- This is the 2nd week of iteration 1.0a and work has focussed on the Hunter interface and user admin
- Progress has been slightly slower than planned as we've been experiencing issues with the Bamboo automated deployment, which has not been used with Sequel Server before (this is logged in the issue/change log as an issue)
- The planned end of iteration review has been rescheduled to Monday due to the severe weather , as not all team members were able to get into the office.
Tom Russell at SciQuest 21-Nov-13 18:34 and correcpondence between us
1. Yes we can start the upgrade work on 7 January.
Would you please help us verify two key assumptions?:
1.1. We are upgrading the existing test and production environment in place, and not creating new installations
- Ewan confirmed that this is correct
1.2. The current test environment is operational (you can currently log in and perform key functions)
Online Registration has gone live for ALL new students with start dates from 1/1/14, NO paper forms will be sent out beyond this date. Six weeks before their start date from the 19th November these students will be e-mailed to let them know that the online process is available for them to go through within My-Ed.
SSP Deployment Checklist for the project. This is a cut down version of the IS version of the document
Agreed Resourcing by Team
Apps Supp 1/2 day handover at end of each phase
Corporate Services Investigation and Build
Dev Tech TEST and LIVE
Dev Tech Security patches
Corporate Services P60 work
Team resourcing has been agreed for:
Summary of to-days discussion ITS103 - Core Technology updates.
Present
Stevie Conlon, Mark Lang , Maurice Franceschi, Stefan Kaempf, Adam Wheavil
Apologies : Ewan Scott.
Next Meeting Thursday 5th December , 4.09.
General.
- Maurice noted that budgets on the project were tight and advised strong milestones be planned.
The Events Bookings changes have been deployed to TEST. The service owner and the business user in the Careers service have been informed.
The deploymemt was postponed due to staff illness and is replanned for the 27/11. All bookings are in place and scheduled approriately
Work/Task Breakdown
Task | Deliverable | Owner |
Project Management | Project authorisation Brief and Project documents. Communication and coordination with stakeholder | Sheila Fraser (Programme Manager) Ruth McCallum (Project Manager) |
Build It | Business Analysis (BRD) System Analysis (SDS) Build solution and peer test |
Priority and Funding
The project is a discretionary one within the progamme. A budget of 211 IS days has been allocated for the Project with the programme.
With currently 12/13 - 114 days 13/14 - 97 days