Report for September 2016
- Report Date
- September 2016
Achievements in Last Period
- Roll back work progressed
- Final milestones replanned
Issues
- Thr roll back work has been hampered by the assigned developer attending Pythoin training. It is still expected to finished and deployed as scheduled at the end of next month
Next Steps
- Complete and deploy roll back
- Finally move to closure
- Approved budget
- 171.0 days
- Activity this month
- 2.0 days
- Activity this year
- 4.0 days
- Activity to date
- 171.0 days
- Estimate to complete current year
- 5.0 days
- Estimate to complete future years
- 0.0 days