Meeting Minutes 15/11/2013
_____________________________________________ From: CONLON Stephen Sent: 15 November 2013 14:11 To: DARBY Bruce; FILALITHIS Stratos; GRAY Tim; FORREST Colin Subject: UWP007 and UWP008 Meetings Minutes.
Guys, a quick recap of our meeting to-day. Ongoing , I will add minutes to the journal section of the project and send on links . Please feel free to comment .
UWP008 - POLO Database Upgrade
Database upgrade will move the POLO database to the new database architecture infrastructure resulting in a small increase in budget but within the annual planning estimate . The brief will be completed w/e 22/11.
UWP007 - Polopoly CMS Upgrade
In addition to upgrading Polopoly to version 10, the project will now assume responsibility for the Polopoly front end server upgrade.
The investigations have been ongoing into the Polopoly 10 upgrade and the resulting estimate from development suggests some substantial effort will have to be applied.
This estimate will be clarified to determine what the days cover namely
1. Is the estimate for the development install effort ?
2. If yes what is the effort to install on TEST and consequently LIVE.
3. The document mentions further developer effort may be needed (P3). This needs clarified and estimated.
4. Does the estimate include the creation of new deployment instructions to include, for example, how to configure the legacy Lucerne search mentioned on Page 1.
Geir and Mairi's time to be discussed with their resource manager - Stevie to follow up with resource Manager.
Investigations have been ongoing this week as to the compatibility of Polopoly with our proposed standard new servers. This is planned to complete this week Action . Stevie to follow up with the Dev Tech team.
A planning and resource meeting is scheduled for Monday to firm up estimates and requirements , brief expect to complete w/e 22/11.
Determine whether layout of Brief is acceptable or should it be presented in tabular form - Bruce.
UWS004
UWS004 will deploy to LIVE as planned on the 03/12. It has been determined that the new search does not compile with Polopoly 10 and some time will be planned into UWP007 to ensure the effort to address the issue can be sized. If the effort proves to be too costly the UWS004 changes can be rolled back.
Stratos to review document and determine whether he needs to see Polopoly 10 on the local install or wait until the Dev rollout which will be January at the earliest - Stratos.
General
The Comms to the wider Polopoly community will be handled by the UWP team . UWP will determine what and when to communicate including ,but not exclusively, what is communicated as regards the new look and feel and what training may be required . The UWP comm's preparation and timing will be added to the projects schedule and plan to ensure it coincides with the technical deliverable milestones. - Stratos/Bruce.
General testing effort which covers all detailed test scripts is estimated at 50 hours duration by UWP. Some of the testing effort may be split over different environments but this will be in the plan we agree- Bruce/Stratos/ Stevie
Book regular project meeting Friday morning at DL as this seems to suit. Potential for bacon rolls also - Stevie
Add technical risks to projects to review - Stevie
Best regards.
Stevie Conlon
Project Manager/Business Analyst
Project Services
0131 6514543
07973498371