Report for November 16

Report Date
November 2016

Achievements

  • Closure was approved by the project team by 21 November and submitted to WIS 25 November

 

Issues

  • Stakeholders and interested parties who replied were happy with the closure report and moving the project to closure. WIS rejected closure and asked for meeting to review lessons learned. They have since agreed that the meeting can take place after closure and have agreed closure.  

 

Next Steps

  • An internal meeting to agree the lessons learned wording in the closure report

 

 

Project Status
RAG Status
Overall
BLUE
RAG Commentary
WIS asked for meeting to reword lessons learned - due to other priorities the meeting will be scheduled when senior managers are free
Change Status
Activity
Approved budget
40.0 days
Activity this month
3.0 days
Activity this year
32.0 days
Activity to date
41.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
TEL039 WebPA Migration
Code
TEL039
Programme
ISG - Technology Enhanced Learning (TEL)
Management Office
ISG PMO
Project Manager
Sue Woodger
Project Sponsor
Anne-Marie Scott
Current Stage
Close
Status
Closed
Start Date
13-Jun-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
03-Feb-2017
Overall Priority
Normal
Category
Discretionary