October 2016

Report Date
October 2016

IS Applications Infrastructure Programme Report for Programme Owner Stefan Keampf

Section One: Programme Commentary, RAG and Resources Update

 

Section Two: Projects Not Started Section Three: Projects In Progress Section Four: Closed or Withdrawn Projects

Section One: Programme Commentary, RAG and Resources Update

Overall Programme RAG: GREEN

The contingency has already been applied to a number of 15/16 projects to balance budgets and enable their completion this year. Budget is sufficient for all planned proejcts.

Almost all projects for 16/17 have now started, with just System Monitoring to be rescoped before deciding whether to continue.  

 

 

 

 

Section Two: Projects Not Started  

Project Info Programme Manager's Commentary
Implement Environment Monitoring Solution This is unlikely to proceed, at least as it had been expected. A scoping / gap analysis exercise may  be undertaken.
Annual Upgrade of Development Tools With the unplanned projects from last year using up this budget, we will not upgrade further in 16/17.

 

Section Three: Projects in Progress

 

Project Info Project Manager's Commentary

INF116 ASTA Upgrade 15/16

C

Milestones

17-Nov-2016 LIVE Upgrade Complete (Deployment)
30-Nov-2016 Deployment Sign Off
16-Dec-2016 Project Closure

 

RAG Status

GREEN

Report by Nikki Stuart for October 2016

Achievements in Last Period

  • LIVE upgrade dates confirmed 
  • Resources secured for LIVE uprade

Issues

None

Next Steps

  • Issue comms to ASTA users regarding downtime for LIVE upgrade
  • complete LIVE upgrade

 

Status

Project status has been set to GREEN as there are no issues

 

INF119 (AP56-047)

Service Resilience Capability

Category: Discretionary

 

Milestones

TBC

Review of Top & Medium Priority Services

TBC SRM Testing Complete

TBC

Priority Service (1) Development Failover complete

TBC

Priority Service (1) Test Failover complete

TBC

Priority Service (1) Live Failover complete

TBC

Delivery

TBC

Closure

 

RAG Status / RAG change during last month

AMBER

Report by Karen Stirling for October 2016

Achievements in Last Period

  • LTW have agreed for the University Website (EdWeb) to be used for proof of concept activity for SRM
  • Initial high level planning for Central Wiki for database failover testing to be reviewedw ith project team and service owner

Issues

  • Due to Project Manager on annual leave during October limited activity completed on project
  • Project milestones to be reviewed and revised removing any milestones no longer relevant
  • Agree scope change to introduce SRM testing - ITI and Consultant activity has been brought forward to 14th Nov, advised that timescales too tight to have Dev VM in place business owner agreement not in place at that time. ITi wi9ll work with Consukltabt and IS Apps testing will be completed at a later time
  • Review project budget for inclusion of new scope and only one application being tested for database failover

Next Steps

  • Confirm tasks for SRM activity with Business team and agreement environment
  • Plan Wiki failover activity for Dev and agree Dev Tech resource

Status

The project status is AMBER due to revising activity plan for database failover / SRM tasks, milestones need to be reviewed and agreed.

INF120

Disaster Recovery for Priority Services

Category: Discretionary

 

Milestones

 

TBC DR Document Storage Area ready
TBC Priority Services DR Documentation complete
14-Nov-2016 Delivery
02-Dec-2016 Closure

 

RAG Status / RAG change during last month

GREEN

Report by Karen Stirling for October 2016

Achievements in Last Period

  • Draft Disaster Recovery Plan issued out for review and agreement by project team

Issues

  • Due to Project manager's annual leave during October  limted activity completed on project
  • DR repository has still to be created - waiting for confirmation TADs can be uploaded onto SharePoint Site - Project Sponsor proposing this to OGG, also Service Management resource availability to support repository creation.
  • Project milestones to be reviewed and resource effort estimated for final activity on project - budget review for funding to be returned to the INF programme

Next Steps

  • Update Sharepoint site with key documentation
  • DR plans updated where required
  • Review project resource estimates, returning potential unused days back to programme
  • Following Major Incident in mid September impacting KB, a template document to be created for information on priority services to be included within project

Status

  • The project status is GREEN

INF121

Migrate Core Databases to Oracle 12c

Category: Compliance

 

Milestones

04-Nov-2016 Test environment build for NEWSLive complete
23-Nov-2016 NewsLive Integration Sign off
09-Dec-2016 NewsLive Acceptance sign off
22-Dec-2016 Live environment build for NewsLive complete
11-Jan-2017 NewsLive deploy to LIVE
25-Jan-2017 NewsLive Deployment sign off
31-Jan-2017 Re-estimation for GenLive

 

RAG Status / RAG change during last month

GREEN

Report by Chris Konczak for October 2016

Achievements in Last Period

  • Pre migration testing for all NewsDev applications completed and wiki page updated
  • NewsDev migration has been done
  • Application connections for 12c NewsDev currently being done.

Issues

  • About a 1 week delay while testing was completed of pre migration applications on NewsDev
  • DEV migration delayed by a day due to a clash with patching on the DEV database tier.
  • Milestones for Test Environment build could need replanned in November

Next Steps

  • Test post migration on DEV
  • Sign off build
  • NewsTest environment build
  • TEST environment migration
  • NewsTest integration sign off

Status

  • The project status is GREEN

 

INF122

16 - 17 Infrastructure Rationalisation

Category: Compliance

 

Milestones

 

30-Nov-2016 Publish applications to be migrated (16-17)
31-Mar-2017 Completion of 16-17 migrations
28-Apr-2017 Project completion

RAG Status / RAG change during last month

GREEN

Report by David Watters for October 2016

Achievements in Last Period

  • Produced listings of technology & software approaching EOL for other programmes
  • 15-16 migrations almost complete 

Issues and Risks

  • Awaiting update on final 15-16 migrations

​Next Steps

  • Produce listings of technology & software to be migrated in 16-17
  • Sign-off migrations from last year

Status

  • The project status is GREEN

 

INF123

16-17 Provisioning of Python environment

Compliance

Milestones

Target Datesort descending Title
04-Nov-2016 Planning
01-May-2017 Delivery
17-May-2017 Closure

RAG Status

AMBER

 

Report by Adam Wadee for October 2016

Achievements in Last Period

  • Planning meeting held with Dev Services, Production Management and Project Services.
  • Agreed that the project will focus on two main strands . 1 - Development Capability and 2. Infrastructure.
  • It was noted that the Infrastructure strand is heavily dependent on ITI engagement and completion of key infrastructure tasks (expected by the end Dec 2016).
  • Dev Services and Production to estimate the infrastructure and development tasks so that planning can complete.

Issues

  • Planning phase expected to take longer due to availability of key staff.
  • Resources for Development tasks not likely to be available until the new year.

Next Steps

  • Complete Planning phase and book resources.

Status

  • Amber due to delay completing the planning phase. This is due to key staff not being available to identify and confirm the project deliverables.

 

 

Section Four: Closed or Withdrawn Projects

 

Project Info Project Managers Commentary
INF115 Python Development Platform Implementation Closure approved August 2016

INF113 (AP45-067)

System Monitoring Pilot

Closure Approved 16 September 2016

INF111 (AP56-006)

New SQL Server Database Tier Replacement

Closure submitted 30 September 2016

INF118

JIRA upagrade 2016

Closure  Approved 30 September 2016

 

 

 