Organisation

 

Work/Task Breakdown

ColdFusion Upgrade

  • DevTech: will update TAD, create DEV, TEST and LIVE and will liaise with Unix team for server set up

  • Dev: will ensure DEV and TEST are fit for use - that testing can be carried out end to end

  • Dev will create the Bamboo Plan, prepare code for upgrade to CF11, check in environments

  • Dev: will carry out any rework at any of the stages

  • Apps Management: will test when application is in TEST

  • USD: will complete user acceptance testing in TEST

  • All teams will be involved in handovers

Moving XPR SQL server database from MIS-FORD to an new SQL server instance

  • DevTech: will update TAD, create DEV, TEST and LIVE on new server instance and will liaise with Unix team for server set up
  • DevTech: lift XPR database out of the shared SQL Server instance on Ford and move to new server
  • Dev: repoint the XPR components to the new database
  • Dev:repoint the cold fusion application to the new database

 