Report for October
- Report Date
- October 2013
Report compiled by Rhian Davies (IS Apps Programme Manager) for Liz Welch (Programme Owner)
Section One: Programme Commentary, and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, and Resources Update
1. FIN080: Project requires to be replanned following conflicts with high priority projects. |
2. FIN076: Issues resolved or in progress, revised budget to be approved |
3. FIN087: Project requires to be replanned following conflicts with high priority projects. |
4. FIN089: Loss of Lead developer to agile project, revised project budget to be approved |
5. FIN091: Revised project budget to be approved |
Section Two: Projects Not Started
Project Info | Programme Managers Commentary |
AP34 Student Fees - Interest Charging on Invoices Compliance Planning - January 2014 Delivery - tbc RAG Status - GREEN | Plan
Dependencies Need to get decision from Fee Strategy Group which meets quarterly - FIS following up on status. No change to timeline from previous report. |
AP34 Student Fees - SAAS and SLC Fees Reconciliation Compliance Planning - December 2013 Delivery - May 2014 RAG Status - GREEN | Plan
Dependencies There will be input required from Registry, however this is not required at the beginning of the project. |
AP34 Migration of BOXI reports Compliance Planning - October 2013 Delivery - March 2014 RAG Status - AMBER | Plan
Dependencies The purpose of this project is to address any issues following the BOXI Upgrade. Need update from this project to understand if this project is still required. |
AP34 Essential Enhancements for Finance Applications Compliance Planning - September 2013 Delivery - July 2014 RAG Status - GREEN | Plan Planning underway, the project brief will be completed during November. Dependencies |
AP34 eExpenses Replacement Compliance Planning - tbc Delivery - tbc RAG Status | Plan This is the procurement and implementation of a new eExpenses Solution Dependencies The direction of this project depends on the outcome of the proof of concept project. |
AP89-008 FPM for eInvoicing
Discretionary Planning - January 2014 Delivery - July 2014 RAG Status - GREEN |
Plan The project is due to start in January 2014.
Dependencies |
Section Three: Projects in Progress
Project Info | Project Managers Commentary | |||||||||||||||||||||||
FIN056 (AP Number) eProcurement Scotland - eInvoicing
Category: Funded Milestones --- --- --- RAG Status SUSPENDED
| Report by Rhian Davies for June 2013. Project suspended until 13/14 - resources not available within FIS until the early Autumn.
| |||||||||||||||||||||||
FIN076 (AP12-029) Student Finance Channel - Further Developments for Staff and Students
Category: Discretionary Milestones
RAG Status GREEN | Report by Susan McKeown for October 2013 Achievements in Last Period
| |||||||||||||||||||||||
FIN080 (AP Number) Customer Interface Improvements
Category: Discretionary Milestones
RAG Status AMBER | Report by Dawn Nicholls for October 2013 Achievements this period
Issues
Next steps
Full details on project activities can be seen in the Project Journal | |||||||||||||||||||||||
FIN081 (AP Number) Document Management for Finance Applications
Category: Discretionary Milestones --- --- --- RAG Status SUSPENDED | Report by Rhian Davies for October 2013 Project suspended until 13/14. | |||||||||||||||||||||||
FIN085 (AP01-008) eTime Phase 3
Category: Compliance
Milestones
RAG Status: GREEN | Report by Jill Nicoll for October 2013 Achievements in last period: ISA: Deployed Release 5 to Live Designed Release 6 - Batch Entry functionality New Developer completed project familiarisation Stakeholders: Reviewed and signed off the Design for Release 6 Issues: The new developer's start date was delayed by two weeks. This in turn delayed the remaining milestones. HSS will fund two additional items, one enhancement and one fix. These have not yet been designed or estimated. They may further extend milestones. Next Steps: ISA: Build Release 5 post-deployment fixes; release for UAT; deploy to Live Progress with Release 6 Build Stakeholders: UAT test and sign off Release 5 post-deployment fixes | |||||||||||||||||||||||
FIN086 (AP23-004) ePay Reconciliation
Category: Compliance
Milestones 26-Apr-13 Planning
RAG Status: GREEN
| Report by Rhian Davies for October 2013 Project suspended until 13/14 to enable eAuthorisations to start in 12/13.
| |||||||||||||||||||||||
FIN087 Credit Note/Sales Invoice Interface Changes Category: Funded
Milestones
RAG Status: AMBER | Report by Dawn Nicholls for October 2013 Achievements this period
Issues
Next steps
| |||||||||||||||||||||||
FIN088 (AP12-017) ERA Decommissioning
Category: Compliance
Milestones
RAG Status: GREEN | Report Date: August 2013 Louise Heathcote
Achievements in this Reporting Period
Issues
Next Steps
| |||||||||||||||||||||||
FIN089 eAuthorisations Migration
Category: Compliance
Milestones
RAG Status: Amber | Report by Jill Nicoll for October 2013 Achievements in last period: Phase 1: Assessed and resolved Phase 1 post-deployment issues. BOXI: BOXI R4 issues investigated and resolved. BOXI R4 Universe deployed to Live. Phase 2: Completed Phase 2 batch 1 Build stage. Performed pre-deployment Impact tests in Test.
Issues: The project has been re-estimated and re-planned following the loss of the Designer as a full-time member of the project team. A 10% support booking will be retained, for the Designer to provide continuing support for the new Developer. The revised estimate, which also takes into account additional time required for post-deployment support for Phase 1, and for complications arising from the BOBI universe implementation, is significantly higher then the available remaining budget. A request has been submitted to IS Applications managers for 24 days of the increase to be funded from the departmental reorganisation fund, and the Deputy Director has indicated that this request will be approved. The Programme Manager has indicated that the Programme budget should be able to cover the rest, and that this has been agreed with the Project Sponsor. However, this has all still to be formally confirmed. As a result, the Cost and Overall status flags remain Amber. The Phase 2 Build sign-off was delayed by two weeks. Remaining stages have been rescheduled accordingly, with the result that UAT will now run up to the Christmas closure period, with Live deployment early in the New Year. The Phase 3 top priority business requirement, to improve the look and feel of the User Interface, has not been defined sufficiently to allow its Build to progess. The Build stage will progress with the remaining requirements, until the required User Interface changes are better defined. The Business Area Manager has changed. However, the new Manager has already been making valuable contributions to the project, and so the transition is expected to be a smooth one.
Next Steps: Phase 2: Deploy Phase 2 batch 1 to Test. Perform post-deployment Phase 2 Impact tests in Test. Complete Integration testing and sign-off. Release for UAT. Phase 3: Progress with Build.
| |||||||||||||||||||||||
FIN091 eFinancials Upgrade Phase 2 Category: Compliance
RAG STATUS: AMBER
| Achievements this period
Outstanding Issues
Next Steps
The project is AMBER as a new budget and estimate must be approved.
| |||||||||||||||||||||||
FIN092 Corporate Planner Category: Compliance
Milestones
RAG Status: GREEN
| Report for September 2013 by Anne Mathison
Achievements this period
Outstanding Issues
Next steps
|
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
FIN078 eFin Journal Auto Upload (JAMS) Category : Discretionary | Report by Dawn Nicholls This project was closed on 4th October 2013 Please see the completion report for further information |
FIN079 LEAN Review of Financial Systems Category : Discretionary | Report by Dawn Nicholls This project was closed on 24th September 2013 Please see the completion report for further information |
Section Five: New Approved Projects from 13/14 Annual Plan
Any projects that were approved in previous annual planning rounds and have been postponed to start in 13/14 will be listed under section 2: Projects Not Started. Projects started in 12/13 but which will carry over to 13/14 are listed under section 3: In Progress.
Project Info | Project Managers Commentary |
AP34 Student Fees - Interest Charging on Invoices Compliance Planning - Delivery - RAG Status | Plan
Dependencies
|
AP34 Student Fees - SAAS and SLC Fees Reconciliation Compliance Planning - Delivery - RAG Status | Plan
Dependencies |
AP34 Migration of BOXI reports Compliance Planning - Delivery - RAG Status | Plan
Dependencies |
AP34 Essential Enhancements for Finance Applications Compliance Planning - Delivery - RAG Status | Plan
Dependencies |
AP34 eExpenses replacement Compliance Planning - Delivery - RAG Status | Plan
Dependencies |