Report for May 2015
- Report Date
- May 2015
Achievements in Last Period
- Login issue cause identified
- ITI added new certificate to central auth servers
- login issue solution tested and confirmed resolved
- project closure review held
Issues
- No known issues
Next Steps
- Proceed to closure
Milestones
| 04-May-2015 | Resolve login issue |
| 01-Jun-2015 | Close Project |
Project status is GREEN as the project can now close.
- Approved budget
- 60.0 days
- Activity this month
- 5.0 days
- Activity this year
- 58.0 days
- Activity to date
- 58.0 days
- Estimate to complete current year
- 1.0 day
- Estimate to complete future years
- 0.0 days