- Initial feedback received from potential consultant
- Meeting with Project Sponsor and Acting Estates Assistant Director to discuss the representtaives on the
- overall project board
- project team
- Meeting with Energy project team and potential consultant to outline basic project requirements.
- Subsequent feedback to be provided to UoE
You’re right about FP Recs, I‘ll just get Martin to migrate these together.
For eStores I am hoping this will take less than the others as in theory it should just be about altering the current plan to point to the new servers and then deploy.
Application | Project | Start Date | Developer | Notes |
Salary Forecasting | FIN110 | 15/02/2015 | Gavin |
|
eStores | FIN110 | 02/02/2016 | Greg | Already Deployed via Bamboo |
WebFirst | FIN110 | 01/02/2016 | Jonny |
Build Documents drafted for each application - Build Records to be reviewed
3 to 4 days effort required to complete environment set-up
6 instances needed - Dev x 2, Test x 2, Live x 2
Will look into what's required for CMDS task
Will check with Riky and Mark on number of TADs needed - just append the CF TAD or update TAD for each Finance application
Report prepared by Nikki Stuart (IS Apps Programme Manager) for Terry Fox (Programme Owner)
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
To obtain a blank persona template (MSPowerpoint format), click on the link below which will open a read-only view. This can then be saved to your local machine (using 'Save As') and edited as required.
The edited document should then be uploaded to this page.