Report for January 2014

Report Date
January 2014

Report compiled by Rhian Davies (IS Apps Programme Manager) for Liz Welch  (Programme Owner)

Section One: Programme Commentary, and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

 

Section One: Programme Commentary, and Resources Update  

 

 

 

 

 

Section Two: Projects Not Started

 

Project InfoProgramme Managers Commentary

 AP34

Student Fees - Interest Charging on Invoices

Compliance

Planning - September 2014

Delivery - tbc

 RAG Status - GREEN

 Plan

 

Dependencies

Need to get decision from Fee Strategy Group which meets quarterly - FIS following up on status, but agreed that the project will not start until next year now as FIS resources are allocated to other projects.

AP34

eExpenses Replacement

Compliance

Planning - tbc

Delivery - tbc

 RAG Status

Plan

 This is the procurement and implementation of a new eExpenses Solution

Dependencies

The direction of this project depends on the outcome of the proof of concept project.

 

Section Three: Projects in Progress

 

Project InfoProject Managers Commentary

FIN056 (AP Number)

eProcurement Scotland - eInvoicing

Category: Funded

Milestones

---

---

--- 

RAG Status : SUSPENDED

Report by Rhian Davies for Jan 2014.

Project suspended until 13/14 - decision to be taken in early 2014 re future of project.

 

 

FIN080 (AP Number)

Customer Interface Improvements

Category: Discretionary

Milestones

Target dateTitle
28-Jan-2014Acceptance review (part 2)
11-Feb-2014Phase 2 Go-live (part 2)
28-Feb-2014Phase 2 - Deployment Review
14-Mar-2014Closure

RAG Status : AMBER

Report by Dawn Nicholls for January 2014

Achievements ths period

  • Phase 2 part 1 went live in January.  This included the new debt chasing fields such as 'country of domicile' and 'nationality'

Issues

  • The sign-off for Phase 2 Part 2 had to be postponed after an issue was with the historic feed was discovered by SACS.  SACS are working with the developer to find a resolution.  The project has been placed on AMBER status as new issues keep emerging with this feed and the UAT stage has now been going on for several months.

Next steps

  • Resolve issue with historic feed
  • Sign-off UAT
  • Go-live

 

Full details on project activities can be seen in the Project Journal

FIN081 (AP Number)

Document Management for Finance Applications

Category: Discretionary

Milestones

28-Feb-2014Planning

 

RAG Status : GREEN

Report by Karen Stirling for January 2014

Achievement in last period

  • Project unsuspended on 24th January
  • New Project Manager assigned to cover PM / BA activity
  • Funding noted as 70 days IS Apps effort

 

Issues

Nothing to report

 

Next Steps

  • Set up initial meeting with Finance, Service Management and IS Apps to discuss scope of project
  • Identify key stakeholders, timescales etc
  • Project brief

FIN085  (AP01-008)

eTime Phase 3

 

Category:  Compliance

 

Milestones

28-Mar-2014UAT (for final release) signed off
18-Apr-2014Deployment signed off
25-Apr-2014Closure

 

RAG Status:  GREEN

Report by Jill Nicoll for January 2014

Achievements in last period:

Release 6:

Build completed 

Release notes completed

 

Issues:

Last month's report included the issue of the low availability of the Designer, and its impact on the expected delivery date for the Peer testing.  The ISA project team has agreed that the Designer will create the Peer Test Plan, which will then be performed by the Developer.  Feedback will be submitted to and discussed with the Designer.  The project has been re-planned to reflect this agreement.  To allow the required elapsed time for the Designer to complete the Test Plan, the Developer's task to complete the updates to the System Description Document has been brought forward from the UAT stage. 

The Project Sponsor and Programme Manager have confirmed that the increased estimate to complete Release 6's Batch Entry functionality will be covered from the Programme budget.

The HSS-funded effort remains with its "holding measure" estimate and milestone dates.  When estimates have been confirmed, the plan will be adjusted accordingly.

 

Next Steps:

Release 6:

Complete Peer Test Plan

Complete Peer testing

Deploy to Test

Release for UAT Testing

FIN086 (AP23-004)

ePay Reconciliation

 

Category:  Compliance

 

Milestones

26-Apr-13  Planning

 

 

 

RAG Status:  GREEN

 

Report by Rhian Davies for January 2014

Project suspended until 13/14 to enable eAuthorisations to start in 12/13.

 

FIN087

Credit Note/Sales Invoice Interface Changes

Category:  Funded

Milestones

Target dateTitle
03-Feb-2014Build Review
17-Feb-2014Integration Review
03-Mar-2014Acceptance Review
17-Mar-2014Go-Live
24-Mar-2014Deployment Review
31-Mar-2014Project Closure

RAG Status:  GREEN

Report by Dawn Nicholls for January 2014

Achievements this period

  • Development work has completed and the application is now undergoing peer testing

Issues

  • Resource conflicts for the peer tester and annual leave of the lead developer have delayed the build review by 2 weeks

Next steps

  • Build sign-off
  • Implement to Test and integration testing
  • UAT by Finance 

 

Full details on project activities can be seen in the Project Journal

FIN088 (AP12-017)

ERA Decommissioning

 

Category:  Compliance

 

 

Milestones

 

20-Dec-201308-Nov-2013Integrate Finance Channel Complete
24-Jan-201415-Nov-2013Acceptance Finance Channel Complete
31-Jan-201418-Nov-2013Deliver Finance Channel
14-Feb-201428-Nov-2013Project Closed & Finance Deployment Sign Off
 

 RAG Status:  RED

Report by Louise Heathcote for January 2014

 

Achievements in this Reporting Period

  • Finance Channel changes are in test and integration testing and has been stopped until the investigation into the WPM failtures has been resolved 
  • Issue resolution meeting held regarding an increase of error for Print Credit

Issues

  • At the issue resolution meeting recognised that the process will never be failure free therefore need to accept a tolerance of errors, one possible solution for Finance Channel is to investigate a means of mopping up failed payments but there is no budget left in this project to deliver
  • For Print Credit the timeout is being reverted as the extension has cause them issues
  • Missed milestones for Finance Channel Integration and UAT due to resource conflict and ongoing issues with failures for Print Credit

  Next Steps

  • Agree to proceed and finalise the testing of the Finance Channel
  • Make Finance Channel live
  • Remove ERA bouncethrough

 

FIN089

eAuthorisations Migration

 

Category:  Compliance & Funded

 

Milestones

28-Feb-2014Phase 3 UAT approved
05-Mar-2014Phase 3 Delivery
21-Mar-2014Phase 3 Deployment approved
23-Apr-2014Phase 4 Build approved
05-May-2014Phase 4 Integration approved
30-May-2014Phase 4 UAT approved
29-May-2014Phase 4 Delivery
20-Jun-2014Phase 4 Deployment approved
04-Jul-2014Closure

 

 

RAG Status:  GREEN

Report by Jill Nicoll for January 2014
 

Achievements in last period:

Phase 2:

Application changes deployed to Live.

BOBI universe changes deployed to Live.

Deployment signed off, contingent upon successful completion of Jira FIN089-138.

Phase 3:

Build completed and signed off in Peer testing.

Integrated to Test and signed off in Integration testing.

Released for UAT testing.

Initial UAT Test Plan created, and released to business testing team for expansion and completion.

Phase 4:

75 days of additional funding confirmed, for Phase 4 High/Medium priority requirements.

 

Issues:

n/a

 

Next Steps:

Phase 2 (IS Apps task):

Complete Jira FIN089-138.

Phase 3 (Business stakeholder tasks):

Complete UAT Test Plan.

Complete UAT Testing.

Confirm UAT sign-off.

Phase 4 (IS Apps task):

Complete System Design.

FIN091

eFinancials Upgrade Phase 2

Category: Compliance

 Milestones

12 Feb 2014 Sign off Launchpad deliverables
28 Feb 2014Close

 

 

RAG Status:: GREEN

Achievements this period

Supplier Self-Service  deployed to LIVE

Supplier Self Service Deployment sign off achieved.

New milestones approved.

 

Outstanding Issues

Single Sign On/Launchpad deliverables to be approved.

 

Next Steps

 

Single Sign On/Launchpad deliverables to be approved.

Project to close.

 

The project is GREEN

 

FIN093

Essential Enhancements for Finance Applications

Compliance

Planning - January 2014

Delivery - July 2014

 RAG Status - GREEN

Report by Rhian Davies for January 2014

Project brief due to be complete in February 2014

FIN094

SAAS/SLC Reconciliation

Compliance

Milestones

Target dateTitle
28-Feb-2014End of planning
30-Sep-2014Delivery

 RAG Status - GREEN

Report by Dawn Nicholls for January 2014

Achievements this period

  • Project initiation and initial scope-finding meetings held with Finance, Registry Finance, SACS and Income Section

Issues

  • None to date

Next steps

  • Production of Project Brief and sign-off of end of planning

 

 Full details on project activities can be seen in the Project Journal

 

 

Section Four: Closed or Withdrawn Projects

 

Project InfoProject Managers Commentary

FIN078

eFin Journal Auto Upload (JAMS)

Category : Discretionary 

Report by Dawn Nicholls

This project was closed on 4th October 2013

Please see the completion report for further information

FIN079

LEAN Review of Financial Systems

Category : Discretionary

Report by Dawn Nicholls

This project was closed on 24th September 2013

Please see the completion report for further information

FIN092

Corporate Planner

Category:  Compliance

Report by Anne Mathison

This project was closed on 20th December 2013

Please see the completion report for further information

FIN076

Student Finance Channel - Further Developments for Staff and Students

Category: Discretionary

Report by Susan McKeown

This project was closed in November 2013.

Please see the completion report for further information

AP34

Migration of BOXI reports

Compliance

Withdrawn - January 2014

AP89-008

FPM for eInvoicing

Withdrawn - January 2014

FIN092

Corporate Planner

Category:  Compliance

Closed - January 2014

 

Section Five: New Approved Projects from 13/14 Annual Plan

Any projects that were approved in previous annual planning rounds and have been postponed to start in 13/14 will be listed under section 2: Projects Not Started. Projects started in 12/13 but which will carry over to 13/14 are listed under section 3: In Progress.

 

 

 

 

 

 

 

 

 

Project InfoProject Managers Commentary

 AP34

Student Fees - Interest Charging on Invoices

Compliance

Planning -

Delivery -

 RAG Status

 Plan

 

Dependencies

 

AP34

Student Fees - SAAS and SLC Fees Reconciliation

Compliance

Planning -

Delivery -

 RAG Status

Plan

 

Dependencies

AP34

Migration of BOXI reports

Compliance

Planning -

Delivery -

 RAG Status

Plan

 

Dependencies

AP34

Essential Enhancements for Finance Applications

Compliance

Planning -

Delivery -

 RAG Status

Plan

 

Dependencies

AP34

eExpenses replacement

Compliance

Planning -

Delivery -

 RAG Status

Plan

 

Dependencies