Report for December 2019
- Report Date
- December 2019
Achievements this period
- Project planning completed and signed off.
- Project manager confirmed as Ken Miller.
- New SDB for 20/21 built from the spf export file.
- 20/21 Medical School Resource Booker delivered.
- Book initial IS Apps resources in ASTA for 19/20 tasks.
Issues
- First task for TTU020 rollforward - creation of new SDB for 20/21 was delayed due to strike action but completed during December.
Next Steps
- Confirm IS Apps resources in ASTA for 19/20 tasks.
- Review and co-ordinate tasks for 20/21 database for the Web applications ( WRB and Web Timetables).
- Approved budget
- 145.0 days
- Activity this month
- 7.1 days
- Activity this year
- 9.2 days
- Activity to date
- 9.2 days
- Estimate to complete current year
- 115.0 days
- Estimate to complete future years
- 24.0 days