Report for September 16

Report Date
September 2016

Achievements

  • Security fixes completed and build signoff completed on 12 September. There was an issue with the LTI connector which was fixed and application moved into Test on 14 September
  • UAT sign off completed on 19 September
  • OLA review held on 26 September – Ana updating with small changes

 

Issues

  • Move to Live was scheduled for 20 September but a last minute discovery by LTW that an assessment was taking place 21 September to 4 October meant that we put the go-live back to 5 October. Further iissues with the LTI connection meant deployment will again be delayed until 12 October.

     

Next Steps

  • Deployment set for 12 October
  • OLA to be agreed between all parties
  • Close by 4 November

Milestones

12-Oct-2016Deploy to Live
12-Oct-2016Synch live data
26-Oct-2016DSOR
4-Nov-2016Close

Project is Green

Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
31.0 days
Activity this month
3.0 days
Activity this year
19.0 days
Activity to date
22.5 days
Estimate to complete current year
2.5 days
Estimate to complete future years
0.0 days

Project Info

Project
TEL039 WebPA Migration
Code
TEL039
Programme
ISG - Technology Enhanced Learning (TEL)
Management Office
ISG PMO
Project Manager
Sue Woodger
Project Sponsor
Anne-Marie Scott
Current Stage
Close
Status
Closed
Start Date
13-Jun-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
03-Feb-2017
Overall Priority
Normal
Category
Discretionary