Report for July 2013 - Draft
- Report Date
- July 2013
Report compiled by Rhian Davies (IS Apps Programme Manager) for Liz Welch (Programme Owner)
Section One: Programme Commentary, and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section Five: New Approved Projects from 13/14 Annual Plan
Section One: Programme Commentary, and Resources Update
Section Two: Projects Not Started
Project Info | Programme Manager's Commentary |
AP23-056 International Bank Validation
Funded Planning June 2013 RAG Status AMBER | Plan The funding for this project has been withdrawn, effective 31st July. FIS are currently in discussion with a software supplier about a product which could deliver the objectives of this project. Apps are providing technical input, and it is hoped that a solution can be found which requires limited Apps effort. This project will either be withdrawn, or will continue at a much reduced size, funded out of the core funded days within the Finance programme budget. |
AP89-008 FPM for eInvoicing
Discretionary Planning tbc Delivery tbc RAG Status GREEN | Plan This project has been delayed to 13/14 following the Mid Year Review.
Dependencies
|
Section Three: Projects in Progress
Project Info | Project Managers Commentary | ||||||||||||||||||||||||||||||||||||||||||||||||||||
FIN056 (AP Number) eProcurement Scotland - eInvoicing
Category: Funded Milestones --- --- --- RAG Status SUSPENDED
| Report by Rhian Davies for June 2013. Project suspended until 13/14 - resources not available within FIS until the early Autumn.
| ||||||||||||||||||||||||||||||||||||||||||||||||||||
FIN076 (AP12-029) Student Finance Channel - Further Developments for Staff and Students
Category: Discretionary Milestones
RAG Status GREEN | Report by Susan McKeown for July 2013 Achievements in Last Period
| ||||||||||||||||||||||||||||||||||||||||||||||||||||
FIN078 (AP Number) eFin Journal Auto-Upload
Category: Discretionary Milestones
RAG Status GREEN | Report by Dawn Nicholls for July 2013
Achievements this period
Issues
Next steps
Full details can be seen in the Project Journal | ||||||||||||||||||||||||||||||||||||||||||||||||||||
FIN079 (AP Number) LEAN- Review of Financial Systems
Category: Discretionary Milestones
RAG Status GREEN | Report by Dawn Nicholls for July 2013 Achievements
Issues
Next steps
Full details can be seen in the Project Journal | ||||||||||||||||||||||||||||||||||||||||||||||||||||
FIN080 (AP Number) Customer Interface Improvements
Category: Discretionary Milestones
RAG Status GREEN | Report by Dawn Nicholls for July 2013 Achievements this period
Issues
Next steps
Full details on project activities can be seen in the Project Journal | ||||||||||||||||||||||||||||||||||||||||||||||||||||
FIN081 (AP Number) Document Management for Finance Applications
Category: Discretionary Milestones --- --- --- RAG Status SUSPENDED | Report by Rhian Davies for June 2013 Project suspended until 13/14. | ||||||||||||||||||||||||||||||||||||||||||||||||||||
FIN083 (AP23-003) eFinancials Upgrade
Category: Compliance Milestones
RAG Status BLUE |
Achievements in this period
The project RAG status has been set to BLUE as the project was closed on 2/8/13 | ||||||||||||||||||||||||||||||||||||||||||||||||||||
FIN085 (AP01-008) eTime Phase 3
Category: Compliance
Milestones
RAG Status: GREEN | Report by Jill Nicoll for June 2013
Stakeholders: UAT test and sign off Release 2 Batch Processing functionality : confirm business requirements / sign off on the proposed soluton ISA: Deploy Release 2 to Live Design Batch Processing functionality
| ||||||||||||||||||||||||||||||||||||||||||||||||||||
FIN086 (AP23-004) ePay Reconciliation
Category: Compliance
Milestones 26-Apr-13 Planning
RAG Status: GREEN
| Report by Rhian Davies for June 2013 Project suspended until 13/14 to enable eAuthorisations to start in 12/13.
| ||||||||||||||||||||||||||||||||||||||||||||||||||||
FIN087 Credit Note/Sales Invoice Interface Changes Category: Funded
Milestones
RAG Status: AMBER | Report by Laura Bell for July 2013
Achievements in Last Period
Issues
Next Steps
| ||||||||||||||||||||||||||||||||||||||||||||||||||||
FIN088 (AP12-017) ERA Decommissioning
Category: Compliance
Milestones
RAG Status: AMBER | Report Date: July 2013 Louise Heathcote Achievements in this Reporting Period
Issues
Next Steps
| ||||||||||||||||||||||||||||||||||||||||||||||||||||
FIN089 eAuthorisations Migration
Category: Compliance
Milestones
Note: The milestones below are based on the ToR estimates, and do not reflect secured resources. When resource availability is taken into account, these milestones may have to change.
RAG Status: Green | Report Date: June 2013 Achievements in last period: Project ToR reviewed with Project Sponsor, agreed changes applied, and ToR signed off. Remaining ISA estimates provided. Project estimate of 247 days approved. Phase 1 Build completed. Issues: Finance's eAuthorisations designer/developer has now left the University. Next Steps: Phase 1 Integration to Test and Integration Testing Phase 1 to be released for User Acceptance Testing Phase 2 Business Analysis to be completed
|
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
FIN082 HMRC Real Time Information Compliance | Report by Jill Nicol This project was closed on 10-Aug-2010 Please see the Completion Report for further information. |
AP23-055 Rolling out Finance BOXI Reports
Funded | Report by Rhian Davies This project was withdrawn from the 12/13 programme. |
FIN072 (AP01-008) eTime
Category: Compliance | Report by Jill Nicol This project was closed on 30-Nov-12. Please see the Completion Report for further information. |
FIN077 Control Account Balancing
Category: /Compliance | Report by Sue Woodger This project was closed 1 February 2013 Please see the Completion Report |
FIN084 eStores Rollout Category : Discretionary
| Report by Dawn Nicholls This project was closed on 20th December 2012 Please see the Completion Report for further information |
FIN083 Efinancials upgrade Vategory:Compliance | Report by Rhian Davies This project was closed on 17/7/13 Please see the completion report for further details. |
Section Five: New Approved Projects from 13/14 Annual Plan
Any projects that were approved in previous annual planning rounds and have been postponed to start in 13/14 will be listed under section 2: Projects Not Started. Projects started in 12/13 but which will carry over to 13/14 are listed under section 3: In Progress.
Project Info | Project Managers Commentary |
AP34 Student Fees - Interest Charging on Invoices Compliance Planning - Delivery - RAG Status | Plan
Dependencies
|
AP34 Student Fees - SAAS and SLC Fees Reconciliation Compliance Planning - Delivery - RAG Status | Plan
Dependencies |
AP34 Migration of BOXI reports Compliance Planning - Delivery - RAG Status | Plan
Dependencies |
AP34 Essential Enhancements for Finance Applications Compliance Planning - Delivery - RAG Status | Plan
Dependencies |
AP34 eExpenses replacement Compliance Planning - Delivery - RAG Status | Plan
Dependencies |