Impact

Priority and Funding

Normal Priority

Core Funded

Estimates (95% confidence) 75 days.

 

Impact and Dependencies

 

  • The deployment must occur in the summer window before the start of session change freeze
  • The go-live date will be negotiated with the user community: user community work patterns must be taken into consideration, as well as any crossover with the annual Learn upgrade
  • Dependencies on plugins from other providers being ready

Project Risks

Ref Title Initial Risk Current Risk Status Management Approach Risk Owner Date of Last Review
1 Reputation GREEN GREEN Open Retain Mark Findlay 12-Feb-2019
2 Schedule GREEN GREEN Open Reduce Colin Watt 12-Feb-2019
3 Decision on version of Moodle RED GREEN Open Reduce Mark Findlay 12-Feb-2019
4 Theme GREEN GREEN Open Retain Mark Findlay 12-Feb-2019

Project Info

Project
Moodle Upgrade
Code
TEL059
Programme
ISG - Technology Enhanced Learning (TEL)
Management Office
ISG PMO
Project Manager
Colin Watt
Project Sponsor
Karen Howie
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
14-Jan-2019
Planning Date
15-Feb-2019
Delivery Date
02-Jul-2019
Close Date
02-Aug-2019
Programme Priority
2
Overall Priority
Normal
Category
Compliance