Report for May

Report Date
May 2013

Report compiled by Rhian Davies (IS Apps Programme Manager) for Liz Welch  (Programme Owner)

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

Section Five: New Approved Projects from 13/14 Annual Plan

Section One: Programme Commentary, RAG and Resources Update

 

 

 

 

 

 

 

Section Two: Projects Not Started

 

Project InfoProgramme Manager's Commentary

AP23-056

International Bank Validation

 

Funded 

Planning July 2013

Delivery December 2013

RAG Status

GREEN  

Plan

The start of the project has been delayed to July due to other priorties within the programme. 

Dependencies

No dependencies identified.

AP89-008

FPM for eInvoicing

 

Discretionary

Planning tbc

Delivery tbc

RAG Status

GREEN 

Plan

 This project has been delayed to 13/14 following the Mid Year Review.

 

Dependencies

 

 

Section Three: Projects in Progress

 

 

Project InfoProject Managers Commentary

FIN056 (AP Number)

eProcurement Scotland - eInvoicing

 

Category: Funded

Milestones

---

---

--- 

RAG Status

SUSPENDED

 

Report by Rhian Davies for October 2012

Project suspended

 

 

FIN076  (AP12-029)

Student Finance Channel - Further Developments for Staff and Students

 

Category: Discretionary

Milestones

 

 

Milestones are to be rescheduled when estimate obtained for re-work

 

22-May-2013

Integration
22-May-2013Acceptance
29-May-2013Deployment
11-Jun-2013Deployment review
25-Jun-2013Closure

RAG Status

AMBER

Report by Susan McKeown for May 2013

 

Achievements in Last Period
  • Finance carried out some UAT with students 
  • Finance demo'd the revised channel to Business Partners that use the channel to support students
  • UAT progressed with some issues being resolved
Issues
  • New JIRAs were raised in UAT causing unplanned re-work and a delay to the Go Live
  • The remaining milestones need rescheduled once the re-work estimates are known - this has been delayed due to PM time
  • The TEST finance pathway at WPM was promoted to LIVE without any consultation with the project and this caused a delay in testing
Next Steps
  • Reschedule delivery milestones
  • Complete testing (Integration/UAT/Student)
  • Communications to staff and students and Helpline
  • Deliver

 

 

 

 

 

 

FIN078 (AP Number)

eFin Journal Auto-Upload

 

Category: Discretionary

Milestones

 

Target dateTitle
24-Apr-2013Integration
03-Jun-2013Acceptance
11-Jun-2013 *Go-live
19-Jun-2013Deployment sign-off
27-Jun-2013Closure
 

RAG Status

GREEN

Report by Dawn Nicholls for May 2013

Achievements this period

  • Integration and acceptance testing have both taken place this month but were unable to fully complete due to issues with the Test eFin database (see Issues section for more detail).  * As a result the go-live planned for 11th Jun will be delayed.
  • Testing resulted in minor requests for enhancements/changes and due to developer unavailability this has prevented the sign-off of these milestones.

Issues

  • Issues securing the developer for the re-work from testing (now resolved)
  • Issues in completing the testing due to Test eFIn being set at period 01/2014.  In order to work around this the application had to be temporarily hard-coded to the corresponding period in order to complete end-to-end testing (now resolved).
  • Potential further re-mapping following relocation of eFin databases under project FIN083 

Next steps

  • Sign-off integration and acceptance testing following completion of re-work
  • Go-live

 

Full details can be seen in the Project Journal

FIN079 (AP Number)

LEAN- Review of Financial Systems

 

Category: Discretionary

Milestones

 

Target dateTitle
31-May-2013Delivery - workpackage 13 (BOXI enhancements)
31-May-2013Delivery - workpackage 9 (eStores code validation)
31-May-2013Delivery - workpackage 2 (eIT enhancements)
30-Jun-2013Delivery - workpackage 8 (Serengeti interface improvements)
30-Jun-2013Delivery - workpackage 11 (Support staff survey)
30-Jun-2013Delivery - workpackage 10 (WebFirst report 19 fix)
30-Jun-2013Delivery - workpackage 3 (new/changed WebFirst reports)
30-Jun-2013Delivery - workpackage 14 (eIT transfer queue)
12-Jul-2013Closure
 

RAG Status

GREEN

Report by Dawn Nicholls for May2013

Achievements this period

  • Wiki/website usability review took place and a written report has been submitted to FIS for consideration/action.
  • Development work completed on EDUNESI interface split to improve supportability.  This change will be put live as part of FIN080 as the 2 projects are inter-related in this area.
  • eFin screen ACS208P fixes to improve performance are now live.
  • Development work completed on eStores workpackage to use ABS code validation.  UAT has been completed and the package is now ready for live deployment w/c 10th June

Issues

  • Ongoing issues securing development resources against higher priority projects

Next steps

  • eStores enhancement to go live w/c 10/06/13
  • Complete last of several Serengeti fixes
  • Complete last of several BOXI object requests
  • Secure additional resource to complete eIT enhancements (currently not working on Test)

 

Full details can be seen in the Project Journal

FIN080 (AP Number)

Customer Interface Improvements

 

Category: Discretionary

Milestones

 

Target dateTitle
01-Mar-2013Phase 2 - Design
24-May-2013Phase 2 - Build
28-Jun-2013Phase 2 - Integration
12-Jul-2013Phase 2 - Acceptance
19-Jul-2013Phase 2 - Go-live
26-Jul-2013Phase 2 - Deployment
12-Aug-2013Closure

RAG Status

GREEN

Report by Dawn Nicholls for May 2013

Achievements this period

  • Historic feed build completed
  • Debt chasing info build completed
  • Peer testing of both historic feed and debt chasing info

Issues

  • Lead developer left the department.  A new developer has been assigned and a handover took place.
  • Further discrepencies in the design document from what was agreed with SACS

Next steps

  • Replan milestones to reflect the new 'workpackage' approach to delivery
  • Deploy historic feed and debt chasing info to Test
  • UAT
  • Design for interface automation

 

Full details on project activities can be seen in the Project Journal

FIN081 (AP Number)

Document Management for Finance Applications

 

Category: Discretionary

Milestones

---

---

--- 

RAG Status

SUSPENDED

Report by Rhian Davies for October 2012

Project suspended

FIN083  (AP23-003)

eFinancials Upgrade

 

Category: Compliance

Milestones

 

 

  
27-Mar-2013Deployment Sign Off
10-Apr-2013Closure

 

RAG Status

GREEN

 

Report by Morna Findlay for Rhian Davies for March  2013

Achievements in this period
  1. Estates  interfaces signed off in  TEST and deployed to LIVE

  2. Salary forecasting issues resolved

  3. POPR50 issue resolved

  4. PECOS interface  issues resolved

  5. Old EFIN DEV and TEST databases and applications taken down.

  6. 63 JIRA issues resolved.

  7. Script killing orphaned processes now runs nightly.

 

Outstanding Issues
  1. 13 JIRA issues remaining.

  2. Batch processing issue - awaiting ABS fix for CLIR09

  3. Issues with Spinning processes - possible  ACTRB9 FIX to be deployed to LIVE

  4. New version of Supplier Self-Service supplied by ABS to be deployed to DEV and TEST and tested.

  5. Issues with new PCs accessing EFIN - workaround in place, ABS fix awaited

  6. Sciquest extract issue resolution - to be tested and confirmed

  7. Deployment Sign-Off review missed.

 

Next Steps
  1. Remaining issues to be resolved - Finance and IS Apps staff to update JIRA issues

  2. Deployment of Supplier Self-Service Portal - new version supplied by ABS to resolve performance issues.

  3. Lessons learned to be captured

  4. Documentation to be completed

  5. Deployment sign-off review.

 

The project RAG status has been set to AMBER as a new date for the Deployment Sign-Off review has yet to be agreed and the closure date of April 10th will not be achievable.

 

FIN085  (AP01-008)

eTime Phase 3

 

Category:  Compliance

 

Milestones

 

 

18-Oct-2013UAT (for final release) signed off
13-Nov-2013Deployment signed off
22-Nov-2013Closure

 

 

RAG Status:  GREEN

Report by Jill Nicoll for May 2013

Achievements in last period:

System Design stage sign-off confirmed by stakeholder group.

Development of Release 1 of the top priority requirements is progressing well.

Issues:

The Project Sponsor has confirmed that the new Batch Processing functionality remains a top priority for the project.  However, Finance have still not been able to confirm the business requirements for this requirement.  As a result, it has not been possible to design the functionality, or even to estimate how much of the project's budget will be required to deliver it.  

Consequently, it was agreed with the stakeholder group that the Build will be suspended for 4 weeks following the completion of top priority batches 1 and 2, to allow Finance additional time to either confirm the business requirements, or sign off on the solution that was proposed by the Designer on 10th April.  

By the end of June at the latest, either the batch processing business requirements must be confirmed, or the Project Sponsor must make the decision as to whether to:

  • drop the batch processing requirement, and progress with the remaining top priority requirements
  • suspended the rest of the project and reassign its resources to other work, then re-request them when the business requirements are available (this would also mean suspending work on the remaining top priority requirements)
  • progress with the design and development of the solution that was proposed by the Designer on 10th April

The 4-week suspension of the Build has required that the rest of the project be re-planned, with delays to the remaining milestones.  

HSS have asked for estimates to deliver four of the non-top priority HTBN requirements under a separate, funded arrangement.  The Project Sponsor has agreed in principle to the separately-funded being done under the umbrella of the project.  The estimate of 30 days of ISA effort will be communicated to HSS at the start of the next period.     

Next Steps:

ISA:

Peer test and publish Release 1 to Test for UAT testing

Address Release 1 UAT feedback 

Develop Release 2 

Stakeholders:

UAT test and sign off Release 1

Batch Processing functionality : confirm business requirements / sign off on the proposed soluton / drop the requirement

FIN086 (AP23-004)

ePay Reconciliation

 

Category:  Compliance

 

Milestones

26-Apr-13  Planning

 

 

 

RAG Status:  GREEN

 

Report by Rhian Davies for March 2013

 

Achievements in last period:

  • Project manager assigned 

 

Issues

  • None

 

Next Steps

  • Kick off meeting with Finance
  • Complete Planning phase

 

FIN087

Credit Note/Sales Invoice Interface Changes

Category:  Funded

 

Milestones

 

Target dateTitle
14-Jun-2013Project Brief
21-Jun-2013PPAR: Analysis Review - Phase 1

 

 

RAG Status:  AMBER

Report by Laura Bell for May 2013

Achievements in Last Period

  • Initial Project Brief completed and signed off
  • Phased development approach agreed with Finance
  • Brief revised to reflect phased approach; currently completing sign off
  • Business requirements for Phase 1 drafted and now under review

Issues

  • Project status is Amber; as to complete Phases 2/3 (deliver core functionality) will require input from ABS, which may impact timescales and cost. Engagement with ABS to commence.

 

Next Period

  • Sign off revised Project Brief
  • Sign off requirements for Phase 1
  • Continue requirements gathering for Phase 2/3
  • Engage ABS

 

FIN088 (AP12-017)

ERA Decommissioning

 

Category:  Compliance

 

Milestones

Note - This milestones will be changed following a rebaslining of the plan w/c10th June due to resourcing levels

 

26-Jun-2013Build OLLIE CompleteBuild
01-Jul-2013Integrate OLLIE CompleteIntegrate
01-Jul-2013Acceptance OLLIE CompleteAccept
02-Jul-2013Deliver OLLIEDeliver
09-Aug-2013Build PCounter CompleteBuild
20-Aug-2013Integrate PCounter CompleteIntegrate
22-Aug-2013Build Finance Channel CompleteBuild
28-Aug-2013Acceptance PCounter CompleteAccept
29-Aug-2013Deliver PCounterDeliver
02-Sep-2013Integrate Finance Channel CompleteIntegrate
09-Sep-2013Acceptance Finance Channel CompleteAccept
10-Sep-2013Deliver Finance ChannelDeliver
16-Sep-2013Project ClosedClose
 

 

RAG Status:  GREEN

Report by Louise Heathcote for May 2013

 

Achievements in this Reporting Period

  • Signed off Business Requirement Document
  • Sgined off System Design Document
  • Commenced Build

Issues

  • Resourcing - lost first 5 days of build plan due to Development resource completing FIN076 (priority project)
  • Additional Resource not yet assigned
  • Current milestones for deployment not signed off as too close to beginning of academic year, pending a rebaseling of the plan to publish new milestones

Next Steps

  • Complete Build Phase 1 - OLLIE & WPM Call Back
  • Secure additional resource
  • Re baseline estimates and plan w/c 10th June

 

FIN089

eAuthorisations Migration

 

Category:  Compliance

 

Milestones

Note:  The milestones below are based on the ToR estimates, and do not reflect secured resources.  When resource availability is taken into account, these milestones may have to change.

 

14-Jun-2013Terms of Reference approved
28-Jun-2013Phase 2 Analysis approved
28-Jun-2013Phase 1 Build approved
12-Jul-2013Phase 1 Integration approved
19-Jul-2013Phase 2 Design approved
09-Aug-2013Phase 1 UAT sign-off
21-Aug-2013Phase 1 Delivery
04-Sep-2013Phase 1 Deployment approved
18-Oct-2013Phase 2 Build approved
18-Oct-2013Phase 3 Business Analysis approved
25-Nov-2013Phase 2 Integration approved
10-Jan-2014Phase 2 UAT approved
17-Jan-2014Phase 4 Analysis signed off
20-Jan-2014Phase 2 Delivery
03-Feb-2014Phase 2 Deployment approved
07-Feb-2014Closure

 

 

RAG Status:  RED

  • ToR estimate exceeds Proposal estimate
  • ToR scope exceeds Proposal scope
  • ToR still to be reviewed with Project Sponsor

Report by Jill Nicoll for May 2013

Achievements in last period:

Project ToR drafted.

Dev Team resources agreed; Dev Tech resources secured.

Estimates obtained from all teams except Apps Mgt.

Issues:

The three point estimation exercise produced a project estimate considerably higher than the Proposal estimate.  The estimates, and the ToR objectives and deliverables upon which they were based, will be reviewed with the Project Sponsor at the start of the next period.

Because of the imminent departure of Finance's eAuthorisations designer/developer, later stages of the project have been brought forward to run in parallel with the Planning stage.  This has resulted in planning delays, and to the risk of spending project budget on areas that will ultimately be de-scoped from the project. 

Next Steps:

Project ToR to be reviewed by Project Sponsor, agreed changes applied, and signed off.

Apps Mgt still to provide estimates. 

Remaining resources to be secured.

AP23-059

eExpenses- Business Case

 

Compliance

 

Planning June 2013

Delivery tbc

RAG Status

AMBER

Report by Rhian Davies for May 2013

Initial planning underway, project amber as there is no available business analyst to work on the project.  Discussions taking place about bringing in a contract resource.  

 

Section Four: Closed or Withdrawn Projects

 

Project InfoProject Managers Commentary

FIN082

HMRC Real Time Information

Compliance 

Report by Jill Nicol

This project was closed on 10-Aug-2010

Please see the Completion Report for further information.  

AP23-055

Rolling out Finance BOXI Reports

 

Funded 

Report by Rhian Davies

This project was withdrawn from the 12/13 programme.

FIN072 (AP01-008)

eTime

 

Category: Compliance

Report by Jill Nicol

This project was closed on 30-Nov-12.

Please see the Completion Report for further information.

FIN077

Control Account Balancing

 

Category: /Compliance

Report by Sue Woodger 

This project was closed 1 February 2013

Please see the Completion Report

FIN084

eStores Rollout

Category : Discretionary

 

Report by Dawn Nicholls

This project was closed on 20th December 2012

Please see the Completion Report for further information

 

 

 

Section Five: New Approved Projects from 13/14 Annual Plan

Any projects that were approved in previous annual planning rounds and have been postponed to start in 13/14 will be listed under section 2: Projects Not Started. Projects started in 12/13 but which will carry over to 13/14 are listed under section 3: In Progress.

 

 

 

Project InfoProject Managers Commentary

 AP34

Student Fees - Interest Charging on Invoices

Compliance

Planning -

Delivery -

 RAG Status

 Plan

 

Dependencies

 

AP34

Student Fees - SAAS and SLC Fees Reconciliation

Compliance

Planning -

Delivery -

 RAG Status

Plan

 

Dependencies

AP34

eAuthorisations

Compliance

Planning -

Delivery -

 RAG Status

Plan

 

Dependencies

AP34

Migration of BOXI reports

Compliance

Planning -

Delivery -

 RAG Status

Plan

 

Dependencies

AP34

Essential Enhancements for Finance Applications

Compliance

Planning -

Delivery -

 RAG Status

Plan

 

Dependencies

AP34

eExpenses replacement

Compliance

Planning -

Delivery -

 RAG Status

Plan

 

Dependencies