Report for July 2016

Report Date
July 2016

Achievements this period

  •  new BI reports signed off in TEST 15/16
  • existing BI reports rolled forwad in DEV, TEST and LIVE
  • LEARN building block rolled forward in LIVE
  • PADS, OneLan, MyED and URL August roll-forward carried out in TEST

Issues

 

Next Steps

  • Deploy BI reports to LIVE 15/16 and sign off
  • Roll-forward BI reports in TEST and LIVE and sign off
  • Carry out August roll-forward tasks

Milestones

14-Jul-2016BI reports delivery in 15/16
08-Aug-201616/17 academic year and project WRAP
15-Aug-2016BI reports roll-forward
29-Aug-2016Close

 

RAG Status

The project RAG status is AMBER as the BI reports are yet to be delivered into LIVE

Project Status
RAG Status
Time
AMBER
Cost
AMBER
Scope
GREEN
Overall
AMBER
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Timetabling Service Annual rebuild and Roll-Forward to 16/17
Code
TTU012
Programme
Timetabling (TTU)
Management Office
ISG PMO
Project Manager
Morna Findlay
Project Sponsor
Scott Rosie
Current Stage
Close
Status
Closed
Start Date
18-Sep-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
07-Oct-2016
Programme Priority
1
Overall Priority
Higher
Category
Compliance