Actions for Complex Migrations (Completed)
Actions for the various work packages
Actioned by | Description | Date | Status |
Simple Hosting Migrations | |||
Maurice | check with Stewart Cromar in two weeks that no issues have been raised as a result | on 21/4 | Done |
Gary | Shut down server 19 | After 21/4 | Done |
Maurice | Update Milestone for Delivery | on 21/4 | Done |
Server Design and Build | |||
Alister | Get TAD reviewed by Dev Tech, Heather, Gary Scobie | 10th April | Done |
Alister | SQL Server on Linux has been agreed | 10th April | Done |
Requests in to Architecture to build servers - 4 sets for WINWBAT, COLLMED, EEMEC and CMVMEXAM. Live and Test for each, with backup servers KB/AT | w/c 13th April | Done | |
Alister | Confirm to Matt when kit is ready for Test migration | end of April | Done |
cPanel Migrations (Linux) | |||
Matt | cPanel migrations | End of April | Done |
Matt | Communcations and Sign-Off with Service Owners | End of April | Done |
Maurice | contact Alain Forrester about getting more CPanel accounts | 10/4 | Done. More cPanel available no problem, |
IS Infrastructure Migrations | |||
Maurice and Alister | Meet with Heather to discuss permissions for Matt | w/c 13/4 | Done |
Matt | record all migration actions so that Tech Mgmt can follow these through on Live | Through May | Done |
Matt | Communications and Sign-Off with Service Owners/Stewart Cromar - LIVE Migration | starting 24/9 | |
Plesk Migrations (Windows) | |||
Maurice | Update from COM014 project to see if we can migrate earleir than Sept/Oct | ongoing | Done |
Matt | Communications and Sign-Off with Service Owners/Stweart Cromar - LIVE Migration | starting 1/10 | pending |
Matt | If we cannot move HME and ICONZAFRICA sites due to .Net then we will move these to WINWEBAT | to review at the time | |
Other Work | |||
Fernando | Migrate Adobe material on Forth to Waverley that is referred to by eeMec | April | Done |
Maurice | Given a Plesk account I think Alan Gilchrist will port the site over. AG needs to check dependencies of EEVeC on room booking DB. | April/May | Done |
Maurice | Maurice to discuss with Paul Clark if he can fund the £175 for the Little France Post-Doc Society website which will move to CPanel | April | Done |
Gary | Anatomy Museum site needs to move - to cPanel | May | |
Maurice | needs to confirm with Paul Clark a date when we can migrate the CMVMEXAM | April | not an issue now |
Gary and Matt | a list of Support Activities - where infrastructure will be need to support Developer work e.g. VLE rollover | May | Done |
Fernando | Vet VM access for Antony Davies | meeting 17/8 | |
Gary | to confirm that the Config DB material is not required | April/May | Done |