Report for August 2016
- Report Date
- August 2016
Achievements in Last Period
- Roll back work scheduled and started
Issues
- No issues to report
Next Steps
- Complete and deploy roll back
- Move to closure
- Approved budget
- 171.0 days
- Activity this month
- 1.0 day
- Activity this year
- 1.0 day
- Activity to date
- 168.0 days
- Estimate to complete current year
- 10.0 days
- Estimate to complete future years
- 0.0 days