Report for August 2016
- Report Date
- August 2016
Achievements this period
- Main roll-forward tasks completed as planned on 8/8/16 and signed off by business
- New BI reports delivered to LIVE (15/16) and signed off by business
- BI reports rolled forward to 16/17
- post-deployment performance BI issues resolved and BI reports signed off by business
Issues
- Bookable rooms decomissioning tasks raised by support yet to be completed
- TAD not yet signed off
- Budget exceeded by 30 days
- Closure milestone missed
Next Steps
- Agree new budget with programme manager and sponsor
- Agree new closure milestone and close
Milestones
29-Aug-2016 | Close |
RAG Status
The project RAG status is RED as the closure milestone has been missed and the budget exceeded.
- Approved budget
- 176.0 days
- Activity this month
- 31.0 days
- Activity this year
- 31.0 days
- Activity to date
- 205.0 days
- Estimate to complete current year
- 5.0 days
- Estimate to complete future years
- 0.0 days