Report for March 2016

Report Date
March 2016

Achievements in Last Period

  • Iteration 3 deployed to LIVE
  • Iteration 4 started 
  • Requirements completed and estimaated for staff profiles

Issues

  • No significant issues to report

Next Steps

  • Comeplte iteration 4
  • Start iteration 5
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
171.0 days
Activity this month
23.0 days
Activity this year
115.0 days
Activity to date
115.0 days
Estimate to complete current year
66.0 days
Estimate to complete future years
0.0 days

Project Info

Project
EdWeb Additional Requirements
Code
UWP011
Programme
Z. ISG - University Website (UWP) (Closed)
Management Office
ISG PMO
Project Manager
Tim Gray
Project Sponsor
Stratos Filalithis
Current Stage
Close
Status
Closed
Start Date
11-Nov-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
n/a