Report for June 2013 - DRAFT
- Report Date
- June 2013
Report compiled by Rhian Davies (IS Apps Programme Manager) for Liz Welch (Programme Owner)
Section One: Programme Commentary, and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section Five: New Approved Projects from 13/14 Annual Plan
Section One: Programme Commentary, and Resources Update
Section Two: Projects Not Started
Project Info | Programme Manager's Commentary |
AP23-056 International Bank Validation
Funded Planning June 2013 RAG Status AMBER | Plan The funding for this project has been withdrawn, effective 31st July. FIS are currently in discussion with a software supplier about a product which could deliver the objectives of this project. Apps are providing technical input, and it is hoped that a solution can be found which requires limited Apps effort. This project will either be withdrawn, or will continue at a much reduced size, funded out of the core funded days within the Finance programme budget. |
AP89-008 FPM for eInvoicing
Discretionary Planning tbc Delivery tbc RAG Status GREEN | Plan This project has been delayed to 13/14 following the Mid Year Review.
Dependencies
|
Section Three: Projects in Progress
Project Info | Project Managers Commentary | ||||||||||||||||||||||||||||||||||||||
FIN056 (AP Number) eProcurement Scotland - eInvoicing
Category: Funded Milestones --- --- --- RAG Status SUSPENDED
| Report by Rhian Davies for June 2013. Project suspended until 13/14 - resources not available within FIS until the early Autumn.
| ||||||||||||||||||||||||||||||||||||||
FIN076 (AP12-029) Student Finance Channel - Further Developments for Staff and Students
Category: Discretionary Milestones
RAG Status GREEN | Report by Susan McKeown for June 2013 Achievements in Last Period
| ||||||||||||||||||||||||||||||||||||||
FIN078 (AP Number) eFin Journal Auto-Upload
Category: Discretionary Milestones
RAG Status GREEN | Report by Dawn Nicholls for June 2013 Achievements
Issues
Next Steps
Full details can be seen in the Project Journal | ||||||||||||||||||||||||||||||||||||||
FIN079 (AP Number) LEAN- Review of Financial Systems
Category: Discretionary Milestones
RAG Status GREEN | Report by Dawn Nicholls for June 2013 Achievements
Issues
Next Steps
Full details can be seen in the Project Journal | ||||||||||||||||||||||||||||||||||||||
FIN080 (AP Number) Customer Interface Improvements
Category: Discretionary Milestones
RAG Status GREEN | Report by Dawn Nicholls for June 2013 Achievements
Issues
Next Steps
Full details on project activities can be seen in the Project Journal | ||||||||||||||||||||||||||||||||||||||
FIN081 (AP Number) Document Management for Finance Applications
Category: Discretionary Milestones --- --- --- RAG Status SUSPENDED | Report by Rhian Davies for June 2013 Project suspended until 13/14. | ||||||||||||||||||||||||||||||||||||||
FIN083 (AP23-003) eFinancials Upgrade
Category: Compliance Milestones
RAG Status AMBER |
Report by Morna Findlay for Rhian Davies for June 2013 Achievements in this period
Outstanding Issues
From DSOR
Issues not included in DSOR
Next Steps
The project RAG status has been set to AMBER as milestones need to be agreed for the database migration. | ||||||||||||||||||||||||||||||||||||||
FIN085 (AP01-008) eTime Phase 3
Category: Compliance
Milestones
RAG Status: GREEN | Report by Jill Nicoll for June 2013
Stakeholders: UAT test and sign off Release 2 Batch Processing functionality : confirm business requirements / sign off on the proposed soluton ISA: Deploy Release 2 to Live Design Batch Processing functionality
| ||||||||||||||||||||||||||||||||||||||
FIN086 (AP23-004) ePay Reconciliation
Category: Compliance
Milestones 26-Apr-13 Planning
RAG Status: GREEN
| Report by Rhian Davies for June 2013 Project suspended until 13/14 to enable eAuthorisations to start in 12/13.
| ||||||||||||||||||||||||||||||||||||||
FIN087 Credit Note/Sales Invoice Interface Changes Category: Funded
Milestones
RAG Status: AMBER | Report by Laura Bell for April 2013
Achievements in Last Period
Issues
Next Steps
| ||||||||||||||||||||||||||||||||||||||
FIN088 (AP12-017) ERA Decommissioning
Category: Compliance
Milestones
RAG Status: GREEN | Report Date: June 2013 Louise Heathcote Achievements in this Reporting Period
Issues
Next Steps
| ||||||||||||||||||||||||||||||||||||||
FIN089 eAuthorisations Migration
Category: Compliance
Milestones
Note: The milestones below are based on the ToR estimates, and do not reflect secured resources. When resource availability is taken into account, these milestones may have to change.
RAG Status: Green | Report Date: June 2013 Achievements in last period: Project ToR reviewed with Project Sponsor, agreed changes applied, and ToR signed off. Remaining ISA estimates provided. Project estimate of 247 days approved. Phase 1 Build completed. Issues: Finance's eAuthorisations designer/developer has now left the University. Next Steps: Phase 1 Integration to Test and Integration Testing Phase 1 to be released for User Acceptance Testing Phase 2 Business Analysis to be completed
|
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
FIN082 HMRC Real Time Information Compliance | Report by Jill Nicol This project was closed on 10-Aug-2010 Please see the Completion Report for further information. |
AP23-055 Rolling out Finance BOXI Reports
Funded | Report by Rhian Davies This project was withdrawn from the 12/13 programme. |
FIN072 (AP01-008) eTime
Category: Compliance | Report by Jill Nicol This project was closed on 30-Nov-12. Please see the Completion Report for further information. |
FIN077 Control Account Balancing
Category: /Compliance | Report by Sue Woodger This project was closed 1 February 2013 Please see the Completion Report |
FIN084 eStores Rollout Category : Discretionary
| Report by Dawn Nicholls This project was closed on 20th December 2012 Please see the Completion Report for further information |
Section Five: New Approved Projects from 13/14 Annual Plan
Any projects that were approved in previous annual planning rounds and have been postponed to start in 13/14 will be listed under section 2: Projects Not Started. Projects started in 12/13 but which will carry over to 13/14 are listed under section 3: In Progress.
Project Info | Project Managers Commentary |
AP34 Student Fees - Interest Charging on Invoices Compliance Planning - Delivery - RAG Status | Plan
Dependencies
|
AP34 Student Fees - SAAS and SLC Fees Reconciliation Compliance Planning - Delivery - RAG Status | Plan
Dependencies |
AP34 Migration of BOXI reports Compliance Planning - Delivery - RAG Status | Plan
Dependencies |
AP34 Essential Enhancements for Finance Applications Compliance Planning - Delivery - RAG Status | Plan
Dependencies |
AP34 eExpenses replacement Compliance Planning - Delivery - RAG Status | Plan
Dependencies |