Report for July 2016
- Report Date
- July 2016
Achievements this period
- new BI reports signed off in TEST 15/16
- existing BI reports rolled forwad in DEV, TEST and LIVE
- LEARN building block rolled forward in LIVE
- PADS, OneLan, MyED and URL August roll-forward carried out in TEST
Issues
- Bookable rooms decomissioning tasks raised by support which were not identified in planning
- PAS roll-forward in TEST not yet signed off
- Budget exceeded by 8 days
Next Steps
- Deploy BI reports to LIVE 15/16 and sign off
- Roll-forward BI reports in TEST and LIVE and sign off
- Carry out August roll-forward tasks
Milestones
14-Jul-2016 | BI reports delivery in 15/16 |
08-Aug-2016 | 16/17 academic year and project WRAP |
15-Aug-2016 | BI reports roll-forward |
29-Aug-2016 | Close |
RAG Status
The project RAG status is AMBER as the BI reports are yet to be delivered into LIVE
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days