Estimate version 2.0

This is the updated estimate produced for WIS meeting on 11th April.

 

 Project Management Project Manager15 days
 Quality AssuranceIS Apps2 days
PlanningPlanningProject Services2 days
Business Analysis Business Analysis for RadiumBusiness Analyst6 days
Remaining tasks for Phase 1 SQL/ Coldfusion UpgradeSupport Testing on DEVDevelopment Services - Development Technolog, Production Management Application Management4 days
 Migrate to LIVEDevelopment Services - Development Technolog, Production Management Application Management3 days
 Deploy to LIVE and support any issuesDevelopment Services - Development Technolog, Production Management Application Management3 days
Waiting List Enhancements (changes for 2 lists), DSA Process Improvements Work for KELSO system that has been signed off in the Business Requirements Document  
Systems DesignSystems DesignDevelopment Services2 days
 Waiting List  modicifcationsDevelopment Services32 days
 Peer TestingDevelopment Services2 days
 System Documentation Production Management - Applications Management1 day
 Implementation PlanDevelopment Services - Development and Configuration Team

2 days

Radium Enhancements   
Business Analysis    
Systems DesignSystems DesignDevelopment Services3 days
 Radium EnhancementsDevelopment Services13 days
 Peer TestingDevelopment Services1 days
 System Documentation Production Management - Applications Management1 days
 Implementation PlanDevelopment Services - Development and Configuration Team2 days
    
Total Revised Estimate for work remaining 94 days
    
Overall Proposed Approved Budget  259 days

 