Report for September 2016

Report Date
September 2016

Achievements in Last Period

  • Roll back work progressed
  • Final milestones replanned

Issues

  • Thr roll back work has been hampered by the assigned developer attending Pythoin training. It is still expected to finished and deployed as scheduled at the end of next month

Next Steps

  • Complete and deploy roll back 
  • Finally move to closure
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
BLUE
Change Status
Activity
Approved budget
171.0 days
Activity this month
2.0 days
Activity this year
4.0 days
Activity to date
171.0 days
Estimate to complete current year
5.0 days
Estimate to complete future years
0.0 days

Project Info

Project
EdWeb Additional Requirements
Code
UWP011
Programme
Z. ISG - University Website (UWP) (Closed)
Management Office
ISG PMO
Project Manager
Tim Gray
Project Sponsor
Stratos Filalithis
Current Stage
Close
Status
Closed
Start Date
11-Nov-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
n/a