Report for March 2015

Report Date
March 2015

Achievements in Last Period

  • Proposal for new approach to providing new version of timetabling software discussed and agreed by support, the project team and  the project sponsor 
  • New aproach estimated
  • "Login" issue progressed with Scientia

 

Issues

  • "Login" issue still not resolved  ( key resources on leave) this must be resolved before  work on an upgraded version can begin.

Next Steps

  • resolve login issue with Scientia
  • Agree  new plan for delivering a  LIVE 3.11 ( or 3.12) environment with  project sponsor 
  • Transfer unused effort to programme

 

Milestones

To be confirmed 

 

Project status is AMBER as the effort required to resolve the login issue is uncertain and therefore the  closure milestone cannot be agreed.

Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
Change Status
Activity
Approved budget
80.0 days
Activity this month
16.0 days
Activity this year
49.0 days
Activity to date
49.0 days
Estimate to complete current year
11.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Timetabling Scientia Upgrade
Code
TTU009
Programme
Timetabling (TTU)
Project Manager
Morna Findlay
Project Sponsor
Scott Rosie
Current Stage
Close
Status
Closed
Start Date
28-Oct-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
05-Jun-2015