Report for June 2016
- Report Date
- June 2016
Achievements in Last Period
- Final development iteration prepared, estimated and started
- To maximise deliver and allow time for STAGING investigations, final iteration will have a three week duration and be deployed to LIVE in July
Issues
- An issue with deployment has occurred, a fix is ready for deployment to STAGING
- The final deployment will be moved to 18/07/16 to allow time for resolution of the issue on STAGING
Next Steps
- Complete iteration and deploy to LIVE
- Move to closure
- Approved budget
- 171.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days