Report for August 2013 _ DRAFT
- Report Date
- August 2013
Report compiled by Rhian Davies (IS Apps Programme Manager) for Liz Welch (Programme Owner)
Section One: Programme Commentary, and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section Five: New Approved Projects from 13/14 Annual Plan
Section One: Programme Commentary, and Resources Update
Section Two: Projects Not Started
Project Info | Programme Managers Commentary |
AP34 Student Fees - Interest Charging on Invoices Compliance Planning - January 2014 Delivery - tbc RAG Status - GREEN | Plan
Dependencies Need to get decision from Fee Strategy Group which meets quarterly - FIS following up on status. No change to timeline from previous report. |
AP34 Student Fees - SAAS and SLC Fees Reconciliation Compliance Planning - October 2013 Delivery - May 2014 RAG Status - GREEN | Plan
Dependencies There will be input required from Registry, however this is not required at the beginning of the project. |
AP34 Migration of BOXI reports Compliance Planning - October 2013 Delivery - March 2014 RAG Status - GREEN | Plan
Dependencies The purpose of this project is to address any issues following the BOXI Upgrade. |
AP34 Essential Enhancements for Finance Applications Compliance Planning - September 2013 Delivery - July 2014 RAG Status - GREEN | Plan Intially planning required to determine scope for this project - it will include the work required for International Bank Account Validation.
Dependencies |
AP34 eExpenses Replacement Compliance Planning - tbc Delivery - tbc RAG Status | Plan This is the procurement and implementation of a new eExpenses Solution Dependencies The direction of this project depends on the outcome of the proof of concept project. |
AP89-008 FPM for eInvoicing
Discretionary Planning - January 2014 Delivery - July 2014 RAG Status - GREEN |
Plan The project is due to start in January 2014.
Dependencies |
Section Three: Projects in Progress
Project Info | Project Managers Commentary | |||||||||||||||||||||||||||||
FIN056 (AP Number) eProcurement Scotland - eInvoicing
Category: Funded Milestones --- --- --- RAG Status SUSPENDED
| Report by Rhian Davies for June 2013. Project suspended until 13/14 - resources not available within FIS until the early Autumn.
| |||||||||||||||||||||||||||||
FIN076 (AP12-029) Student Finance Channel - Further Developments for Staff and Students
Category: Discretionary Milestones *To be replanned once callback issue estimated*
RAG Status RED | Report by Susan McKeown for August 2013 Achievements in Last Period
| |||||||||||||||||||||||||||||
FIN078 (AP Number) eFin Journal Auto-Upload
Category: Discretionary Milestones
RAG Status GREEN | Report by Dawn Nicholls for August 2013 Achievements this period
Issues
Next steps
Full details can be seen in the Project Journal | |||||||||||||||||||||||||||||
FIN079 (AP Number) LEAN- Review of Financial Systems
Category: Discretionary Milestones
RAG Status GREEN | Report by Dawn Nicholls for August 2013 Achievements this period
Issues
Next steps
Full details can be seen in the Project Journal | |||||||||||||||||||||||||||||
FIN080 (AP Number) Customer Interface Improvements
Category: Discretionary Milestones
RAG Status AMBER | Report by Dawn Nicholls for August 2013 Achievements this period
Issues
Next steps
Full details on project activities can be seen in the Project Journal | |||||||||||||||||||||||||||||
FIN081 (AP Number) Document Management for Finance Applications
Category: Discretionary Milestones --- --- --- RAG Status SUSPENDED | Report by Rhian Davies for June 2013 Project suspended until 13/14. | |||||||||||||||||||||||||||||
FIN083 (AP23-003) eFinancials Upgrade
Category: Compliance Milestones
RAG Status BLUE |
Achievements in this period
The project RAG status has been set to BLUE as the project was closed on 2/8/13 | |||||||||||||||||||||||||||||
FIN085 (AP01-008) eTime Phase 3
Category: Compliance
Milestones
RAG Status: RED | Report by Jill Nicoll for August 2013 Release 3 signed off in UAT and deployed to Live. Release 4 (HSS) signed off in Peer testing, deployed to Test, signed off in UAT and deployed to Live. Actual cost for this HSS funded work is 12 days of ISA effort. First 3 of 4 Release 5 requirements built. Issues:The Batch Processing requirements remain unconfirmed. No progress has been made on this over the past two months. The Development Team has indicated that there is a strong likelihood that the Designer & Lead Developer will be reassigned away from the project. This has been raised as Project Risk 5, and has resulted in the project's RAG status being changed to RED. Next Steps:Stakeholders: UAT test and sign off Release 5 Automatic transfer to Payroll (Release 6) : confirm business requirements Batch Processing functionality (Release 7) : confirm business requirements OR sign off on the Designer's proposed solution ISA: Design Release 5's requirement 4 Build Release 5's requirement 4 Peer test Release 5 Deploy Release 5 to Test and release for UAT testing | |||||||||||||||||||||||||||||
FIN086 (AP23-004) ePay Reconciliation
Category: Compliance
Milestones 26-Apr-13 Planning
RAG Status: GREEN
| Report by Rhian Davies for June 2013 Project suspended until 13/14 to enable eAuthorisations to start in 12/13.
| |||||||||||||||||||||||||||||
FIN087 Credit Note/Sales Invoice Interface Changes Category: Funded
Milestones
RAG Status: AMBER | Report by Dawn Nicholls for August 2013
Achievements this period
Issues
Next steps
| |||||||||||||||||||||||||||||
FIN088 (AP12-017) ERA Decommissioning
Category: Compliance
Milestones
RAG Status: AMBER | Report Date: August 2013 Louise Heathcote
Achievements in this Reporting Period
Issues
Next Steps
| |||||||||||||||||||||||||||||
FIN089 eAuthorisations Migration
Category: Compliance
Milestones
RAG Status: Green | Report by Jill Nicoll for August 2013 Achievements in last period: Phase 1: Some items of Phase 1 UAT testing signed off. Phase 1 UAT and Deployment stages re-planned, per advice from Business Area Manager. Request raised to, and approved by, the Change Advisory Board (CAB) for Phase 1 Live deployment on 19th September (during start-of-term Change Freeze). Live environment set up. BOXI: BOXI universe built and signed off in Peer Testing Phase 2: Phase 2 Business Analysis signed off. Phase 2 System Design signed off. Issues: The BOXI universe was developed in BOXI R2, because the BOXI R4 environment was not yet stable in the Dev environment. Attempts to migrate to Dev R4 have revealed some known issues with R4's support of SQL Server universes. These will be further investigated, and a way forward agreed, in the next period. In the meantime, the universe will be pulished to Test R2, to allow UAT testing to progress. When the issues have been resolved, this project will migrate the eAuthorisations universe to R4 in the Dev and Test environments. The Project Sponsor's request to re-plan Phase 2 to deliver in batches could not be fully met, due to Dev Tech resource constraints during September and early October. As a result, the plan has been adjusted to deliver in two batches only at this time. Further batch break-down will be provided, if this becomes possible. A list of requirements has been sent to the Project Sponsor for prioritisation, to support the batch planning. The re-estimation at the close of the Phase 2 Design stage confirmed a revised project estimate of 259 days, an increase of 12 days over the approved 247 days. The Project Sponsor and Programme Manager have confirmed that this increase will be supplied from elsewhere in the FInance Programme budget (details to be confirmed). Next Steps: Phase 1: Phase 1 UAT testing to be completed and signed off by FIS testing team. Phase 1 Live deployment (contingent upon timely UAT completion and sign-off). BOXI: BOXI Universe to be deployed to Test and released for UAT testing. BOXI Universe to be UAT tested by FIS team. BOXI Universe Live deployment (contingent upon UAT completion and sign-off). Phase 2: Project Sponsor to provide prioritised list of requirements, to support batch planning. Phase 2 batch 1 Build will continue throughout the next period. | |||||||||||||||||||||||||||||
FIN091 Edinancials Upgrade Phase 2 Category: Compliance
RAG STATUS: AMBER
| Report by Morna Findlay for August 2013 Achievements this periodInitial kick-off project meeting held Project team established Initial draft project brief, estimate and plan published Approval for IS applications to continue work on database migration befor brief approved agreed by WIS. Supplier Self-Service application signed off on DEV by Finance Database migrated to test. Testing of database DEV migration continues. DR/resilience recommendations provided to Finance Outstanding Issues Estimate, Brief and plan not approved. Trigger/dataguard resolution not yet approved by ABS FIS test plan not received. Unclear how Supplier Self Service can be tested in TEST by a supplier. Next Steps Approve project brief, estimate and plan DR/resilience requirements to be finalised by Business.
The project is AMBERas the brief has not yet been approved, | |||||||||||||||||||||||||||||
FIN092 Corporate Planner
Category: Compliance
Milestones
RAG Status: GREEN | Report for August 2013 by Anne Mathison Achievements this period
Outstanding Issues
Next steps
|
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
FIN082 HMRC Real Time Information Compliance | Report by Jill Nicol This project was closed on 10-Aug-2010 Please see the Completion Report for further information. |
AP23-055 Rolling out Finance BOXI Reports
Funded | Report by Rhian Davies This project was withdrawn from the 12/13 programme. |
FIN072 (AP01-008) eTime
Category: Compliance | Report by Jill Nicol This project was closed on 30-Nov-12. Please see the Completion Report for further information. |
FIN077 Control Account Balancing
Category: /Compliance | Report by Sue Woodger This project was closed 1 February 2013 Please see the Completion Report |
FIN084 eStores Rollout Category : Discretionary
| Report by Dawn Nicholls This project was closed on 20th December 2012 Please see the Completion Report for further information |
FIN083 Efinancials upgrade Vategory:Compliance | Report by Rhian Davies This project was closed on 17/7/13 Please see the completion report for further details. |
Section Five: New Approved Projects from 13/14 Annual Plan
Any projects that were approved in previous annual planning rounds and have been postponed to start in 13/14 will be listed under section 2: Projects Not Started. Projects started in 12/13 but which will carry over to 13/14 are listed under section 3: In Progress.
Project Info | Project Managers Commentary |
AP34 Student Fees - Interest Charging on Invoices Compliance Planning - Delivery - RAG Status | Plan
Dependencies
|
AP34 Student Fees - SAAS and SLC Fees Reconciliation Compliance Planning - Delivery - RAG Status | Plan
Dependencies |
AP34 Migration of BOXI reports Compliance Planning - Delivery - RAG Status | Plan
Dependencies |
AP34 Essential Enhancements for Finance Applications Compliance Planning - Delivery - RAG Status | Plan
Dependencies |
AP34 eExpenses replacement Compliance Planning - Delivery - RAG Status | Plan
Dependencies |