Organisation

Work/Task Breakdown

Planning  Planning  Project Services
  Sign Off IS Apps
  Sign Off DLAM
     
Analysis Review Release notes and Forums Software Development
  Review Release notes and Forums DLAM
  BRD DLAM
  Sign off IS Apps
  Sign off DLAM
     
Design System Design Spec Software Development
  Implementation Plan Software Development
  Assessment of Plugins DLAM
  Review Implementation Plan DLAM
  TAD Updates Development Technology
  Review TAD Technology Management
  Check the Moodle Data Feed and recommend a course of action.  DLAM
  Sign off IS Apps
  Sign off DLAM
     
Build  Refresh Dev Data from Live Dev Tech
  Update Moodle in DEV Dev Tech
  Check Moodle In DEV including o365 Config Software Development
  Check Moodle In DEV including o365 Config DLAM
  Boost Theme Build Software Development
  UAT Documentation including Benchmark Tests DLAM
  Sign Off IS Apps
  Sign Off DLAM
     
Integration Refresh TEST data from Live and Upgrade Moodle Dev Tech
  Upgrade Moodle in TEST Dev Tech
  Complete Benchmark Tests Dev Tech
  Apply the Boost Theme and Check Moodle In TEST Software Development
  Check Moodle In TEST DLAM
  Sign Off IS Apps
  Sign Off DLAM
     
Acceptance Capacity check after benchmark tests Dev Tech
  UAT DLAM
  UAT Support Applications Management/Technology Management
  JIRAs Software Development/Development Technology
  JIRAs DLAM
  Deployment Checklist Application Management/Technology Management
  Handover to production All Teams
  Sign Off IS Apps
  Sign Off DLAM
     
Deployment User guide updates and additions DLAM
  Deploy to LIVE Dev Tech
  Review Deploy to Live DLAM
  Sign Off IS Apps
  Sign Off DLAM
     
Closure Closiing Sign Off IS Apps
  Closiing Sign Off DLAM

 

Resources, Skills and Costs

At the planning stage we estimate the following.

IS Applications: 50 Days

DLAM: 30 Days

This is on the assumption that IS Applications development will build the new theme.

 

 

Project Info

Project
Annual Moodle Upgrade
Code
TEL045
Programme
ISG - Technology Enhanced Learning (TEL)
Management Office
ISG PMO
Project Manager
Karen Stirling
Project Sponsor
Josephine Kinsley
Current Stage
Close
Status
Closed
Start Date
06-Feb-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
25-Aug-2017
Overall Priority
Normal
Category
Compliance