Organisation

Resources, Skills and Costs

LTW are providing resources for Senior User and Business Lead roles.

IS Applications are providing Project management, Business Analyst, Software Development, Development Technology, Production Management and Service Management resources from the agreed funding.

Blackboard PM will be assigned to the project and Blackboard will be responsible for data migration to SaaS.

Project Governance

Governance will be provided by the Project Team and a Project Board which is to be established.  PMO will provide project Quality Assurance.

Project Stakeholders

Name                                      Role                                                     Business Area

Anne-Marie Scott                    Project Sponsor                                   DLAM

Karen Howie                           Senior User                                              DLAM             

Steph Hay                                Business Lead                                         DLAM

Dave Berry                              Senior Supplier                                       IS Apps

Andrew Gleeson                     Application Management Lead      IS Apps

Geir Granum                           Software Dev Services Lead              IS Apps

Mark Lang                               Development Technology Lead       IS Apps

Chris Cord                               Technology Management Lead        IS Apps                        

Susan Cooke                            Service Management                         IS Apps

Colin Watt                               Programme Manager                            IS Apps                        

Sonali Nakhate                        Project Manager                                   IS Apps            

 

Project Estimations

See the estimations log.

 

Project Info

Project
Learn to the Cloud
Code
TEL058
Programme
ISG - Technology Enhanced Learning (TEL)
Management Office
ISG PMO
Project Manager
Karen Beggs
Project Sponsor
Karen Howie
Current Stage
Execute
Status
In Progress
Project Classification
Grow
Start Date
01-Oct-2018
Planning Date
16-Nov-2018
Delivery Date
31-Jan-2020
Close Date
14-Feb-2020
Programme Priority
2
Overall Priority
Normal
Category
Discretionary

Documentation

Plan