Report for October

Report Date
October 2013

Report compiled by Rhian Davies (IS Apps Programme Manager) for Liz Welch  (Programme Owner)

Section One: Programme Commentary, and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

 

 

 

Section One: Programme Commentary, and Resources Update  

1. FIN080: Project requires to be replanned following conflicts with high priority projects. 
2. FIN076: Issues resolved or in progress, revised budget to be approved
3. FIN087: Project requires to be replanned following conflicts with high priority projects. 
4. FIN089: Loss of Lead developer to agile project, revised project budget to be approved
5. FIN091: Revised project budget to be approved

 

 

 

 

 

 

Section Two: Projects Not Started

 

 

Project InfoProgramme Managers Commentary

 AP34

Student Fees - Interest Charging on Invoices

Compliance

Planning - January 2014

Delivery - tbc

 RAG Status - GREEN

 Plan

 

Dependencies

 Need to get decision from Fee Strategy Group which meets quarterly - FIS following up on status.

No change to timeline from previous report.

AP34

Student Fees - SAAS and SLC Fees Reconciliation

Compliance

Planning - December 2013

Delivery - May 2014

 RAG Status - GREEN

Plan

 

Dependencies

There will be input required from Registry, however this is not required at the beginning of the project.

AP34

Migration of BOXI reports

Compliance

Planning - October 2013

Delivery - March 2014

 RAG Status - AMBER

Plan

 

Dependencies

The purpose of this project is to address any issues following the BOXI Upgrade.  Need update from this project to understand if this project is still required.

AP34

Essential Enhancements for Finance Applications

Compliance

Planning - September 2013

Delivery - July 2014

 RAG Status - GREEN

Plan

Planning underway, the project brief will be completed during November. 

Dependencies

AP34

eExpenses Replacement

Compliance

Planning - tbc

Delivery - tbc

 RAG Status

Plan

 This is the procurement and implementation of a new eExpenses Solution

Dependencies

The direction of this project depends on the outcome of the proof of concept project.

AP89-008

FPM for eInvoicing

 

Discretionary

Planning - January 2014

Delivery - July 2014

RAG Status - GREEN

 

Plan

The project is due to start in January 2014.

 

Dependencies

 

Section Three: Projects in Progress

 

 

Project InfoProject Managers Commentary

FIN056 (AP Number)

eProcurement Scotland - eInvoicing

 

Category: Funded

Milestones

---

---

--- 

RAG Status

SUSPENDED

 

Report by Rhian Davies for June 2013.

Project suspended until 13/14 - resources not available within FIS until the early Autumn.

 

 

FIN076  (AP12-029)

Student Finance Channel - Further Developments for Staff and Students

 

Category: Discretionary

Milestones

08-Nov-2013Closure

RAG Status

GREEN

Report by Susan McKeown for October 2013

 

Achievements in Last Period
  • All issues other than call-back intemittent failure resolved
  • Deployment Sign-off achieved
  • Closure process in progress
Issues
  • Remaining call-back issue has been transferred into a Unidesk call with Production Management and is also being progressed under FIN088 where another service is experiencing the same problem.
Next Steps 
  • Close project

 

 

 

 

 

 

FIN080 (AP Number)

Customer Interface Improvements

 

Category: Discretionary

Milestones

 

Target dateTitle
30-Aug-2013Phase 2 - Acceptance
13-Sep-2013Phase 2 - Go-live
20-Sep-2013Phase 2 - Deployment
27-Sep-2013Closure

RAG Status

AMBER

Report by Dawn Nicholls for October 2013

Achievements this period

  • Further work has taken place on the outstanding Jiras from SSP, though not all are complete yet 

Issues

  • Development resource to complete outstanding Jiras due to higher priority projects
  • Lack of clarity on requirements for outstanding Jiras

Next steps

  • Clarify business decision on outstanding Jiras
  • Re-plan remaining milestones
  • UAT by Finance

 

 

 

  

Full details on project activities can be seen in the Project Journal

FIN081 (AP Number)

Document Management for Finance Applications

 

Category: Discretionary

Milestones

---

---

--- 

RAG Status

SUSPENDED

Report by Rhian Davies for October 2013

Project suspended until 13/14.

FIN085  (AP01-008)

eTime Phase 3

 

Category:  Compliance

 

Milestones

 

07-Feb-2014UAT (for final release) signed off
28-Feb-2014Deployment signed off
07-Mar-2014Closure

 

RAG Status:  GREEN

Report by Jill Nicoll for October 2013

Achievements in last period:

ISA:

Deployed Release 5 to Live

Designed Release 6 - Batch Entry functionality

New Developer completed project familiarisation

Stakeholders:

Reviewed and signed off the Design for Release 6

Issues:

The new developer's start date was delayed by two weeks.  This in turn delayed the remaining milestones.

HSS will fund two additional items, one enhancement and one fix.  These have not yet been designed or estimated.  They may further extend milestones.  

Next Steps:

ISA:

Build Release 5 post-deployment fixes; release for UAT; deploy to Live

Progress with Release 6 Build

Stakeholders:

UAT test and sign off Release 5 post-deployment fixes

FIN086 (AP23-004)

ePay Reconciliation

 

Category:  Compliance

 

Milestones

26-Apr-13  Planning

 

 

 

RAG Status:  GREEN

 

Report by Rhian Davies for October 2013

Project suspended until 13/14 to enable eAuthorisations to start in 12/13.

 

FIN087

Credit Note/Sales Invoice Interface Changes

Category:  Funded

 

Milestones

 

Target dateTitle
20-Aug-2013PPDR - Design Review
04-Oct-2013PPBR - Build Review
31-Oct-2013PPIR - Integration Review
07-Nov-2013ASOR: Acceptance Review
11-Nov-2013Deploy to Live
20-Nov-2013DSOR - Deployment Review
28-Nov-2013Project Closure

  

RAG Status:  AMBER

Report by Dawn Nicholls for October 2013

Achievements this period

  • Draft system design has been completed
  • Design walk-through with Finance and support contacts booked for w/c 11/11/13

Issues

  • Securing development resource in Dev Team hence the project is still flagged as Amber status. Remaining milestones will be re-planned once design sign-off has been completed.

Next steps

  • Design sign-off
  • Re-estimation and re-planning
  • Start Build

 

 

FIN088 (AP12-017)

ERA Decommissioning

 

Category:  Compliance

 

 

Milestones

 

06-Sep-2013Integrate Finance Channel Complete
13-Sep-2013Acceptance Finance Channel Complete
04-Nov-2013Deliver Finance Channel
14-Nov-2013DOS Review
28-Nov-2013Project Closed
 

 RAG Status:  GREEN

Report Date: August 2013
Louise Heathcote
 

 

Achievements in this Reporting Period

  • Print Credit Build Deployed pending one issue to be resolved pending sign off
  • OLL Deployment Signed Off
  • JAMS for OLL and Print Credit in live no issues
  • Removal of ERA Bouncethrough scheduled for 1st November

Issues

  • Post go-live issues with Print Credit , investigations underway
  • Finance Channel changes have been awaiting the implementation of FIN076 and then FIN091 before progressing to test. FIN076 now signed of and FIN091 going into live 25th October.

Next Steps

  • Resolve Print Credit issue and sign off deployment
  • Remove ERA Bouncethrough
  • Commence test of Finance Channel changes

 

FIN089

eAuthorisations Migration

 

Category:  Compliance

 

Milestones

 

25-Nov-2013Phase 2 Integration approved
20-Dec-2013Phase 2 UAT approved
08-Jan-2014Phase 2 Delivery
24-Jan-2014Phase 2 Deployment approved
28-Jan-2014Phase 3 Build approved
31-Jan-2014Phase 3 Integration approved
28-Feb-2014Phase 3 UAT approved
05-Mar-2014Phase 3 Delivery
21-Mar-2014Phase 3 Deployment approved
04-Apr-2014Closure

 

 

RAG Status:  Amber

Report by Jill Nicoll for October 2013
 

Achievements in last period:

Phase 1:

Assessed and resolved Phase 1 post-deployment issues.

BOXI:

BOXI R4 issues investigated and resolved.

BOXI R4 Universe deployed to Live.

Phase 2:

Completed Phase 2 batch 1 Build stage.

Performed pre-deployment Impact tests in Test.

 

Issues:

The project has been re-estimated and re-planned following the loss of the Designer as a full-time member of the project team. A 10% support booking will be retained, for the Designer to provide continuing support for the new Developer. The revised estimate, which also takes into account additional time required for post-deployment support for Phase 1, and for complications arising from the BOBI universe implementation, is significantly higher then the available remaining budget.

A request has been submitted to IS Applications managers for 24 days of the increase to be funded from the departmental reorganisation fund, and the Deputy Director has indicated that this request will be approved.  The Programme Manager has indicated that the Programme budget should be able to cover the rest, and that this has been agreed with the Project Sponsor.  However, this has all still to be formally confirmed.  As a result, the Cost and Overall status flags remain Amber. 

The Phase 2 Build sign-off was delayed by two weeks.  Remaining stages have been rescheduled accordingly, with the result that UAT will now run up to the Christmas closure period, with Live deployment early in the New Year.

The Phase 3 top priority business requirement, to improve the look and feel of the User Interface, has not been defined sufficiently to allow its Build to progess.  The Build stage will progress with the remaining requirements, until the required User Interface changes are better defined. 

The Business Area Manager has changed.  However, the new Manager has already been making valuable contributions to the project, and so the transition is expected to be a smooth one. 

 

Next Steps:

Phase 2:

Deploy Phase 2 batch 1 to Test.

Perform post-deployment Phase 2 Impact tests in Test.

Complete Integration testing and sign-off.

Release for UAT.

Phase 3:

Progress with Build. 

 

FIN091

eFinancials Upgrade Phase 2

Category: Compliance

 

 

04- Oct--2013Project Brief ApprovedPlan
09-Oct-2013Sign off EFIN TEST database migrationAccept
09-Oct-2013Sign off DR testing and SSSAccept
21-Oct-2013Prototype SSO/Launchpad deliveredBuild
25-Oct-2013Migrate EFIN LIVE databaseDeliver
30-Oct-2013Sign off Launchpad prototypeAccept
04-Nov-2013DB migration DSORDeliver
11-Nov-2013Close

 

 

RAG STATUS: AMBER

 

 

Achievements this period
  • Acceptance review ( database migration) approved
  • eFinancials database migration delivered
  • Single-Sign-on/Launchpad prototype delivered

 

Outstanding Issues
  • DR test delayed due to lack of resources in UNIX and techman 
  • Supplier Self-Service testing to be completed by business.
  • The project budget is likely to be exseeded. The remaining deliverables to be reviewed in the light of this.

 

Next Steps
  • DR/resilience test  date to be carried out.
  • New estimate to be agreed.
  • Supplier Self-Service testing to be completed and approved and application deployed to LIVE.
  • Single Sign On/Launchpad deliverables to be approved.
  • Deployment sign-off ( database migration) to be approved.

 

The project is AMBER as a new budget  and estimate must be approved.

 

FIN092

Corporate Planner

Category:  Compliance

 

Milestones 

 

04-Oct-2013Technical Design Milestone
09-Oct-2013Application and Infrastructure User Acceptance (LIVE)
18-Oct-2013Release FEC / TRAC Returns
24-Oct-2013Post UAT Release To Users (LIVE)
01-Nov-2013Deployment Sign Off and Closure

 

 RAG Status:  GREEN

 

Report for September 2013 by Anne Mathison

  

Achievements this period

  • Brief was approved at WIS
  • Worked with IS Team and Account Ability to get all set up for 20th September
  • Confirmed and agreed technical requirements for urgent LIVE work
  • Environment in LIVE was set up in preparation for Consultant.
    • He completed the work on 20th September, however there were plenty of issues to jointly resolve until 24th before the Customers could check it out.
  • Customers completed checking LIVE out on 1st October
  • IS Apps completed TAD and Operations Document with required handovers on Oct 4th.
  • Support Live until Return submitted - ongoing  
  • Agreement of funding (agreed - 36 days)

  

Outstanding Issues
  • None

 

Next steps
  • Agree new milestones and plan for new business requirements
  • Obtain Business Requirements for data required from eFin to be loaded into Corporate Planner
    • initial meeting held 9-Oct-13
    • Options to be investigated with estimates for te options investigated
  • Support LIVE until TRAC Return submitted

   

 

Section Four: Closed or Withdrawn Projects

 

Project InfoProject Managers Commentary

FIN078

eFin Journal Auto Upload (JAMS)

Category : Discretionary 

Report by Dawn Nicholls

This project was closed on 4th October 2013

Please see the completion report for further information

FIN079

LEAN Review of Financial Systems

Category : Discretionary

Report by Dawn Nicholls

This project was closed on 24th September 2013

Please see the completion report for further information

 

Section Five: New Approved Projects from 13/14 Annual Plan

Any projects that were approved in previous annual planning rounds and have been postponed to start in 13/14 will be listed under section 2: Projects Not Started. Projects started in 12/13 but which will carry over to 13/14 are listed under section 3: In Progress.

 

 

 

 

 

 

Project InfoProject Managers Commentary

 AP34

Student Fees - Interest Charging on Invoices

Compliance

Planning -

Delivery -

 RAG Status

 Plan

 

Dependencies

 

AP34

Student Fees - SAAS and SLC Fees Reconciliation

Compliance

Planning -

Delivery -

 RAG Status

Plan

 

Dependencies

AP34

Migration of BOXI reports

Compliance

Planning -

Delivery -

 RAG Status

Plan

 

Dependencies

AP34

Essential Enhancements for Finance Applications

Compliance

Planning -

Delivery -

 RAG Status

Plan

 

Dependencies

AP34

eExpenses replacement

Compliance

Planning -

Delivery -

 RAG Status

Plan

 

Dependencies