Report for March 2014

Report Date
March 2014

Report compiled by Rhian Davies (IS Apps Programme Manager) for Liz Welch  (Programme Owner)

Section One: Programme Commentary, and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

Section One: Programme Commentary, and Resources Update  

 

Commentary

Programme on track, no significant concerns.

Two projects at risk (amber):

FIN094 SAAS/SLC - brief not complete yet as Finance need to clarify what the project should deliver

FIN087 Credit Notes/Sales Invoices - rework required following integration testing, need to update plan and secure resources

 

 

Section Two: Projects Not Started

 

Project InfoProgramme Managers Commentary

 AP34

Student Fees - Interest Charging on Invoices

Compliance

Planning - September 2014

Delivery - tbc

 RAG Status - GREEN

 Plan

 

Dependencies

Need to get decision from Fee Strategy Group which meets quarterly - FIS following up on status, but agreed that the project will not start until next year now as FIS resources are allocated to other projects.

 

Section Three: Projects in Progress

 

Project InfoProject Managers Commentary

FIN056 (AP Number)

eProcurement Scotland - eInvoicing

Category: Funded

Milestones

---

---

--- 

RAG Status : SUSPENDED

Report by Rhian Davies for Mar 2014.

Project suspended until 13/14 - meeting held with Finance and Procurement to discuss future of project.  Will know by early May if this project is still required. 

 

FIN080 (12-924)

Customer Interface Improvements

Category: Discretionary

Milestones

Target dateTitle
08-Apr-2014Closure

RAG Status : GREEN

Report by Dawn Nicholls for March 2014

Achievements this period

  • Go-live of new student historic feed and associated Business Objects universe
  • Deployment sign-off

Issues

  • None this period

Next steps

  • Project closure

 Full details on project activities can be seen in the Project Journal

FIN081 (12-024)

Document Management for Finance Applications

Category: Discretionary

Milestones

04-Apr-2014

Agree Scanning Activity Ownership

04-Apr-2014

Finance Document Requirements available

25-Apr-2014

Business Analysis

16-May-2014

Document Scanning Activity Completed

13-Jun-2014

Deploy to Development

11-Jul-2014

Deploy to Test

25-Jul-2014

Deploy to Live

01-Aug-2014

Closure

RAG Status : GREEN

Report by Karen Stirling for March 2014

Achievements in last period

  • Project Brief submitted to WIS
  • Business Analysis / Process Workshop held on 27th March with Finance representatives to discuss requirements for document management and future processes/users
  • Initial list of future potential documents to be scanned created and issued for business review and feedback
  • User personas created and issued out to Finance for review
  • Initial high level document list for Directorate area provided by Finance to start analysis

 

Issues

  • PM concern around availability of document requirements, Finance team have been discussing the disposal the files which are more than 7 years and are no use.  They will need to screen the files (>400 lever arch files) and to arrange them into different groups (dispose, scan and archive).    A new list will be produced once these are done, resulting in a lower number of the files. Finance team members have agreed to help screening the files, dates for this activity to take place have been issued out to members and this is expected to be finished by end of April.  
  • High level estimate costs have been provided by external company DDSR to complete scanning however discussions have still to take place on actual requirements and timescales this requires to be progressed.

 

Next Steps

  • Review future potential scanning documents with other areas identified within Finance
  • Confirm user personas
  • Agree external scanning activity
  • Availability of Directorate documentation to complete business analysis

FIN085  (AP01-008)

eTime Phase 3

 

Category:  Compliance

 

Milestones

09-May-2014UAT (for final release) signed off
14-May-2014Delivery
02-Jun-2014Deployment signed off
13-Jun-2014Closure

 

RAG Status:  GREEN

Report by Jill Nicoll for March 2014

Achievements in last period:

Release 6:

Complete Peer testing

Provide three demo sessions to stakeholders, on the new Batch Processing functionality

Deploy to Test

Release for UAT Testing

Issues:

The continued unavailability of the project's Business Area Manager has resulted in critical delays in the identification and training of UAT testers.  Regression testing by Research colleagues has also been slow to start.  Only the HSS stakeholder group started UAT testing to plan.

The project estimate has increased from 206 to 227 days (see change item 14).  The Project Sponsor and Programme Manager have confirmed that the 21 additional days will be transferred from elsewhere in the Finance Programme budget.

Next Steps:

Release 6:

Progress with UAT and regression testing

HSS-funded enhancement:

Complete Build and Peer test

FIN086 (AP23-004)

ePay Reconciliation

 

Category:  Compliance

 

Milestones

26-Apr-13  Planning

 

 

 

RAG Status:  GREEN

 

Report by Louise Heathcote for March 2014

 

Achievements in this Reporting Period

  • Analysis meeting held with Michael MacMonagle and Liz Welch to agree project scope

Issues

  • Brief has been delayed pending the outcome of the above meeting, now is being drafted for sign off.

Next Steps

  • Issue Brief for sign off
  • Estimate project
  • Complete Business Requirements Document

 

FIN087 (23-058)

Credit Note/Sales Invoice Interface Changes

Category:  Funded

Milestones

Target dateTitle
18-Apr-2014Integration Review
09-May-2014Acceptance Review
26-May-2014Go-Live
09-Jun-2014Deployment Review
16-Jun-2014Project Closure

RAG Status:  AMBER

Report by Dawn Nicholls for March 2014

Achievements this period

  • Re-work and integration testing

Issues

  • Issues detected during integration testing requiring more re-work than anticipated. This has led to an increased estimate and delayed timeline so the project is reported as AMBER.
  • Resource unavailability due to higher priority projects, annual leave, and bereavement leave

Next steps

  • Further re-work and Integration testing
  • UAT

 Full details on project activities can be seen in the Project Journal

FIN088 (AP12-017)

ERA Decommissioning

 

Category:  Compliance

 

Milestones

 

18-Apr-201420-Dec-2013Integrate Finance Channel Complete
09-May-201424-Jan-2014Acceptance Finance Channel Complete
19-May-201431-Jan-2014Deliver Finance Channel
30-May-201414-Feb-2014Project Closed & Finance Deployment Sign Off

 RAG Status:  GREEN

Report by Louise Heathcote for March 2014

 

Achievements in this Reporting Period

  • Finance Channel changes are in test and integration testing and has been stopped until the investigation into the WPM failtures has been resolved 
  • WPM investigating possible timestamp discrepancy which may be impacting failed transactions.
  • Finance confirmed that failure update errors currently running at 1.87% of transactions

Issues

  • At the issue resolution meeting recognised that the process will never be failure free therefore need to accept a tolerance of errors, one possible solution for Finance Channel is to investigate a means of mopping up failed payments but there is no budget left in this project to deliver

  Next Steps

  • Agree to proceed and finalise the testing of the Finance Channel
  • Gain sign off for new milestones
  • Make Finance Channel live
  • Remove ERA bouncethrough

 

FIN089 (34-004)

eAuthorisations Migration

 

Category:  Compliance & Funded

 

Milestones

13-Jun-2014Phase 4 UAT approved
19-Jun-2014Phase 4 Delivery
04-Jul-2014Phase 4 Deployment approved
11-Jul-2014Closure

 

 

 

RAG Status:  GREEN

Report by Jill Nicoll for March 2014
 

Achievements in last period:

Phase 3:

Complete UAT Test Plan and UAT Testing

Confirm UAT sign-off

Deliver to Live

Confirm Live deployment sign-off

Phase 4:

Complete System Design

Issues:

It has been agreed that Phase 4 will deliver iteratively, in a number of small batches.  This will allow the new eTime roles in eAuthorisations to be deployed to Live at the same time as eTime's new Batch Processing functionality.  It will also support the contingency of removing lower priority scope from the project, should the budget require this.  Given the new iterative approach, the Build and Integration milestones for this phase have been removed.  The UAT and Delivery milestones remain unchanged, except that they will now refer to the phase's final batch only.

The project estimate has increased from 362 to 388 days (see change item 21).  The Project Sponsor and Programme Manager have confirmed that the 26 additional days will be transferred from elsewhere in the Finance Programme budget.

Next Steps:

Phase 4:

Batch 1:

Build, peer test, and release for UAT

UAT test and sign off

Batch 2:

Build, peer test, and release for UAT

UAT test and sign off

FIN093

Essential Enhancements for Finance Applications

Compliance

Planning - January 2014

Delivery - July 2014

 RAG Status - GREEN

Report by Steph Ruthven for March 2014

Achievements in Last Period

  • Top 4 enhancements identified
  • Analysis and work started on 3 out of the top 4

Issues

  • none

 

Next Steps

  • Coordinate meeting with ABS and Experian for international account validation
  • Discuss results of analysis and proceed with next steps for PDF Module

 

 

FIN094

SAAS/SLC Reconciliation

Compliance

Milestones

Target dateTitle
18-Apr-2014End of planning
30-Sep-2014Delivery

 RAG Status - AMBER

Report by Dawn Nicholls for March 2014

Achievements this period

  • Draft Project Brief produced and distributed for review

Issues

  • The project scope and deliverables require further clarification which is causing delays to the timeline - hence the project is reported on AMBER 

Next steps

  • Sign-off the Project Brief
  • Business/systems analysis

  

Full details on project activities can be seen in the Project Journal

FIN095

Local Implementation of SSO and Launchpad

Discretionary

28-Apr-201428-Apr-2014End of Planning
10-Jul-201410-Jul-2014Delivery
31-Jul-201431-Jul-2014Close

 

 

Report by Morna Findlay for March 2014

Achievements this period

  •  A kick off and estimation meeting has been held.
  • Initial investigations into integrating shibboleth have been carried out.
  • A meeting with EDINA was held to inform the shibboleth investigations.
  • Delivery of the brief was delayed due to the delay in delivery of the  SSO/Launchpad recommendations  to be delivered by FIN091 
  • These recommendations have been fed into the draft project brief, plan and estimate.
  • Resources for initial phase of project secured.

 

Next Steps

  •  End of planning to be achieved,
  • ABS consultant arranged to work with devtech on implementing Launchpad into DEV

 

 

FIN096

eInvoicing

 

Category:  Funded

 

Milestones

tbc by Project Brief

 

 

RAG Status:  GREEN

Report by Jill Nicoll for March 2014
 
Achievements in last period:
  • Project startup approved.
  • Template Project website generated.
  • Project kick-off meeting with stakeholders scheduled.

Issues:

n/a

Next Steps:

  • Project website to be set up.
  • Project Brief to be created, reviewed by Project Sponsor, and signed off.
  • ISA effort to be estimated.
  • Project milestones to be established.
  • Project plan to be created in Asta, and ISA resources requested.
  • Resources to be secured in both ISA and Finance.

FIN097

Archiving for eFinancials

 

Category:  Funded

 

Milestones

tbc by Project Brief

 

 

RAG Status:  GREEN

Report by Morna Findlay for March 2014
 
Achievements in last period:
  • Project startup approved.
  • Template Project website generated.
  • Project kick-off meeting with stakeholders scheduled.

Issues:

n/a

Next Steps:

  • Project website to be set up.
  • Project Brief to be created, reviewed by Project Sponsor, and signed off.
  • ISA effort to be estimated.
  • Project milestones to be established.
  • Project plan to be created in Asta, and ISA resources requested.
  • Resources to be secured in both ISA and Finance.

 

Section Four: Closed or Withdrawn Projects

 

Project InfoProject Managers Commentary

FIN078

eFin Journal Auto Upload (JAMS)

Category : Discretionary 

Report by Dawn Nicholls

This project was closed on 4th October 2013

Please see the completion report for further information

FIN079

LEAN Review of Financial Systems

Category : Discretionary

Report by Dawn Nicholls

This project was closed on 24th September 2013

Please see the completion report for further information

FIN092

Corporate Planner

Category:  Compliance

Report by Anne Mathison

This project was closed on 20th December 2013

Please see the completion report for further information

FIN076

Student Finance Channel - Further Developments for Staff and Students

Category: Discretionary

Report by Susan McKeown

This project was closed in November 2013.

Please see the completion report for further information

AP34

Migration of BOXI reports

Compliance

Withdrawn - January 2014

AP89-008

FPM for eInvoicing

Withdrawn - January 2014

FIN092

Corporate Planner

Category:  Compliance

Closed - January 2014

FIN091

eFinancials upgrade Phase 2

Category; Compliance

Closed 31/3/14

 

Section Five: New Approved Projects from 13/14 Annual Plan

Any projects that were approved in previous annual planning rounds and have been postponed to start in 13/14 will be listed under section 2: Projects Not Started. Projects started in 12/13 but which will carry over to 13/14 are listed under section 3: In Progress.

 

 

 

 

 

 

 

 

 

 

Project InfoProject Managers Commentary

 AP34

Student Fees - Interest Charging on Invoices

Compliance

Planning -

Delivery -

 RAG Status

 Plan

 

Dependencies

 

AP34

Student Fees - SAAS and SLC Fees Reconciliation

Compliance

Planning -

Delivery -

 RAG Status

Plan

 

Dependencies

AP34

Migration of BOXI reports

Compliance

Planning -

Delivery -

 RAG Status

Plan

 

Dependencies

AP34

Essential Enhancements for Finance Applications

Compliance

Planning -

Delivery -

 RAG Status

Plan

 

Dependencies

AP34

eExpenses replacement

Compliance

Planning -

Delivery -

 RAG Status

Plan

 

Dependencies