps
Investigations by IS Apps and FIS of Launchpad functionality in DEV. Report on shibboleth integration investigations to be delivered. Project re-estimate and confirmaton of deliverables. FIS to provide benchmarking information in order to assess impact of Launchpad on eFinancials performance. Launchpad to be implemented in TEST. Decison taken on whether to integrate Launchpad with shibboleth.
The project status is GREEN
| ||||||||||||||||||||||||||||
FIN096 eInvoicing
Category: Funded
Milestones
RAG Status: GREEN | Report by Jill Nicoll for April 2014 Achievements in last period:
Issues: The Brief has been delayed by a change of scope, to investigate and assess other potential project approaches. The project plan cannot be confirmed, and ISA resources cannot be requested, until the selected approach has been confirmed.
Next Steps:
| ||||||||||||||||||||||||||||
FIN097 Archiving for eFinancials
Category: Funded
Milestones tbc by Project Brief
RAG Status: GREEN | Achievements this periodInitial project kick-off meetings held Project brief drafted Information session with ABS consultant held for project team
Next StepsApproval of project brief, estimate, plan and milestones
The project status is GREEN | ||||||||||||||||||||||||||||
FIN098 eExpenses Replacement
Category: Discretionary
Milestones
RAG Status: GREEN | Report by Dawn Nicholls for April 2014Achievements this period
Issues
Next steps
Further details on project activities can be seen in the Project Journal
|
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
FIN078 eFin Journal Auto Upload (JAMS) Category : Discretionary | Report by Dawn Nicholls This project was closed on 4th October 2013 Please see the completion report for further information |
FIN079 LEAN Review of Financial Systems Category : Discretionary | Report by Dawn Nicholls This project was closed on 24th September 2013 Please see the completion report for further information |
FIN092 Corporate Planner Category: Compliance | Report by Anne Mathison This project was closed on 20th December 2013 Please see the completion report for further information |
AP34 Migration of BOXI reports Compliance | Withdrawn - January 2014 |
AP89-008 FPM for eInvoicing | Withdrawn - January 2014 |
FIN092 Corporate Planner Category: Compliance | Closed - January 2014 |
FIN091 eFinancials upgrade Phase 2 Category; Compliance | Closed 31/3/14 |
FIN080 Customer Interface Improvements Category : Discretionary | Report by Dawn Nicholls This project was closed on 8th April 2014 Please see the completion report for further information |
Section Five: New Approved Projects from 13/14 Annual Plan
Any projects that were approved in previous annual planning rounds and have been postponed to start in 13/14 will be listed under section 2: Projects Not Started. Projects started in 12/13 but which will carry over to 13/14 are listed under section 3: In Progress.
Project Info | Project Managers Commentary |
AP34 Student Fees - Interest Charging on Invoices Compliance Planning - Delivery - RAG Status | Plan
Dependencies
|
AP34 Student Fees - SAAS and SLC Fees Reconciliation Compliance Planning - Delivery - RAG Status | Plan
Dependencies |
AP34 Migration of BOXI reports Compliance Planning - Delivery - RAG Status | Plan
Dependencies |
AP34 Essential Enhancements for Finance Applications Compliance Planning - Delivery - RAG Status | Plan
Dependencies |
AP34 eExpenses replacement Compliance Planning - Delivery - RAG Status | Plan
Dependencies |