Report for February 2014

Report Date
February 2014

Report compiled by Rhian Davies (IS Apps Programme Manager) for Liz Welch  (Programme Owner)

Section One: Programme Commentary, and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

 

Section One: Programme Commentary, and Resources Update  

 

 

 

 

 

Section Two: Projects Not Started

 

Project InfoProgramme Managers Commentary

 AP34

Student Fees - Interest Charging on Invoices

Compliance

Planning - September 2014

Delivery - tbc

 RAG Status - GREEN

 Plan

 

Dependencies

Need to get decision from Fee Strategy Group which meets quarterly - FIS following up on status, but agreed that the project will not start until next year now as FIS resources are allocated to other projects.

AP34

eExpenses Replacement

Compliance

Planning - tbc

Delivery - tbc

 RAG Status

Plan

 This is the procurement and implementation of a new eExpenses Solution

Dependencies

The direction of this project depends on the outcome of the proof of concept project.

 

Section Three: Projects in Progress

 

Project InfoProject Managers Commentary

FIN056 (AP Number)

eProcurement Scotland - eInvoicing

Category: Funded

Milestones

---

---

--- 

RAG Status : SUSPENDED

Report by Rhian Davies for Jan 2014.

Project suspended until 13/14 - decision to be taken in early 2014 re future of project.

 

 

FIN080 (AP Number)

Customer Interface Improvements

Category: Discretionary

Milestones

Target dateTitle
11-Mar-2014Phase 2 Go-live (part 2)
25-Mar-2014Phase 2 - Deployment Review
08-Apr-2014Closure

RAG Status : GREEN

Report by Dawn Nicholls for February 2014

Achievements this period

  • Phase 2 part 2 (the historic feed) acceptance testing completed this month and was signed off by Finance, SACS and IS reps
  • A go-live date of 11th March has been agreed to allow for the SITS upgrade to complete and the Business Object freeze to be lifted

Issues

  • None currently

Next Steps

  • Go-live is planned for 11th March
  • Deployment review

 

Full details on project activities can be seen in the Project Journal

FIN081 (AP Number)

Document Management for Finance Applications

Category: Discretionary

Milestones

14-Mar-2014Planning

 

RAG Status : AMBER

Report by Karen Stirling for January 2014

Achievements in last period

  • Initial meeting held with Finance, Service Management and IS Apps to discuss scope of project
  • Key stakeholders identified
  • Project brief draft in progress
  • Draft timeline created for review with IS Apps and Finance
  • Review of Serengeti Tech and Bus Admin material

 

Issues

  • A risk has been raised on the project regarding the dependency on CMW010 Upgrade Document Management project completing environment upgrades on Serengti system ahead of this project’s activities
  • Due to the availability of Serengti resource not until mid April this may have an impact in the delivery date of this project completing before end of financial year in July, a risk has also been raised on the project relating to this.
  • PICCL issued to WIS to amend planning milestone due to limited availability of Project Manager in February and understanding scope and deliverables against availability of resource

 

Next Steps

  • Approval of Project Brief
  • Commence analysis of documentation information to be provided by Finance

FIN085  (AP01-008)

eTime Phase 3

 

Category:  Compliance

 

Milestones

09-May-2014UAT (for final release) signed off
14-May-2014Delivery
02-Jun-2014Deployment signed off
13-Jun-2014Closure

 

RAG Status:  GREEN

Report by Jill Nicoll for February 2014

Achievements in last period:

Release 6:

Complete Peer Test Plan (see link to Release 6 test document)

Issues:

1.  The complexity of the Batch Processing functionality, and hence of the Release 6 Peer Test Plan, has resulted in the estimate to complete the peer testing (including addressing any testing feedback) increasing from 6 to 15 days of ISA effort. 

2.  During February, the Developer was diverted away from the project to address a high priority Live Finance issue and to support a higher priority Finance project (See Risk 6). 

These combined to extend the project's Peer Testing stage by four weeks, causing the UAT stage to move out to span the Easter holidays.  As a result, the stakeholders requested that the UAT stage be extended by two weeks.  This has resulted in revised milestones and estimates for the project.  (Approved estimate = 206 days, current estimate = 225 days.)  

The HSS-funded effort remains with its "holding measure" estimate and milestone dates.  When estimates have been confirmed, the plan will be adjusted accordingly.

Next Steps:

Release 6:

Complete Peer testing

Deploy to Test

Release for UAT Testing

FIN086 (AP23-004)

ePay Reconciliation

 

Category:  Compliance

 

Milestones

26-Apr-13  Planning

 

 

 

RAG Status:  GREEN

 

Report by Louise Heathcote for February 2014

 

Achievements in this Reporting Period

  • Analysis meeting held with Michael MacMonagle and Liz Welch to agree project scope

Issues

  • Brief has been delayed pending the outcome of the above meeting, now is being drafted for sign off.

Next Steps

  • Issue Brief for sign off
  • Estimate project
  • Complete Business Requirements Document

 

FIN087

Credit Note/Sales Invoice Interface Changes

Category:  Funded

Milestones

Target dateTitle
28-Feb-2014Integration Review
14-Mar-2014Acceptance Review
28-Mar-2014Go-Live
11-Apr-2014Deployment Review
18-Apr-2014Project Closure

RAG Status:  GREEN

Report by Dawn Nicholls for February 2014

Achievements this period

  • Software development completed this month.  Peer testing was undertaken and following some minor re-work the build was signed off.
  • Integration testing is underway though this has highlighted some minor re-work which has delayed the review by a few days

Issues

  • A resource conflict for the developer to allow them to work on a priority JAMS issue plus sickness delayed the build by about 2 weeks. The milestones dates shown on the left reflect the new planned dates.

Next steps

  • Integration review
  • Acceptance testing by Finance

  

Full details on project activities can be seen in the Project Journal

FIN088 (AP12-017)

ERA Decommissioning

 

Category:  Compliance

 

Milestones

 

18-Apr-201420-Dec-2013Integrate Finance Channel Complete
09-May-201424-Jan-2014Acceptance Finance Channel Complete
19-May-201431-Jan-2014Deliver Finance Channel
30-May-201414-Feb-2014Project Closed & Finance Deployment Sign Off

 RAG Status:  AMBER

Report by Louise Heathcote for February 2014

 

Achievements in this Reporting Period

  • Finance Channel changes are in test and integration testing and has been stopped until the investigation into the WPM failtures has been resolved 
  • WPM investigating possible timestamp discrepancy which may be impacting failed transactions.
  • Finance confirmed that failure update errors currently running at 1.87% of transactions

Issues

  • At the issue resolution meeting recognised that the process will never be failure free therefore need to accept a tolerance of errors, one possible solution for Finance Channel is to investigate a means of mopping up failed payments but there is no budget left in this project to deliver

  Next Steps

  • Agree to proceed and finalise the testing of the Finance Channel
  • Gain sign off for new milestones
  • Make Finance Channel live
  • Remove ERA bouncethrough

 

FIN089

eAuthorisations Migration

 

Category:  Compliance & Funded

 

Milestones

 

07-Mar-2014Phase 3 UAT approved
12-Mar-2014Phase 3 Delivery
28-Mar-2014Phase 3 Deployment approved
02-May-2014Phase 4 Build approved
14-May-2014Phase 4 Integration approved
13-Jun-2014Phase 4 UAT approved
19-Jun-2014Phase 4 Delivery
04-Jul-2014Phase 4 Deployment approved
11-Jul-2014Closure

 

 

 

RAG Status:  GREEN

Report by Jill Nicoll for February 2014
 

Achievements in last period:

Phase 2 (IS Apps task):

Complete Jira FIN089-138

Issues:

The project has sufffered a number of delays during this reporting period:

Delay 1, reported 31-Jan:  due to illness, and to a higher than expected number of Integration testing issues.

Delay 2, reported 17-Feb:  due to the unplanned 6.5 days of Developer effort needed to address the Phase 2 post-deployment Jira 138 (linked above), to an increased estimate for Phase 3 UAT support, and to annual leave.

Delay 3, reported 26-Feb:  due to the stakeholders' request for an additional week for UAT testing (also see Risk 11, re. continuing higher priority demands on the Business Area Manager's time).

As a result, the remaining milestones have moved out.

The ISA Development Team Resource Manager has warned that further milestone slippage cannot be permitted, as the Developer is required for an upcoming eExpenses project.  Any further delays will therefore have to be balanced by reducing Phase 4's scope, as will any estimate increases.

Next Steps:

Phase 3 (Business stakeholder tasks):

Complete UAT Test Plan

Complete UAT Testing

Confirm UAT sign-off

Approve Live deployment

Phase 3 (IS Apps task):

Deliver to Live

Phase 4 (IS Apps task):

Complete System Design

FIN091

eFinancials Upgrade Phase 2

Category: Compliance

 Milestones

12 Feb 2014 Sign off Launchpad deliverables
28 Feb 2014Close

 

 

RAG Status:: RED

 Achievements this period

Lessons learned for project closure collected from devtech and appman teams.

SIngle Sign On?Launchpad document drafted and circulated to IS Architecture group and head of IS Applications.

 

Outstanding Issues

Single Sign On/Launchpad deliverables to be approved.

 

Next Steps

Single Sign On/Launchpad deliverables to be approved.

Project to close.

 

The project is RED as the final delivery and closure milestones have been missed and no new milestones agred with the programmem manager or project sponsor.  .

FIN093

Essential Enhancements for Finance Applications

Compliance

Planning - January 2014

Delivery - July 2014

 RAG Status - GREEN

Achievements in Last Period

  • Top 4 enhancements identified
  • Analysis and work started on 3 out of the top 4

Issues

  • none

 

Next Steps

  • Coordinate meeting with ABS and Experian for international account validation
  • Discuss results of analysis and proceed with next steps for PDF Module

 

 

FIN094

SAAS/SLC Reconciliation

Compliance

Milestones

Target dateTitle
21-Mar-2014End of planning
30-Sep-2014Delivery

 RAG Status - AMBER

Report by Dawn Nicholls for February 2014

Achievements this period

  • Initial meeting have taken place with all of the key stakeholder groups involved in the SAAS/SLC fees process: SACS, Registry, FIS, Accounts Payable and Financial Accounts.
  • A draft Project Brief has been drawn up

Issues

  • Concerns have been raised by Financial Accounts about the intention of the project to automatically match the fee lines, which is one of the key objectives for the project.  This has been reported to the Project Sponsor and a meeting requested with all parties to discuss this before the project progresses.  This has delayed the finalising of the Project Brief and the sign-off of the End of Planning phase.  The project is being reported as AMBER until these concerns have been discussed and agreed with the Project Sponsor and key stakeholders.

Next steps

  • Finalise Project Brief
  • Commence system analysis for options appraisal

 

 Full details on project activities can be seen in the Project Journal

 

Section Four: Closed or Withdrawn Projects

 

Project InfoProject Managers Commentary

FIN078

eFin Journal Auto Upload (JAMS)

Category : Discretionary 

Report by Dawn Nicholls

This project was closed on 4th October 2013

Please see the completion report for further information

FIN079

LEAN Review of Financial Systems

Category : Discretionary

Report by Dawn Nicholls

This project was closed on 24th September 2013

Please see the completion report for further information

FIN092

Corporate Planner

Category:  Compliance

Report by Anne Mathison

This project was closed on 20th December 2013

Please see the completion report for further information

FIN076

Student Finance Channel - Further Developments for Staff and Students

Category: Discretionary

Report by Susan McKeown

This project was closed in November 2013.

Please see the completion report for further information

AP34

Migration of BOXI reports

Compliance

Withdrawn - January 2014

AP89-008

FPM for eInvoicing

Withdrawn - January 2014

FIN092

Corporate Planner

Category:  Compliance

Closed - January 2014

 

Section Five: New Approved Projects from 13/14 Annual Plan

Any projects that were approved in previous annual planning rounds and have been postponed to start in 13/14 will be listed under section 2: Projects Not Started. Projects started in 12/13 but which will carry over to 13/14 are listed under section 3: In Progress.

 

 

 

 

 

 

 

 

 

Project InfoProject Managers Commentary

 AP34

Student Fees - Interest Charging on Invoices

Compliance

Planning -

Delivery -

 RAG Status

 Plan

 

Dependencies

 

AP34

Student Fees - SAAS and SLC Fees Reconciliation

Compliance

Planning -

Delivery -

 RAG Status

Plan

 

Dependencies

AP34

Migration of BOXI reports

Compliance

Planning -

Delivery -

 RAG Status

Plan

 

Dependencies

AP34

Essential Enhancements for Finance Applications

Compliance

Planning -

Delivery -

 RAG Status

Plan

 

Dependencies

AP34

eExpenses replacement

Compliance

Planning -

Delivery -

 RAG Status

Plan

 

Dependencies