Report for June 2013 - DRAFT

Report Date
June 2013

Report compiled by Rhian Davies (IS Apps Programme Manager) for Liz Welch  (Programme Owner)

Section One: Programme Commentary, and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

Section Five: New Approved Projects from 13/14 Annual Plan

 

Section One: Programme Commentary, and Resources Update  

 

 

 

 

Section Two: Projects Not Started

 

Project InfoProgramme Manager's Commentary

AP23-056

International Bank Validation

 

Funded 

Planning June 2013

RAG Status

AMBER

Plan

The funding for this project has been withdrawn, effective 31st July.

FIS are currently in discussion with a software supplier about a product which could deliver the objectives of this project.  Apps are providing technical input, and it is hoped that a solution can be found which requires limited Apps effort.

This project will either be withdrawn, or will continue at a much reduced size, funded out of the core funded days within the Finance programme budget.

AP89-008

FPM for eInvoicing

 

Discretionary

Planning tbc

Delivery tbc

RAG Status

GREEN 

Plan

 This project has been delayed to 13/14 following the Mid Year Review.

 

Dependencies

 

 

Section Three: Projects in Progress

 

 

Project InfoProject Managers Commentary

FIN056 (AP Number)

eProcurement Scotland - eInvoicing

 

Category: Funded

Milestones

---

---

--- 

RAG Status

SUSPENDED

 

Report by Rhian Davies for June 2013.

Project suspended until 13/14 - resources not available within FIS until the early Autumn.

 

 

FIN076  (AP12-029)

Student Finance Channel - Further Developments for Staff and Students

 

Category: Discretionary

Milestones

 

 

08-Jul-201

Deployment
22-Jul-2013Deployment review
02-Aug-2013Closure

RAG Status

GREEN

Report by Susan McKeown for June 2013

 

Achievements in Last Period
    • Integration and Acceptance sign-off meeting was held and approval was given to proceed to LIVE
    • Project was rescheduled and resources secured
Issues
  • There is work noted in the Acceptance milestone which needs completed prior to go live.
Next Steps
    • Complete action points in Acceptance sign-off
    • Deliver
    • Deployment Sign-off
    • Close - the closure process will commence at the start of July to ensure the project does not overrun into 13/14.

 

 

 

 

 

 

FIN078 (AP Number)

eFin Journal Auto-Upload

 

Category: Discretionary

Milestones

 

Target dateTitle
22-Jul-2013Go-live
26-Jul-2013Deployment sign-off
02-Aug-2013Closure

RAG Status

GREEN

Report by Dawn Nicholls for June 2013

Achievements

  • Following successful interfacing of both WPM and manual files, UAT sign-off was agreed in mid-June and the new JAMS application was installed onto Live.  However, shortly before it was activated we were made aware of a previously unknown requirement for multiple vat codes for delegate registration files for Accommodation Services (AS). The requirement was clarified with AS and FIS and plans put in place to make the necessary changes. 

Issues

  • Previously unknown requirement for multiple vat codes for delegate registration files resulting in delays to timescales and increased budget.

Next Steps

  • Complete changes for delegate registration vat (for AS)and clearing CLINK table upon failure (for FIS).
  • UAT and sign-off of changes
  • Go-live

 

Full details can be seen in the Project Journal

FIN079 (AP Number)

LEAN- Review of Financial Systems

 

Category: Discretionary

Milestones

 

Target dateTitle
31-Jul-2013Delivery - workpackage 13 (BOXI enhancements)
31-Jul-2013Delivery - workpackage 2 (eIT enhancements)
31-Jul-2013Delivery - workpackage 8 (Serengeti interface improvements)
31-Jul-2013Delivery - workpackage 11 (Support staff survey)
31-Jul-2013Delivery - workpackage 14 (eIT transfer queue)
31-Jul-2013Delivery - workpackage 10 (WebFirst report 19 fix)
31-Jul-2013Delivery - workpackage 3 (new/changed WebFirst reports)
31-Jul-2013Delivery - workpackage 16 (eIT description)
02-Aug-2013Closure
 

RAG Status

GREEN

Report by Dawn Nicholls for June 2013

Achievements

  • eStores category re-sequencing (workpackage 15) went live this month.  This enhancement was to facilitate Roslin moving onto the system, so completing the rollout of eStores to all eFIn Stock stores.
  • eStores enhancement for invalid finance codes (workpackage 9) went live this month.  The corresponding change for eAuthorisations has been picked up by project FIN089.
  • eIT enhancements (workpackage 2) now in UAT and passed to FIS for testing
  • Meeting held with FInance Business Rep to agree priority of remaining workpackages as there is insufficient budget or time to complete all of them.
  • Of the 17 workpackages identied to-date, 12 are now either complete or almost complete

 

Issues

  • Ongoing issues securing development resources against higher priority projects
  • Insufficient time/budget to complete all of the remaining workpackages (although it was always made clear that we would only be able to complete as many as there was time/budget for, as the project has to close at the year-end)

Next Steps

  • FIS to undertake UAT of eIT enhancements
  • Go-live of eIT enhancements
  • Secure resources to complete as many of the final workpackages as possible before the year-end

 

Full details can be seen in the Project Journal

FIN080 (AP Number)

Customer Interface Improvements

 

Category: Discretionary

Milestones

 

Target dateTitle
12-Jul-2013Phase 2 - Acceptance
19-Jul-2013Phase 2 - Go-live
26-Jul-2013Phase 2 - Deployment sign-off
12-Aug-2013Closure
 

RAG Status

GREEN

Report by Dawn Nicholls for June 2013

Achievements

  •  The automation of the customer/product feeds (requirement FIN075-006) has been passed to FIN087 as that project was also looking to automate these feeds and is better placed to carry this work forwards.
  • Meeting held with Finance Business Reps to agree actions for the remaining outstanding requirements (FIN075-005 Volume Issue, FIN075-009 FPA Invoices and 4.1.10 Debt Flag).  It was agreed that these requirements are currently either not a priority or are not feasible with current working practices.  A summary will be provided for the Project Sponsor.

Issues

  • Several issues identified by SACS during UAT of the EUGEX-side of the new historic feed.  These are being worked on by the developer and a meeting has been set up with SACS ro discuss in more detail. 

Next Steps

  • UAT by FIS of historic feed and debt chasing info on EDUS01/02 screens
  • Go-live

 

Full details on project activities can be seen in the Project Journal

FIN081 (AP Number)

Document Management for Finance Applications

 

Category: Discretionary

Milestones

---

---

--- 

RAG Status

SUSPENDED

Report by Rhian Davies for June 2013

Project suspended until 13/14.

FIN083  (AP23-003)

eFinancials Upgrade

 

Category: Compliance

Milestones

 

 

  
17-Jul-13Closure

 

RAG Status

AMBER

 

Report by Morna Findlay for Rhian Davies for June  2013

Achievements in this period
  1. DEV  database migrated to new infrastructure

  2. New budget approved

  3. DSOR held and approved subject to remaining relevant JIRA issues (4) being closed

  4. Proof-of-concept  for Single-Sign-on/Launchpad applications  presented to Finance and approved  (although progressing this is not in the scope of this project)

  5. Documentation completed.

 

Outstanding Issues

 

From DSOR

  1. 1. 4 JIRA issues to be closed

 

Issues not included in DSOR

 

  1. Clarify if triggers preventing use of dataguard on new database infrastructure are required by business
  2. DEV database migration to be completed and  signed off.
  3. Supplier Self-Service Performance to be installed on TEST and then LIVE

 

Next Steps

 

  1. Sign off Dev database migration

  2. eFIn TEST and LIVE  to be migrated to new infrastructure.

  3. Supplier Self-Service Portal - install on TEST and LIVE
  4. Renaming of all applications, URLS to use new DEV and TEST names to be completed.

  5. Lessons learned to be captured

  6. Closure of project for Phase 1
  7. Create Phase 2 project - database migration, SSO, and SSS

The project RAG status has been set to AMBER as milestones need to be agreed for the database migration.

 

FIN085  (AP01-008)

eTime Phase 3

 

Category:  Compliance

 

Milestones

 

18-Oct-2013UAT (for final release) signed off
13-Nov-2013Deployment signed off
22-Nov-2013Closure

 

 

RAG Status:  GREEN 

Report by Jill Nicoll for June 2013

 
Achievements in last period:
  1. Release 1 signed off in UAT and deployed to Live.
  2. Release 2 signed off in Peer testing, deployed to Test, and released for UAT.
Issues:
  1. Batch Processing requirements remain unconfirmed.
  2. HSS have agreed to fund the estimated 30 days to deliver the four of the non-top priority HTBN requirements.   HSS are willing for this work to be done during the current planning year, to provide extra time for Finance to determine the Batch Processing requirements, but to be billed in the next planning year, to reduce the impact on Finance's 2013-14 annual budget.  This proposal is with the Programme Manager, for consideration. 
Next Steps:

Stakeholders:

UAT test and sign off Release 2

Batch Processing functionality : confirm business requirements / sign off on the proposed soluton

ISA:

Deploy Release 2 to Live 

Design Batch Processing functionality

 

FIN086 (AP23-004)

ePay Reconciliation

 

Category:  Compliance

 

Milestones

26-Apr-13  Planning

 

 

 

RAG Status:  GREEN

 

Report by Rhian Davies for June 2013

Project suspended until 13/14 to enable eAuthorisations to start in 12/13.

 

FIN087

Credit Note/Sales Invoice Interface Changes

Category:  Funded

 

Milestones

   

Target dateTitle
10-May-2013Project Brief
06-Jun-2013PPAR/ PPDR - Analysis and Design Review

 

 

RAG Status:  AMBER

Report by Laura Bell for April 2013

 

Achievements in Last Period

  • Project Brief prepared - awaiting sign off from sponsor
  • Requirements gathering underway; initial set of potential business rules identified
  • Review held with Finance team to discuss whether Controls/ Business rules can be developed to acceptable level for automation

 

Issues

  • Project status is Amber; awaiting confirmation from Finance that they are comfortable adequate controls/ business rules can be developed

 

Next Steps

  • Sign off Project Brief
  • Continue requirements gathering/ development of phased approach

 

 

 

FIN088 (AP12-017)

ERA Decommissioning

 

Category:  Compliance

 

Milestones

 

10-Jul-2013Build OLLIE CompleteBuild
16-Jul-2013Integrate OLLIE CompleteIntegrate
22-Jul-2013Acceptance OLLIE CompleteAccept
23-Jul-2013Deliver OLLIEDeliver
29-Jul-2013Build Finance Channel CompleteBuild
06-Aug-2013Integrate Finance Channel CompleteIntegrate
12-Aug-2013Acceptance Finance Channel CompleteAccept
12-Aug-2013Build PCounter CompleteBuild
19-Aug-2013Deliver Finance ChannelDeliver
20-Aug-2013Integrate PCounter CompleteIntegrate
28-Aug-2013Acceptance PCounter CompleteAccept
29-Aug-2013Deliver PCounterDeliver
16-Sep-2013Project Closed
 

RAG Status:  GREEN

Report Date: June 2013
Louise Heathcote
 

Achievements in this Reporting Period

  • OLLIE Build ready for Peer Testing
  • Resolved issues with PCounter Dev & Test Environments
  • PCounter Build underway

 

Issues

  • Milestone changes due to impact of FIN076 test and deployment
  • OLLIE milestones for deployment at end of July are tight due to annual leave and rescourcing issues which are now resolved but caused a delay in starting the build
  • Finance Channel cannot start build until FIN076 has been deployed and our changes cannot be deployed until database changes FIN084 are complete, in addition Finance want to include a new requirement from FIN076 in FIN088 which will impact the deployment milestone for Finance Channel
  • FIN078 JAMS has not gone live and may be deployed after OLLIE has been deployed this will require a interim manual work around for posting finance transactions

 

 

Next Steps

  • Complete Integrate, Test and Deploy for OLLIE
  • Complete Build, Integrate and Test for PCounter
  • Review requirements and milestones for Finance Channel once FIN076 has gone live

 

 

FIN089

eAuthorisations Migration

 

Category:  Compliance

 

Milestones

 

 

Note:   The milestones below are based on the ToR estimates, and do not reflect secured resources.  When resource availability is taken into account, these milestones may have to change.

 

 

28-Jun-2013Phase 1 Build approved
24-Jul-2013Phase 1 Integration approved
24-Jul-2013Phase 2 Analysis approved
05-Aug-2013Phase 2 Design approved
19-Aug-2013Phase 1 UAT sign-off
23-Aug-2013Phase 1 Delivery
06-Sep-2013Phase 1 Deployment approved
18-Oct-2013Phase 2 Build approved
18-Oct-2013Phase 3 Business Analysis approved
25-Nov-2013Phase 2 Integration approved
10-Jan-2014Phase 2 UAT approved
17-Jan-2014Phase 4 Analysis signed off
20-Jan-2014Phase 2 Delivery
03-Feb-2014Phase 2 Deployment approved
07-Feb-2014Closure

 

 

RAG Status:  Green

Report Date: 

June 2013

 

Achievements in last period:

Project ToR reviewed with Project Sponsor, agreed changes applied, and ToR signed off.

Remaining ISA estimates provided.  Project estimate of 247 days approved.

Phase 1 Build completed.

Issues:

Finance's eAuthorisations designer/developer has now left the University. 

Next Steps:

Phase 1 Integration to Test and Integration Testing 

Phase 1 to be released for User Acceptance Testing

Phase 2 Business Analysis to be completed

 

 

Section Four: Closed or Withdrawn Projects

 

Project InfoProject Managers Commentary

FIN082

HMRC Real Time Information

Compliance 

Report by Jill Nicol

This project was closed on 10-Aug-2010

Please see the Completion Report for further information.  

AP23-055

Rolling out Finance BOXI Reports

 

Funded 

Report by Rhian Davies

This project was withdrawn from the 12/13 programme.

FIN072 (AP01-008)

eTime

 

Category: Compliance

Report by Jill Nicol

This project was closed on 30-Nov-12.

Please see the Completion Report for further information.

FIN077

Control Account Balancing

 

Category: /Compliance

Report by Sue Woodger 

This project was closed 1 February 2013

Please see the Completion Report

FIN084

eStores Rollout

Category : Discretionary

 

Report by Dawn Nicholls

This project was closed on 20th December 2012

Please see the Completion Report for further information

 

 

Section Five: New Approved Projects from 13/14 Annual Plan

Any projects that were approved in previous annual planning rounds and have been postponed to start in 13/14 will be listed under section 2: Projects Not Started. Projects started in 12/13 but which will carry over to 13/14 are listed under section 3: In Progress.

 

 

 

 

Project InfoProject Managers Commentary

 AP34

Student Fees - Interest Charging on Invoices

Compliance

Planning -

Delivery -

 RAG Status

 Plan

 

Dependencies

 

AP34

Student Fees - SAAS and SLC Fees Reconciliation

Compliance

Planning -

Delivery -

 RAG Status

Plan

 

Dependencies

AP34

Migration of BOXI reports

Compliance

Planning -

Delivery -

 RAG Status

Plan

 

Dependencies

AP34

Essential Enhancements for Finance Applications

Compliance

Planning -

Delivery -

 RAG Status

Plan

 

Dependencies

AP34

eExpenses replacement

Compliance

Planning -

Delivery -

 RAG Status

Plan

 

Dependencies