Report for June 2016

Report Date
June 2016

Achievements in Last Period

  • Final development iteration prepared, estimated and started
    • To maximise deliver and allow time for STAGING investigations, final iteration will have a three week duration and be deployed to LIVE in July

Issues

  • An issue with deployment has occurred, a fix is ready for deployment to STAGING
  • The final deployment will be moved to 18/07/16 to allow time for resolution of the issue on STAGING

Next Steps

  • Complete iteration and deploy to LIVE
  • Move to closure
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
171.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
EdWeb Additional Requirements
Code
UWP011
Programme
Z. ISG - University Website (UWP) (Closed)
Management Office
ISG PMO
Project Manager
Tim Gray
Project Sponsor
Stratos Filalithis
Current Stage
Close
Status
Closed
Start Date
11-Nov-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
n/a