Report for Nov 2019
- Report Date
- November 2019
Achievements this period
- Project planning in-progress
- Project manager changed from Victoria Weinsberg to Ken Miller
Issues
- First task for TTU020 rollforward - creation of new SDB for 20/21 is delayed due to strike actionÂ
Next Steps
- Complete end of Planning
- Build new SDB for 20/21 from the spf export file
- Book IS Apps resources in ASTA for 19/20 tasks
- Approved budget
- 145.0 days
- Activity this month
- 0.5 days
- Activity this year
- 0.6 days
- Activity to date
- 0.6 days
- Estimate to complete current year
- 115.0 days
- Estimate to complete future years
- 10.0 days