Report for Oct 2019
- Report Date
- October 2019
Achievements this period
- Project started
Issues
- Planned Project Manager (Victoria Weinsberg) now not available as she have moved to SEP core systems for next 3 months , PM cover will be provided by Ken Miller for next 6 weeks, until Project Services have recruited a new start
Next Steps
- Complete end of Planning
- Book IS Apps resources in ASTA
- Approved budget
- 185.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 185.0 days
- Estimate to complete future years
- 0.0 days