IS Applications Infrastructure Programme Report for Programme Owner Stefan Keampf

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

 

Section One: Programme Commentary, RAG and Resources Update

Overall Programme RAG: AMBER

A number of the remaining projects now have slipped into July or have been re-estimated and re-planned into 2016/17, resulting in unplanned carry over of circa 40 days. We anticpate being able to accomodate this from next year's budget.

Programme Owne and Programme Manager will meet before the new year begins to review current framework of accountability and responsibility to see how we can assist project teams in providing more realistic assessments of project status, project plans and risk management.

 

 

 

 

 

 

 

Section Two: Projects Not Started  

Project InfoProgramme Manager's Commentary

 

Section Three: Projects in Progress

 

Project InfoProject Manager's Commentary
INF105 (AP45-053)

Decommission Obsolete Infrastructure

Category: Core Funding

 

Milestones

 

30-Jun-2016Windows decommissioning (15-16) completedDeliver
30-Jun-2016RedHat decommissioning (15-16) completedDeliver
30-Jun-2016Solaris decommissioning (15-16) completedDeliver
28-Jul-2016ClosureClose

 

RAG Status/ RAG change during last month

Project status is GREEN.

Report by David Watters for June 2016

Achievements this Period

  • Further monitoring of CF migrations - all now completed
  • Related wiki pages and reports updated
  • All LSA migrations now effected except one (HR - planned for early July)
  • Red Hat & Solaris machines now availble for switching off

Issues

  • Technology Management time limited for work on some migrations

Next Steps

  • Final migrations to be completed
  • Project closure to be drafted and circulated
  • Project to be closed
 

 

INF110 (AP56-004)

Install Oracle 12c

Category: Compliance

 

Milestones

08-Jul-2016Deployment sign-offDeliver
29-Jul-2016Project closureClose

RAG Status/ RAG change during last month

Project status is AMBER (final milestones delayed)

Report by David Watters for June 2016

Achievements this Period

  • Workshop/handover to Production undertaken

Issues

  • Deployment sign-off delayed - documentation to be updated 

Next Steps

  • Completion of handover
  • Final changes to documentation to be made
  • Project closure to be carried out

INF111 (AP56-006)

New SQL Server Database Tier Replacement

Category: Compliance

 

Milestones

26-Aug-2016Closure

 

 

 

 

 

RAG Status/ RAG change during last month

Project status is AMBER

Report by Karen Stirling for  June 2016

 

Achievements in Last Period

  • High level costings provided by XMA for 3 servers (no license costs or VAT / Delivery information provided)
  • Draft TAD updated with information as provided by XMA for host servers
  • ITI review of XMA proposal completed and options provided 
  • Enterprise Edition License costs provided from Microsoft
  • Agreement gained following license position for option 3 to purchase one new server to expand the cluster and the VMware licences for it based on the spec that we use 
  • ITI to request quotes and raising purchase order

Issues

  • ITI have reviewed information provided by XMA, although a formal quote has not been received, 3 options and true associated costs have been provided :
  1. To build a completely separate VMware cluster as per the XMA specification: £73.7K total (not including IS staff costs which would be additional to existing support cost (0.1FTE), storage, backup, networking etc.)
  2. To build a completely separate cluster as per our current environment to offer the usual level of resilience and redundancy: £134.4K total (not including IS staff costs which would be additional to existing support cost (0.2FTE), storage, backup, networking etc.)
  3. To add additional capacity to the existing VM estate: We cannot easily define until we know the required footprint of SQL Server VMs spec & count but from what we know of the existing service, the spec below should provide sufficient initial capacity and is based on 0.5TB of RAM being made available at each site. This would give 36 cores/vCPUs available at each site. If more capacity was required for the service then the physical server specification may need to be increased but this could be done in later years £28.3K total (not including IS staff costs but this would be minimal through existing operational support, storage, backup, networking etc.)
  • Meeting arranged with ITI on 28th June when PM returned from annual leave where it was agreed that ITI Enterprise Manager would discuss MS SQL Licences Enterprise with them to gauge if option 3 would be the preferred option and way forward
  • Closure milestone extended to end of July to await confirmation of Licence position now moved to end of August at Project Sponsor's request
  • There is a risk that project may have to carry forward to August 16/17 if no decision agreed as Project Sponsor is on annual leave for 3 weeks in July and will be unable to sign off project clsoure

Next Steps

  • Agree project closure

 

The project current status is AMBER due to extension of project closure date to accommodate decision around options and licensing

INF113 (AP45-067)

System Monitoring Pilot

Category: Discretionary

 

Milestones

 

29-Jul-2016Recommendations
12-Aug-2016Close

 

RAG Status / RAG change during last month

AMBER

Report by Colin Watt for for June 2016

 

Achievements in Last Period

  • Additional work has been done with SCOM on the linux stack for Learn.
  • Feedback on SquaredUp sample dashboards consolidated for review by project team and wider group.
  • The wider project group met on 28/06/16 to review the additional work agreed at the 15/04/16 meeting.
  • It was agreed that SCOM (with 3rd party tools to improve the out of the box functionality) provided useful information however there was consensus that it could not function as the "single pane of glass" which had been hoped for (see issues below).

 

Issues

The wider group met 28/06/16 to review the work agreed 25/04/16 and after much discussion reached consensus that:

  • SCOM could not be used without 3rd party tools to deal with limitations
  • SCOM (even with 3rd party tools) does not provide sufficient functionality to meet the needs across IS
  • Recommendation will be to not proceed further with SCOM; report will provide rationale from the wider group of Apps and ITI staff and will be completed in July. It is possible the actual closure may be pushed into August but this would only be expected to require 0.5d or less.

 

Next Steps

  • Complete recommendations report.
  • Close Project

 

The project current status is AMBER due to staff availability to complete the recommendations report.

INF115 Python Development Platform Implementation

D

Milestones

Target dateTitle
29-Jul-2016Release 1
19-Aug-2016Closure

RAG Status

AMBER

 

Report by Adam Wadee for June 2016

 

Achievements in Last Period

  • At the end of June, Iteration 9 has been completed.
  • In total, 32 user stories have been completed (99 story points).
  • Resourcing with Software Dev and Dev Tech is progressing well, no conflicts to report.

Issues

  • We have extended the project timeline and increased the budget to allow Release 1 to be completed (see PICCL for more info).

 

Next Steps

  • Continue project into July and complete the required stories for Release 1.

 

Delivery and Closure milestones changed by 1 month, and budget increased making the project RAG Amber.

 

 

INF116 ASTA Upgrade 15/16

C

Milestones

22-Jul-2016TEST Upgrade Complete
05-Aug-2016Testing Complete
29-Aug-2016LIVE Upgrade Complete (Deployment)
16-Sep-2016Deployment Sign Off
26-Sep-2016Project Closure

RAG Status

RED

Report by Nikki Stuart for June 2016

Achievements:

  • Project replanned folowing a minor conflict with Dev Tech that would have pushed the LIVE upgrade to the IS Apps end or year period. 
  • Prep work for the TEST migration underway
  • Discussions with ASTA to agree the TEST and LIVE upgrade dates

Issues:

  • the major milestone changes resulting from an initial conflilct in Dev Tech and then subsequent conflicts with the ASTA admins to mitigate the risk around migrating the LIVE application at the end of July and during the end/start if year activities. - RESOLVED

Next Steps:

  • TEST upgrade
  • UAT 
  • planning for LIVE upgrade

 

Status

Project status has been set to RED to cover the replanning of the project in the last month. There are no outstanding issues and the current RAG status is GREEN. 

 

 

INF118 (AP56-005)

JIRA Upgrade 2016

Category: Compliance

 

Milestones

14-Jul-2016Test config complete
03-Aug-2016Integration testing
05-Aug-2016LIVE config complete
19-Aug-2016Acceptance sign off
05-Sep-2016Delivery
16-Sep-2016Deployment Sign Off Review
23-Sep-2016Closure

 

RAG Status / RAG change during last month

GREEN

 

 

Report by Chris Konczak for for June 2016

 

Achievements in Last Period

  • JIRA DEV configuration complete
  • Data refreshed from LIVE into DEV
  • Replaned into 16/17 year in agreement with sponsor
  • TEST and LIVE environments set up

 

Issues

  •  Issue 4. Milestones have been replanned and days are to be returned to the programme. Delivery date remains the same.

Budget details

  • Effort to complete in 15/16: 18 days
  • Total Effort in 15/16: 50 days
  • Effort to complete in 17/18: 16 days
  • Days to be returned to the 16/16 programme budget: 20 days

 

Next Steps

  • Build and integration sign off
  • Install and configuration on TEST and LIVE

 

The project current status is GREEN.

INF119 (AP56-047)

Service Resilience Capability

Category: Discretionary

 

Milestones

08-Jul-2016Project Brief
30-Nov-2016Delivery
15-Dec-2016Closure

 

RAG Status / RAG change during last month

AMBER

Report by Karen Stirling for June 2016

 

Achievements in Last Period

  • Further planning meeting held on 16th June to understand requirements, deliverables etc. from this project - this to ensure that we have clearly defined and contained scope to take forward.
  • Project brief being updated following meeting and estimates to be provided
  • Identified key stakeholders and candidate applications (Events Booking and Web Central/EBIS Online)

Issues

  • PICCL raised and submitted to WIS to extend the project brief milestone to 08/07/16 as PM on annual leave to  allow estimation and allocation of resource to project to be confirmed, Project Sponsor and Programme Manager advised of change to project brief submission
  • Unlikely to use forecasted resource budget in 15/16

Next Steps

  • Estimation agreed and Resource assigned
  • Project brief approval

The project status is AMBER due to delay in project brief being approved

INF120

Disaster Recovery for Priority Services

Category: Discretionary

 

Milestones

 

15-Jul-2016Initial Priority Services Review
05-Aug-2016DR Document Storage Area ready
21-Oct-2016Priority Services DR Documentation complete
14-Nov-2016Delivery
02-Dec-2016Closure

 

RAG Status / RAG change during last month

GREEN

Report by Karen Stirling for June 2016

 

Achievements in Last Period

  • Commenced Analysis activity to review all applications & components which make up the Top Priority Services (12 in total)
  • Template created to capture relevant information and dash board format produced, currently using this as an Excel spreadsheet via One Drive
  • Identified that there will be services which are currently on old version of Technical Architecture Document – team agreed the project would not transfer to new format at this stage
  • Graeme Wood to be ITI contact for project

Issues

N/A

Next Steps

  • Continue analysis review for Medium Priority Services
  • Review and agree storage options for a master DR document which can be stored off site

The project status is GREEN

INF121

Migrate Core Databases to Oracle 12c

Category: Compliance

 

Milestones

 

19/07/16: Planning

 

RAG Status / RAG change during last month

RED

Report by Chris Konczak for for June 2016

Achievements this Period

  • Brief started

 

Issues

  • Planning milestone moved by one month resulting in project being RED

 

Impact on budget for 15/16 - see Issue 1

  • Total Effort in 15/16: 1 day
  • Previous budget for 15/16: 25 days
  • Revised budget for 15/16: 5 days
  • Days returned to 15/16 programme budget: 19 days
  • Overall budget therefore reduced from 100 days to 81 days for 16/17

 

Next Steps

  • Kick and estimation meeting
  • Brief writeup and estimation
  • Brief sign off meeting  

 

Section Four: Closed or Withdrawn Projects

 

Project InfoProject Managers Commentary

INF108 (AP45-034)

Automated Server Builds

Closure approved 11 September 2015.

INF112 (AP56-007)

Build and Configure new ColdFusion Version [15/16]

Closure approved December 2015

INF114: Implementation of EASE Second Challenge

Closure approved December 2015
INF117 (AP56-005) Bamboo UpgradeClosure approved June 2016

 

 

 