UniDesk Programme Report -April 2013

 

Report compiled by Maurice Franceschi (IS Apps Programme Manager) for UniDesk Project Board

 

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects

 

Section One: Programme Commentary, RAG and Resources Update  

The ITS081 Change and Release project has closed as planned, with C&R work completing under the Upgrade Proejct or as service support work.

The SMI002 UniDesk Upgrade will deliver upgrades to the four universities between late May and late June, as agreed by partners and SHU.

The SMI003 CMDB project has started, with an initial workshop with our partners and TOPdesk scheduled for late June.

The current estimate is showing 11 days over budget, with an overrun of 13 days coming from SMI002.

Programme Manager will review the actuals and estimates to complete with Project Manager and Service Management to ensure the data is up to date and, if there is an overrun, look to the tasks to complete to see if anything can be considered for descope to keep to budget.

Programme Manager will report back to the board on the budget issue w/c 27th May.

 

 

 

Actions from programme meeting

 

 

 

 

 

 

 

 Section Two: Projects Not Started

Project InfoProgramme Manager's Commentary
All projects have started 

 

Section Three: Projects in Progress

Project InfoProject Managers Commentary

SMI003 (AP23-047)

Unidesk CMDB

Funded

Approved funding for 12/13 is 3 days (5 days for Service management). Approved funding for 13/14 is 105 days (45 days for Service management).  

Milestones

30-Sep-2013Terms of Reference

 

RAG Status

GREEN

Report by Maurice Franceschi for April 2013

 

Achievements in Last Period

  •     Project Started

Issues

No issues  

Next Steps  

Workshop with Partners, Colleagues and  TOPdesk on 27th June to scope project.

Milestones

30-Sep-2013Terms of Reference

 

 

  

SMI002 (AP23-406)

TOPdesk Upgrade to v 5

Funded

Approved funding for 12/13 is 105 days (85 days for Applications) - approved 28 March 13.

Milestones

 

15-May-2013Edinburgh Deployment
27-May-2013Sheffield Hallum Deployment
03-Jun-2013Abertay deployment tbc
10-Jun-2013St Andrews deployment tbc
08-Jul-2013Go-Live Complete
22-Jul-2013Deployment Sign-Off
26-Jul-2013Closure

 

 

 

RAG Status

AMBER

 

Report by Maurice Franceschi for April 2013

 

Achievements in Last Period

 

  • Acceptance Sign-Off of Edinburgh Upgrade
  • Agreement on Dates for Delivery for all four institutions

 

Issues

  • Number of actions from the ASOR for Edinburgh - nothing to prevent delivery

Next Steps

  • Deploy Upgrade for each institution over May and June

 

Project is status Amber as we have a projected overrun of 13 days.

Section Three: Closed/Withdrawn Projects

 

Project InfoProject Managers Commentary
  

AP23-017 UniDesk Shared Service Patch

Not Funded

Withdrawn. Work has been done under Service.

ITS081

UniDesk Change & Release

Funded

 

 

Closed

 

 

Actions from October Programme Meeting (9th November)

Annual Planning to be approved by Project Board, but we propose CMDB carry over Card Reader, sponsored by Bryan, funding could be core or partners if not Edinburgh specific, small UPortal, sponsored by Bryan, core funding, Edinburgh specific, small  Done 
Maurice and Stefan to meet with projects soon to discuss C&RDone 
   

 

Actions from September Programme Meeting (5th October)

Neil Bruce can be C&R Process Manager in UniDesk if Stefan or David cannot take on the role.

Bryan to dicuss with Neil - Maurice to confirm with Stefan and David

Resolved - Robert Gormley

 

 
The current unidesk user group would be a good forum to present C&R changesStuart to action 
   

 

Actions from August Programme Meeting (14th September)

Set up meeting to discuss how to promote CABSMauriceDone
C&R project will not set up CABSMauriceDone  
Get V 5 Upgrade project started asapMauriceDone

 

 