Organisation

Work/Task Breakdown

Task Owner
Planning brief (estimates, plan, resource, milestones) Project Services
Implementation Planning Project Team (Dev Tech, Tech Man, ITI, Project Services and Elecosoft)
Review and update TAD Dev Tech / Tech Man
Data refresh from Live to Test Tech Man
Application Upgrade in Test and Live Elecosoft
Windows Operating System In Place Upgrade in Test and Live ITI
SQLServer Upgrade in Test and Live Dev Tech / Tech Man
Create test plan PMO
User Acceptance Testing PMO
Client Rollout (automated / manual) PMO and Computer Reps
Closure activities  Project Services

 

Resources, Skills and Costs

The project will primarily require input and resource from the following IS Applications teams:

  • Development Technology
  • Project Management Office
  • Project Services
  • Technology Management

Also include 3rd party supplier and other UoE resource:

  • Elecosoft technical resource
  • ITI Enterprise

For business testing and client rollout, selected resource from the following areas will be required:

IS Applications

  • Development Services
  • Project Management Office
  • Project Services
  • Production Management
  • Service Management

SSP via Programme Manager

SEP PMO

A 3 point estimate has been created with initial estimate of 100 days

 

Project Governance

The project will be governed by the following :

  • Weekly, or when necessary, project team meetings to manage the progress of the project deliverables
  • Monthly Status reporting to Project Sponsor, INF Programme Manager and INF Programme Owner
  • Communication to ASTA users within both IS Applications and SEP PMO

 

Project Stakeholders

 

Name Business Area
Dawn Holmes IS Applications - Project Services
Karen Stirling IS Applications - Project Services
Mark Lang / Alister Webb IS Applications - Development Technology
Mark MacGowan/Heather Larnach IS Applications - Technology Management
Matthew Harbour Elecosoft
Maurice Franceschi IS Applications - Project Services
Rhian Davies IS Applications - Project Management Office
Team Managers Porfolio - TBC IS Applications - Project Services
Paul McNulty IS Applications - Development Services
Murray Dippie / John McFarlane ITI - Enterprise Services
Testing Team Applications, SSP, SEP PMO

Project Estimations

https://secure.projects.ed.ac.uk/unpublished/project/inf153/estimations/planning-estimate

 