Meeting Minutes 15/11/2013

_____________________________________________ From: CONLON Stephen Sent: 15 November 2013 14:11 To: DARBY Bruce; FILALITHIS Stratos; GRAY Tim; FORREST Colin Subject: UWP007 and UWP008 Meetings Minutes.

 

 

Guys, a quick recap of our meeting to-day. Ongoing , I will add minutes to the journal section of the project and send on links . Please feel free to comment .

 

UWP008 - POLO Database Upgrade

Database upgrade will move the POLO database to the new database architecture infrastructure resulting in a small increase in budget but within the annual planning estimate . The brief  will be completed w/e 22/11.

 

UWP007 - Polopoly CMS Upgrade

 In addition to upgrading Polopoly to version 10, the project will now assume responsibility for the Polopoly front end server upgrade.

The investigations have been ongoing into the Polopoly 10 upgrade and the resulting estimate from development suggests some substantial effort will have to  be applied. 

This estimate will be clarified to determine what the days cover namely

1. Is the estimate  for the development install effort ?

2. If yes what is the effort to install on TEST and consequently LIVE.

3. The document mentions further developer effort may be needed (P3). This needs clarified and estimated.

4. Does the estimate include the creation of new deployment instructions to include, for example, how to configure the legacy  Lucerne search mentioned on Page 1.

 

Geir and Mairi's time to be discussed with their resource manager  - Stevie to follow up with resource Manager.

 

Investigations have been ongoing this week as to the compatibility of Polopoly with our proposed  standard new servers. This is planned to complete this week Action . Stevie to follow up with the Dev Tech team.

 

A planning and resource meeting is scheduled for Monday to firm up estimates and requirements ,  brief expect to complete w/e 22/11.

 

Determine whether layout of Brief is acceptable or should it be presented in tabular form - Bruce.

 

UWS004

UWS004 will deploy to LIVE as planned on the 03/12. It has been determined that the new search  does not compile with Polopoly 10 and some time will be planned into UWP007 to ensure the effort to address the issue can be sized. If the effort proves to be too costly the UWS004 changes can be rolled back.

 

Stratos to review document and determine whether he needs to see Polopoly 10 on the local install or wait until the Dev rollout which will be January at the earliest - Stratos.

 

General

The Comms to the wider Polopoly community will be handled by the UWP team . UWP will determine what and when to communicate including ,but not exclusively,  what is communicated as regards the new look and feel and what training may be required . The UWP comm's preparation and timing will be added to the projects schedule and plan to ensure it coincides with the technical deliverable milestones.  - Stratos/Bruce.

 

General testing effort which covers all detailed test scripts is estimated at 50 hours duration by UWP. Some of the testing effort may be split over different environments but this will be in the plan we agree-  Bruce/Stratos/ Stevie

 

Book regular project meeting Friday morning at DL as this seems to suit. Potential for bacon rolls also - Stevie

 

Add technical risks to projects to review - Stevie

 

 

Best regards.

 

Stevie Conlon

Project Manager/Business Analyst

Project Services

0131 6514543

07973498371

Project Info

Project
Polopoly Database Upgrade to 11g and Web Server Replacement
Code
UWP007
Programme
Z. ISG - University Website (UWP) (Closed)
Project Manager
Tim Gray
Project Sponsor
Dawn Ellis
Current Stage
Close
Status
Closed
Start Date
06-Sep-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
27-Jun-2014
Category
Compliance