Organisation
Methodology Compliance
Methodology Stage | Standard Stage Sign-Off | Project Approach |
Planning | Approval by Project Manager, Project Sponsor and IS Applications Management Team (WIS) | The project will produce a product plan, associated tasks, estimates and schedule for the project. Interdependencies with concurrent Timetabling projects will be identified and accommodated. Project processes including risk management will be established. Project governance will be in line with wider Timetabling programme. |
Business Analysis | Peer Project Analysis Review (PPAR) | Business analysis will focus on gap analysis - comparing the existing and new versions of Enterprise, including an understanding of the issues resolved in this version, and producing the test cases for UAT. |
System Analysis & Design | Peer Project Design Review (PPDR) | Systems analysis will include an assessment of the technological changes delivered by this new version. Options for any changes to a SQL Server desktop application will be included in this stage. |
Build | Peer Project Build Review (PPBR) | This will be a sign-off to agree that the applications can be upgraded successfully in the Development Environment by following the build document. |
Integration | Peer Project Integration Review (PPIR) | The integration phase will load testing of the web application. Integration with the Reporting Database and web applications will be tested in this stage. |
Acceptance | Acceptance Sign-Off Review (ASOR) | Timetabling Unit will test the applications with regards to users' business processes. |
Deployment | Deployment Sign-Off Review (DSOR) | Deployment of the upgraded applications to the Live environment. |
Closure | Closure Review and Approval by Project Manager, Project Sponsor and IS Applications Management Team | Closure report and business partner sign-off. |
Project Cost Estimates
All costs are 13/14 with no additional service delivery costs resulting from this project.
| Team | Effort (Days) | Cost (GBP) |
| IS Applications | 93 | £25,110 |
| Timetabling Unit | 20 | £5,400 (nominal cost) |
Please see estimate log for further details.
Dedicated Project Team
There is no requirement for a dedicated project team.
Out of Hours Working
There is no requirement for out of hours working in delivery of this project.
Additional Information
N/A