Report for September 16
- Report Date
- September 2016
Achievements
- Security fixes completed and build signoff completed on 12 September. There was an issue with the LTI connector which was fixed and application moved into Test on 14 September
- UAT sign off completed on 19 September
- OLA review held on 26 September – Ana updating with small changes
Issues
- Move to Live was scheduled for 20 September but a last minute discovery by LTW that an assessment was taking place 21 September to 4 October meant that we put the go-live back to 5 October. Further iissues with the LTI connection meant deployment will again be delayed until 12 October.
Next Steps
- Deployment set for 12 October
- OLA to be agreed between all parties
- Close by 4 November
Milestones
| 12-Oct-2016 | Deploy to Live |
| 12-Oct-2016 | Synch live data |
| 26-Oct-2016 | DSOR |
| 4-Nov-2016 | Close |
Project is Green
- Approved budget
- 31.0 days
- Activity this month
- 3.0 days
- Activity this year
- 19.0 days
- Activity to date
- 22.5 days
- Estimate to complete current year
- 2.5 days
- Estimate to complete future years
- 0.0 days