• This is the 2nd week of iteration 1.0a and work has focussed on the Hunter interface and user admin
  • Progress has been slightly slower than planned as we've been experiencing issues with the Bamboo automated deployment, which has not been used with Sequel Server before (this is logged in the issue/change log as an issue)
  • The planned end of iteration review has been rescheduled to Monday due to the severe weather , as not all team members were able to get into the office.

Tom Russell at SciQuest 21-Nov-13 18:34 and correcpondence between us

1. Yes we can start the upgrade work on 7 January. 

 Would you please help us verify two key assumptions?:

1.1.   We are upgrading the existing test and production environment in place, and not creating new installations

  • Ewan confirmed that this is correct

1.2.  The current test environment is operational (you can currently log in and perform key functions)

Online Registration has gone live for ALL new students with start dates from 1/1/14, NO paper forms will be sent out beyond this date.  Six  weeks before their start date from the 19th November these students will be e-mailed to let them know that the online process is available for them to go through within My-Ed.

SSP Deployment Checklist for the project. This is a cut down version of the IS version of the document

Agreed Resourcing by Team

Apps Supp                                         1/2 day handover at end of each phase

Corporate Services                          Investigation and Build

Dev Tech                                             TEST and LIVE

Dev Tech                                             Security patches

Corporate Services                          P60 work

Team resourcing has been agreed for:

Summary of  to-days discussion ITS103 - Core Technology updates.

Present

Stevie Conlon, Mark Lang , Maurice Franceschi, Stefan Kaempf, Adam Wheavil

Apologies : Ewan Scott.

 

Next Meeting Thursday 5th December , 4.09.

 

General.

- Maurice noted that budgets on the project were tight and advised strong milestones be planned.

The Events Bookings changes have been deployed to TEST. The service owner and the business user in the Careers service have been informed.

 

 

The deploymemt was postponed due to staff illness and is replanned for the 27/11. All bookings are in place and scheduled approriately

 

Work/Task Breakdown

 

TaskDeliverableOwner
Project Management

Project authorisation

Brief and Project documents. Communication and

coordination with stakeholder

Sheila Fraser (Programme Manager)

Ruth McCallum (Project Manager)

Build It

Business Analysis (BRD)

System Analysis (SDS)

Build solution and peer test

 

Priority and Funding

The project is a discretionary one within the progamme. A budget of 211 IS days has been allocated for the Project with the programme.

With currently 12/13 - 114 days 13/14 - 97 days