Report for May 2018
- Report Date
- May 2018
Achievements in Last Period
- Both a second attempt to upgrade PMP on LIVE and a subsequent upgrade to a clone of LIVE failed. Failure logs have been sent to the Supplier for comment. Risk #4: Failure to Deploy Upgrade to Password manager Pro (PMP) to LIVE (AMBER) is tracking this situation.
- Bamboo build has been signed off and is due to be deployed 07/06/2018 to LIVE
- Upgrades underway to Sentry, Nexus and Python
Issues
- None
Next Steps
- Attempt another upgrade to PMP on a cloned instance, based on feedback from Suppliers and promote to LIVE (date TBC, but 21/06/2018 is targetted)
- Complete upgrades to Sentry, Bamboo, Python and Nexus
Milestones
These were approved at WIS 06/04/2018:
02-Apr-2018 PMP Build / Acceptance Sign Off
09-Apr-2018 PMP Deployed / Sign Off
17-Apr-2018 Sentry Build / Acceptance Sign Off
07-May-2018 Bamboo Build / Acceptance Sign Off
14-May-2018 Python Build / Acceptance Sign Off
14-May-2018 Bamboo Deployed / Sign Off
21-May-2018 Python Deployed / Sign Off
04-Jun-2018 Nexus Build / Acceptance Sign Off
06-Jun-2018 Nexus Deployed / Sign Off
06-Jul-2018 Over All Build / Acceptance Sign Off
13-Jul-2018 Overall Deployment / Sign Off
23-Jul-2018 Closure
Project Sponsor Commentary / Approval
- Approved budget
- 110.0 days
- Activity this month
- 29.3 days
- Activity this year
- 75.4 days
- Activity to date
- 74.4 days
- Estimate to complete current year
- 26.3 days
- Estimate to complete future years
- 0.0 days