Meeting Minutes 5th June 2013

Hi Guys. The meeting room is booked as usual.

 

Minutes from 05/06.

 

Attendees - Stevie Conlon, Peter Jackson,Neil Grant, Dave Berry , Richard Good, Michael Sun

 

AOB

 

-          The tasks deemed necessary for build sign off  are , in addition to the TAD, there two JIRAs with Dev Tech, which don’t really need to be closed off but could be carried forward. Preferably  the scripts to remove the unwanted xml messages from the SOA dehydration database should also be tested. The build test document should be signed off , this looks good .

-          Peter has been added back in to the project and will be completing environments builds etc in parallel with Neil.TEST build expected to complete w/e 7th. No issues envisaged for remaining tasks end estimates look good.

 

 

8. TAD to be updated ongoing with completion expected w/c 06/05 . To be Signed Off at Dev tech weekly Meeting , 09/05. TAD to contain policy  of SOA DB  and log archiving limit of 60 days. Required for build sign off.

Action Neil :

Update on 15th : - TAD completion pushed back to accommodate TEST server build. To be picked up by w/c 20/5. Ongoing.

Update on 5th :- TAD to complete when all known tasks resolved on TEST.

 

 

16. Outstanding JIRA to be closed and completed by Dev Tech Team. Preferred  for build sign off.

Action : Richard/Michael – complete for Development Team.

Action Neil : 2 outstanding JIRAs with Dev Tech

Update on 5th . Ongoing.

 

17. Arrange build review and sign off

Action : Stevie

Update for 5th May.  Awaiting TAD. To arrange as soon as practical . See AOB for tasks required.

 

 

Completed  Actions

1. Security policy Implementation on the DEV server and SSL Dev install

Actions - Development Teams

Update : - Complete

 

14. Neil to complete Scripts

Action Neil : Complete

Update : Complete

 

 

13. Apply Security Policy to Web Authorisation for Composite and circulate results.

Action Richard

Update : Complete

 

12. Security standards and policies to be updated on the Wiki and circulated.

Action Richard : complete

Update : complete

 

15 . Load Balancer requests for TEST and LIVE.

Action Peter / Neil.

Update for 8th May

Update on the 15th May. Complete

 

 

18. PM to discuss Application Management involvement prior to project end .

Action Stevie

Update for 16th May . Ongoing

Update required for 22nd May. Stefan is in agreement that Hugh should spend some time on the new set-up. Complete

 

19. Include SOA hydration DB script testing in project tasks.

Action Stevie, Neil.

Update for 22nd May. Added to ASTA for Dev Tech. Complete.

 

 

20. Re-plan outstanding tasks.

Action Stevie, Neil ( Iain.)

Update required for 22nd May . complete

 

AOB

The tasks deemed necessary for build sign off  are , in addition to the TAD, there two JIRAs with Dev Tech, which don’t really need to be closed off but could be carried forward. Preferably  the scripts to remove the unwanted xml messages from the SOA dehydration database should also be tested. Additionally , the build test document should be signed off , this looks good .

 

Best regards.

 

Stevie Conlon

Project Manager/Business Analyst

Project Services

0131 6514543

07973498371

 