Report for June 2019
- Report Date
- June 2019
Achievements in Last Period
- Learn TEST upgraded to Learn Q4 2018 and Oracle database patched, testing of the upgraded environment ongoing.
- Security scan carried out on learn TEST.
- Relevant resources secured for July if Learn upgrade has to be carried out on Live self-hosted Learn, in case of issues with deployment to Cloud (TEL058 project)
Issues
- No issues.
Next Steps
- Testing on TEST Learn to be completed.
- Decision to be made if this project will be made live depending on how Learn's migration to the Cloud goes.
- Approved budget
- 50.0 days
- Activity this month
- 8.0 days
- Activity this year
- 0.0 days
- Activity to date
- 22.3 days
- Estimate to complete current year
- 10.0 days
- Estimate to complete future years
- 3.3 days