Report for July 2016

Report Date
July 2016

Achievements in Last Period

  • Final development iteration completed
  • Final deployment successfully delivered

Issues

  • An issue with deployment continued to cause problems, the deployment was moved out one week. The issue has now been fixed.

Next Steps

  • Completer oll back work
  • Move to closure
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
171.0 days
Activity this month
5.0 days
Activity this year
167.0 days
Activity to date
167.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
3.0 days

Project Info

Project
EdWeb Additional Requirements
Code
UWP011
Programme
Z. ISG - University Website (UWP) (Closed)
Management Office
ISG PMO
Project Manager
Tim Gray
Project Sponsor
Stratos Filalithis
Current Stage
Close
Status
Closed
Start Date
11-Nov-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
n/a