Report for July 2013 - Draft

Report Date
July 2013

Report compiled by Rhian Davies (IS Apps Programme Manager) for Liz Welch  (Programme Owner)

Section One: Programme Commentary, and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

Section Five: New Approved Projects from 13/14 Annual Plan

 

 

Section One: Programme Commentary, and Resources Update  

 

 

 

 

Section Two: Projects Not Started

 

Project InfoProgramme Manager's Commentary

AP23-056

International Bank Validation

 

Funded 

Planning June 2013

RAG Status

AMBER

Plan

The funding for this project has been withdrawn, effective 31st July.

FIS are currently in discussion with a software supplier about a product which could deliver the objectives of this project.  Apps are providing technical input, and it is hoped that a solution can be found which requires limited Apps effort.

This project will either be withdrawn, or will continue at a much reduced size, funded out of the core funded days within the Finance programme budget.

AP89-008

FPM for eInvoicing

 

Discretionary

Planning tbc

Delivery tbc

RAG Status

GREEN 

Plan

 This project has been delayed to 13/14 following the Mid Year Review.

 

Dependencies

 

 

Section Three: Projects in Progress

 

 

Project InfoProject Managers Commentary

FIN056 (AP Number)

eProcurement Scotland - eInvoicing

 

Category: Funded

Milestones

---

---

--- 

RAG Status

SUSPENDED

 

Report by Rhian Davies for June 2013.

Project suspended until 13/14 - resources not available within FIS until the early Autumn.

 

 

FIN076  (AP12-029)

Student Finance Channel - Further Developments for Staff and Students

 

Category: Discretionary

Milestones

  

12-Aug-2013Deployment review
23-Aug-2013Closure

RAG Status

GREEN

Report by Susan McKeown for July 2013

 

Achievements in Last Period
    • Work identified in the Integration and Acceptance sign-off was completed
    • The new Finance channel delpoyed to LIVE
    • Closure feedback has been requested
Issues
  • There was an unexpected absence from Finance which postponed the project's delivery. This has meant that the project will now carryover the final tasks into the next financial year.
  • There were some issues raised which were resolved. There are two known queries students just reported that are being investigated. It is unclear at this stage if these are bugs.
Next Steps
  • Deployment Sign-off
  • Closure

 

 

 

 

 

 

FIN078 (AP Number)

eFin Journal Auto-Upload

 

Category: Discretionary

Milestones

 

Target dateTitle
20-Aug-2013Go-live
27-Aug-2013Deployment sign-off
03-Sep-2013Closure

RAG Status

GREEN

Report by Dawn Nicholls for July 2013

 

Achievements this period

  • Development and testing of delegate registration vat coding change ready for go-live

Issues

  • Additional requirement from Project Sponsor has delayed the go-live

Next steps

  • Development & testing of new requirement
  • Rescheduled go-live

 

Full details can be seen in the Project Journal

FIN079 (AP Number)

LEAN- Review of Financial Systems

 

Category: Discretionary

Milestones

 

Target dateTitle
30-Aug-2013Delivery - workpackage 2 (eIT enhancements)
30-Aug-2013Delivery - workpackage 14 (eIT transfer queue)
06-Sep-2013Closure
 

RAG Status

GREEN

Report by Dawn Nicholls for July 2013

Achievements

  • Further work undetaken on the Serengeti and BOXI worlpackages.

Issues

  • eFin Upgrade project are planning to move the test database which may disrupt development and testing
  • Potential issues securing resources from Dev Tech for deployment
  • Due to lack of resource availability delaying progress, the project will now extend into early 13/14

Next steps

  • Complete eIT changes for workpackages 2 and 14
  • FIS acceptance testing

 

Full details can be seen in the Project Journal

FIN080 (AP Number)

Customer Interface Improvements

 

Category: Discretionary

Milestones

 

Target dateTitle
30-Aug-2013Phase 2 - Acceptance
13-Sep-2013Phase 2 - Go-live
20-Sep-2013Phase 2 - Deployment
27-Sep-2013Closure
  

RAG Status

GREEN

Report by Dawn Nicholls for July 2013

Achievements this period

  •  SACS testing of the new historic feed interface

Issues

  •  There have been a significant number of issues raised during the SACS testing which have needed to be addressed

Next steps

  • FIS acceptance testing

  

Full details on project activities can be seen in the Project Journal

FIN081 (AP Number)

Document Management for Finance Applications

 

Category: Discretionary

Milestones

---

---

--- 

RAG Status

SUSPENDED

Report by Rhian Davies for June 2013

Project suspended until 13/14.

FIN083  (AP23-003)

eFinancials Upgrade

 

Category: Compliance

Milestones

 

 

  
17-Jul-13Closure

 

RAG Status

BLUE

 

Achievements in this period

 

  1. DEV database migration largely completed

  2. Project closed

  3. Outstanding deliverables transferred to new project code (FIN091)

 

The project RAG status has been set to BLUE as  the project was closed on 2/8/13

 

FIN085  (AP01-008)

eTime Phase 3

 

Category:  Compliance

 

Milestones

 

18-Oct-2013UAT (for final release) signed off
13-Nov-2013Deployment signed off
22-Nov-2013Closure

 

 

RAG Status:  GREEN 

Report by Jill Nicoll for June 2013

 
Achievements in last period:
  1. Release 1 signed off in UAT and deployed to Live.
  2. Release 2 signed off in Peer testing, deployed to Test, and released for UAT.
Issues:
  1. Batch Processing requirements remain unconfirmed.
  2. HSS have agreed to fund the estimated 30 days to deliver the four of the non-top priority HTBN requirements.   HSS are willing for this work to be done during the current planning year, to provide extra time for Finance to determine the Batch Processing requirements, but to be billed in the next planning year, to reduce the impact on Finance's 2013-14 annual budget.  This proposal is with the Programme Manager, for consideration. 
Next Steps:

Stakeholders:

UAT test and sign off Release 2

Batch Processing functionality : confirm business requirements / sign off on the proposed soluton

ISA:

Deploy Release 2 to Live 

Design Batch Processing functionality

 

FIN086 (AP23-004)

ePay Reconciliation

 

Category:  Compliance

 

Milestones

26-Apr-13  Planning

 

 

 

RAG Status:  GREEN

 

Report by Rhian Davies for June 2013

Project suspended until 13/14 to enable eAuthorisations to start in 12/13.

 

FIN087

Credit Note/Sales Invoice Interface Changes

Category:  Funded

 

Milestones

 

Target dateTitle
24-Jul-2013Project Brief
30-Jul-2013PPAR: Analysis Review
20-Aug-2013PPDR - Design Review
04-Oct-2013PPBR - Build Review

   

 

 

RAG Status:  AMBER

Report by Laura Bell for July 2013

 

Achievements in Last Period

  • Revised Project Brief completed and signed off to reflect new scope
  • Business requirements revised and signed off to reflect new scope 

 

Issues

  • Source of project funding position for 2013/14 to be confirmed by Finance.

Next Steps

  • Complete the design and commence the build of the new functionality

 

FIN088 (AP12-017)

ERA Decommissioning

 

Category:  Compliance

 

 

Milestones

29-Jul-2013 Build Finance Channel Complete Build    
06-Aug-2013 Integrate Finance Channel Complete Integrate    
12-Aug-2013 Acceptance Finance Channel Complete Accept    
12-Aug-2013 Build PCounter Complete Build    
19-Aug-2013 Deliver Finance Channel Deliver    
20-Aug-2013 Integrate PCounter Complete Integrate    
28-Aug-2013 Acceptance PCounter Complete Accept    
29-Aug-2013 Deliver PCounter Deliver    
16-Sep-2013 Project Closed Close  

 

 

RAG Status:  AMBER

Report Date: July 2013
Louise Heathcote
 

Achievements in this Reporting Period

  • OLLIE Deployed
  • Print Credit Build Complete and awaiting sign off
  • Finance Channel ready for build to commence

Issues

  • Print Credit has a hard deployment date of 28th August and a full roll back in test will need to be completed so timescales are tight
  • Finance Channel delayed due to delays in deploying FIN076 also they have an additional requirement from FIN076 which will increase cost of project needs to be estimated and signed off and the milestones re baselined
  • JAMs not signed off in live so awaiting final sign off

Next Steps

  • Complete Integrate and Test for PCounter
  • Define and agree additional Finance Channel Requirement and start build

 

 

FIN089

eAuthorisations Migration

 

Category:  Compliance

 

Milestones

 

 

Note:   The milestones below are based on the ToR estimates, and do not reflect secured resources.  When resource availability is taken into account, these milestones may have to change.

 

 

28-Jun-2013Phase 1 Build approved
24-Jul-2013Phase 1 Integration approved
24-Jul-2013Phase 2 Analysis approved
05-Aug-2013Phase 2 Design approved
19-Aug-2013Phase 1 UAT sign-off
23-Aug-2013Phase 1 Delivery
06-Sep-2013Phase 1 Deployment approved
18-Oct-2013Phase 2 Build approved
18-Oct-2013Phase 3 Business Analysis approved
25-Nov-2013Phase 2 Integration approved
10-Jan-2014Phase 2 UAT approved
17-Jan-2014Phase 4 Analysis signed off
20-Jan-2014Phase 2 Delivery
03-Feb-2014Phase 2 Deployment approved
07-Feb-2014Closure

 

 

RAG Status:  Green

Report Date: 

June 2013

 

Achievements in last period:

Project ToR reviewed with Project Sponsor, agreed changes applied, and ToR signed off.

Remaining ISA estimates provided.  Project estimate of 247 days approved.

Phase 1 Build completed.

Issues:

Finance's eAuthorisations designer/developer has now left the University. 

Next Steps:

Phase 1 Integration to Test and Integration Testing 

Phase 1 to be released for User Acceptance Testing

Phase 2 Business Analysis to be completed

 

 

Section Four: Closed or Withdrawn Projects

 

Project InfoProject Managers Commentary

FIN082

HMRC Real Time Information

Compliance 

Report by Jill Nicol

This project was closed on 10-Aug-2010

Please see the Completion Report for further information.  

AP23-055

Rolling out Finance BOXI Reports

 

Funded 

Report by Rhian Davies

This project was withdrawn from the 12/13 programme.

FIN072 (AP01-008)

eTime

 

Category: Compliance

Report by Jill Nicol

This project was closed on 30-Nov-12.

Please see the Completion Report for further information.

FIN077

Control Account Balancing

 

Category: /Compliance

Report by Sue Woodger 

This project was closed 1 February 2013

Please see the Completion Report

FIN084

eStores Rollout

Category : Discretionary

 

Report by Dawn Nicholls

This project was closed on 20th December 2012

Please see the Completion Report for further information

 

FIN083

Efinancials upgrade

Vategory:Compliance

Report by Rhian Davies

This project was closed on 17/7/13

Please see the completion report for further details.

 

Section Five: New Approved Projects from 13/14 Annual Plan

Any projects that were approved in previous annual planning rounds and have been postponed to start in 13/14 will be listed under section 2: Projects Not Started. Projects started in 12/13 but which will carry over to 13/14 are listed under section 3: In Progress.

 

 

 

 

 

Project InfoProject Managers Commentary

 AP34

Student Fees - Interest Charging on Invoices

Compliance

Planning -

Delivery -

 RAG Status

 Plan

 

Dependencies

 

AP34

Student Fees - SAAS and SLC Fees Reconciliation

Compliance

Planning -

Delivery -

 RAG Status

Plan

 

Dependencies

AP34

Migration of BOXI reports

Compliance

Planning -

Delivery -

 RAG Status

Plan

 

Dependencies

AP34

Essential Enhancements for Finance Applications

Compliance

Planning -

Delivery -

 RAG Status

Plan

 

Dependencies

AP34

eExpenses replacement

Compliance

Planning -

Delivery -

 RAG Status

Plan

 

Dependencies