Current status w/c 11/11
Project has been delayed due to resource unavailability to investigate the Polopoly version upgrade. Polopoly 10 has been decided upon but it will require a local install before estimates can be firmed up. This is now in progress.
- It has been recommended by Tech Management that this project and the follow on project to upgrade the front end web severs be done together to save time and effort. This has been discussed and agreed with the program manager and communicated to UWP team.
- Scope change submitted to WIS and approved this week.