Report for November 2013

Report Date
November 2013

Report compiled by Rhian Davies (IS Apps Programme Manager) for Liz Welch  (Programme Owner) - DRAFT

Section One: Programme Commentary, and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

 

Section One: Programme Commentary, and Resources Update  

1. A review of the programme has taken place, and a number of projects are to be withdrawn:

Migration of BOXI Reports - work has taken place under ITS092

FPM for eInvoicing - work will take place under eInvoicing (34-020)

2. This will enable the programme to take forward the single sign on and launchpad implementation in the new year.
3. Resource useage to date is on target

4. A number of new projects will start in Jan/Feb:

eInvoicing

Document Management

SAAS and SLC Fees Reconciliation

ePay Reconciliation

 

 

 

 

 

Section Two: Projects Not Started

 

Project InfoProgramme Managers Commentary

 AP34

Student Fees - Interest Charging on Invoices

Compliance

Planning - January 2014

Delivery - tbc

 RAG Status - AMBER

 Plan

 

Dependencies

Need to get decision from Fee Strategy Group which meets quarterly - FIS following up on status.

No change to timeline from previous report.

AP34

Student Fees - SAAS and SLC Fees Reconciliation

Compliance

Planning - January 2013

Delivery - August 2014

 RAG Status - GREEN

Plan

This project will start in January 2014.

Dependencies

There will be input required from Registry, however this is not required at the beginning of the project.

AP34

Migration of BOXI reports

Compliance

Planning - x

Delivery - x

 RAG Status - AMBER

Agreed at the programme meeting that this project will be withdrawn as the work is being completed under the BOXI upgrade project.

AP34

eExpenses Replacement

Compliance

Planning - tbc

Delivery - tbc

 RAG Status

Plan

 This is the procurement and implementation of a new eExpenses Solution

Dependencies

The direction of this project depends on the outcome of the proof of concept project.

AP89-008

FPM for eInvoicing

 

Discretionary

Planning - x

Delivery - x

RAG Status - AMBER

 

Agreed at the programme meeting that this project will be withdrawn as the work will be completed under the eInvoicing project, with consultancy support.

 

Section Three: Projects in Progress

 

Project InfoProject Managers Commentary

FIN056 (AP Number)

eProcurement Scotland - eInvoicing

Category: Funded

Milestones

---

---

--- 

RAG Status : SUSPENDED

Report by Rhian Davies for June 2013.

Project suspended until 13/14 - resources not available within FIS until the early Autumn.

 

 

FIN076  (AP12-029)

Student Finance Channel - Further Developments for Staff and Students

Category: Discretionary

Milestones

08-Nov-2013Closure

RAG Status : GREEN

Report by Susan McKeown for October 2013

Achievements in Last Period

  • All issues other than call-back intemittent failure resolved
  • Deployment Sign-off achieved
  • Closure process in progress

Issues

  • Remaining call-back issue has been transferred into a Unidesk call with Production Management and is also being progressed under FIN088 where another service is experiencing the same problem.

Next Steps 

  • Close project 

FIN080 (AP Number)

Customer Interface Improvements

Category: Discretionary

Milestones

Target dateTitle
13-Dec-2013Phase 2 - Acceptance Review
16-Dec-2013Phase 2 - Go-live
10-Jan-2014Phase 2 - Deployment Review
17-Jan-2014Closure

RAG Status : GREEN

Report by Dawn Nicholls for November 2013

Achievements this period

  • Project has been replanned
  • Final Jira has been completed and returned to SACS for testing
  • Production Management resource secured to repeat integration testing 

Issues

  • Apps managers are concerned about the revised milestone dates as the go-live is very close to the acceptance sign-off. This may delay the go-live until the new year.

Next steps

  • Integration testing
  • Finance UAT
  • Go-live

Full details on project activities can be seen in the Project Journal

FIN081 (AP Number)

Document Management for Finance Applications

Category: Discretionary

Milestones

---

---

--- 

RAG Status : SUSPENDED

Report by Rhian Davies for October 2013

Project suspended until 13/14.

FIN085  (AP01-008)

eTime Phase 3

 

Category:  Compliance

 

Milestones

07-Feb-2014UAT (for final release) signed off
28-Feb-2014Deployment signed off
07-Mar-2014Closure

 

RAG Status:  GREEN

Report by Jill Nicoll for November 2013

Achievements in last period:

Release 5:

Post-deployment fixes built, signed off in UAT, and deployed to Live

Release 6:

Build progressing to plan

HSS-funded added scope:

Fix deployed to Live

 

Issues:

The Designer has been unable to progress with the HSS-funded enhancement design, because her project time has been fully committed to the post-deployment fixes.  The HSS-funded enhancement work has not yet been estimated, so revised milestones cannot yet be confirmed.

 

Next Steps:

Release 6:

Complete Build and release for Peer testing

HSS-funded added scope:

Complete Enhancement design 

FIN086 (AP23-004)

ePay Reconciliation

 

Category:  Compliance

 

Milestones

26-Apr-13  Planning

 

 

 

RAG Status:  GREEN

 

Report by Rhian Davies for October 2013

Project suspended until 13/14 to enable eAuthorisations to start in 12/13.

 

FIN087

Credit Note/Sales Invoice Interface Changes

Category:  Funded

Milestones

Target dateTitle
22-Nov-2013Design Review
17-Jan-2014Build Review
31-Jan-2014Integration Review
21-Feb-2014Acceptance Review
28-Feb-2014Go-Live
07-Mar-2014Deployment Review
14-Mar-2014Project Closure

RAG Status:  GREEN

Report by Dawn Nicholls for November 2013

Achievements this period

  • Design walk-through took place with key stakeholders from Finance and IS Apps.  Some minor changes were identified and a follow-up walk-through has been arranged.
  • Project has been re-planned, re-estimated and alternative development resource secured to that development can commence. 

Issues

  • Formal design sign-off has been delayed due to annual leave of key staff
  • The most appropriate developer was not available to undertake development until March 2014 due to a higher priority finance project.  An alternative developer has been secured but a small amount of additional resource will be required to 'upskill' them and for mentoring. This additional resource will be sought from IS Apps budget.

Next steps

  • Formalise design sign-off
  • Software development 

 

Full details on project activities can be seen in the Project Journal

FIN088 (AP12-017)

ERA Decommissioning

 

Category:  Compliance

 

 

Milestones

 

20-Dec-201308-Nov-2013Integrate Finance Channel Complete
24-Jan-201415-Nov-2013Acceptance Finance Channel Complete
31-Jan-201418-Nov-2013Deliver Finance Channel
14-Feb-201428-Nov-2013Project Closed & Finance Deployment Sign Off
 

 RAG Status:  AMBER

Report Date: November 2013
Louise Heathcote
 

 

 

Achievements in this Reporting Period

  • Print Credit Deployment signed off with one caveat that there are ongoing investigations into when WPM fails to update Print Credit.
  • Generic Pathway now signed off with WPM

Issues

  • Finance Channel changes testing delayed by implementation of new Finance Infrastructure, testing now scheduled for w/c 9th December
  • Removing the ERA Bouncethrough has been delayed due to issues with the generic pathway set up which have now been resolved
  • Ongoing investigations into failure to update payment issue for Print Credit - Cold Fusion slow to respond to our queries effort to date on issue resolution 6 days

Next Steps

  • Agree new milestones for Integrate, Acceptance and Deployment of Finance Channel
  • Resolve Print Credit issue
  • Remove ERA Bouncethrough
  • Commence test of Finance Channel changes

 

FIN089

eAuthorisations Migration

 

Category:  Compliance

 

Milestones

 

20-Dec-2013Phase 2 UAT approved
08-Jan-2014Phase 2 Delivery
24-Jan-2014Phase 2 Deployment approved
28-Jan-2014Phase 3 Build approved
31-Jan-2014Phase 3 Integration approved
28-Feb-2014Phase 3 UAT approved
05-Mar-2014Phase 3 Delivery
21-Mar-2014Phase 3 Deployment approved
04-Apr-2014Closure

 

 

RAG Status:  GREEN

Report by Jill Nicoll for November 2013
 

Achievements in last period:

Phase 2:

Deployed to Test.

Impact testing completed and signed off.

Integration testing completed and signed off.

Disaster/Recovery testing completed and signed off.

Released for UAT.

Phase 3:

Build progressing.

 

Issues:

The release for UAT of the BOBI universe changes has been delayed by the unexpected loss of the BOBI Dev environment.  This was due to required product patching, for the BOXI Upgrade project.  Further connection issues were encountered after the environment was restored, and these have not yet been resolved.

The new Business Area Manager has proposed substantial new requirements (see scope changes).  It is tentatively assumed that these will be addressed under a new project phase (Phase 4).  The Project Sponsor has confirmed that funding for this phase should be transferred from the two proposals:  Migration of BOXI Reports (50 days including contingency) and FPM for eInvoicing (165 days including contingency).  However, this has still to be confirmed with the Programme Manager and formalised through the Change Log.  Consequently, the Scope status is currently Amber. 

 

Next Steps:

Phase 2:

Complete BOBI universe peer test, integration, UAT and sign-off.

Complete UAT and sign-off.

Phase 3:

Complete Build tasks.

Release for Peer testing.

FIN091

eFinancials Upgrade Phase 2

Category: Compliance

 Milestones

3 Dec 2013SSS Acceptance
16 Dec 2013SSS Delivery
20 Jan 2014Sign off Launchpad deliverables
27 Jan 2013Close

 

 

RAG Status:: AMBER 

Achievements this period

eFinancials database migration deployment review achieved 

DR test carried out

Supplier Self-Service testing signed off  by business.

Project re-estimated

 

Outstanding Issues

DR test to be signed off

New estimate to be agreed.

Supplier Self-Service acceptance to be approved

 

Next Steps

Single Sign On/Launchpad deliverables to be approved.

Supplier Self-Service to be deployed to LIVE

New closure milestone to be agreed.

 

 

The project is AMBER as a new budget  and estimate must be approved.

 

FIN092

Corporate Planner

Category:  Compliance

 

Milestones  

DateStage
9-Dec-2013Technical Design Milestone
16-Dec-2013Deployment Sign Off and Closure

 

 

 RAG Status:  GREEN

 

Report for November 2013 by Anne Mathison

 

The project has been asked to stop and move to closure as the Customer has decided that they are not currently in a position to say the direction they wish to take.

  • This has meant halting the BOXI/EXCEL work and
  • ensuring that the support and technical documentation is complete as possible.
  • Conclusions for the pilot project will be included in the project closure.

 

Achievements this period

  • Obtained Business Requirements for data required from eFin to be loaded into Corporate Planner
  • The options were investigated and initial findings fed back with a number of further questions to the customer
  • Project halted as described above

 

Issues

  • None

 

Next steps
 
  • Complete Service Level Agreement information ensuring all technical documentation is complete
  • Deployment Sign off and Closure report
    • Closure to include conclusions of the pilot project  
 

 

FIN093

Essential Enhancements for Finance Applications

Compliance

Planning - December 2013

Delivery - July 2014

 RAG Status - GREEN

Report by Rhian Davies for November 2013

Project brief due to be complete in December 2013.

 

Section Four: Closed or Withdrawn Projects

 

Project InfoProject Managers Commentary

FIN078

eFin Journal Auto Upload (JAMS)

Category : Discretionary 

Report by Dawn Nicholls

This project was closed on 4th October 2013

Please see the completion report for further information

FIN079

LEAN Review of Financial Systems

Category : Discretionary

Report by Dawn Nicholls

This project was closed on 24th September 2013

Please see the completion report for further information

 

Section Five: New Approved Projects from 13/14 Annual Plan

Any projects that were approved in previous annual planning rounds and have been postponed to start in 13/14 will be listed under section 2: Projects Not Started. Projects started in 12/13 but which will carry over to 13/14 are listed under section 3: In Progress.

 

 

 

 

 

 

 

Project InfoProject Managers Commentary

 AP34

Student Fees - Interest Charging on Invoices

Compliance

Planning -

Delivery -

 RAG Status

 Plan

 

Dependencies

 

AP34

Student Fees - SAAS and SLC Fees Reconciliation

Compliance

Planning -

Delivery -

 RAG Status

Plan

 

Dependencies

AP34

Migration of BOXI reports

Compliance

Planning -

Delivery -

 RAG Status

Plan

 

Dependencies

AP34

Essential Enhancements for Finance Applications

Compliance

Planning -

Delivery -

 RAG Status

Plan

 

Dependencies

AP34

eExpenses replacement

Compliance

Planning -

Delivery -

 RAG Status

Plan

 

Dependencies